About this file
This Schedule B Pricing Matrix document is a proposal form for the State of Michigan's Graffiti Removal Contract for the Taylor TSC. The contract encompasses three primary service categories: Performance-Based Graffiti Abatement on a monthly basis over 36 months, High Priority Removal services measured in square feet with a quantity of 10,000 square feet, and As-Needed Graffiti Removal services divided into two methods—Blast Cleaning and Paint Over—each at 30,000 square feet. Vendors are required to complete the pricing schedule in a modifiable format such as Microsoft Word or Excel, with the option to submit an additional non-modifiable PDF version. Failure to complete the pricing schedule as requested may result in proposal disqualification.
All price proposals must include comprehensive costs encompassing one-time or setup charges, fees, and any ancillary charges such as shipping, handling, and per-piece pricing. Contractors are encouraged to offer quick payment terms with a specified discount percentage and payment window. Additionally, the document contains an "Old EE" section detailing extensive line items for pavement repair and construction work, including activities such as cold milling, hand patching, joint and crack repair, pavement markings, and traffic control devices, with a total estimated cost of $408,992.50 for those services. By submitting a proposal, contractors certify that pricing was determined independently without consultation or agreement with other contractors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Graffiti Removal RFP- Taylor TSC.docx | DOCX document | |
| Attachment A Equipment Listing.docx | DOCX document | |
| Maintenance Traffic Control Typicals (4).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule B
| Company Name: | Enter Company Name Here |
| STATE OF MICHIGAN |
Request For Proposal No. 21000000xxxx Graffiti Removal Contract Taylor TSC
SCHEDULE B
PRICING MATRIX
1. The Contractor must provide a pricing schedule for the proposed Contract Activities using the table shown below. The pricing schedule should be submitted in a modifiable format (e.g. Microsoft Word or Excel); however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.
2. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State (e.g., shipping and handling, per piece pricing, and palletizing).
3. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.
Quick payment terms: ________ % discount off invoice if paid within ________ days after receipt of invoice.
4. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.
| ITEM DESCRIPTION | UNIT | QUANTITY* | PRICE PER UNIT (Vendor Completes) | TOTAL COST (Vendor Completes) |
| Performance Based Graffiti Abatement | Month | 36 | ||
| High Priority Removal | Sft | 10,000 | ||
| As-Needed Graffiti Removal, Blast Cleaning | Sft | 30,000 | ||
| As-Needed Graffiti Removal, Paint Over | Sft | 30,000 |
TOTAL $0.00
Page &P of &N
Eng Estimate
| Company Name: | Enter Company Name Here |
| STATE OF MICHIGAN |
Request For Proposal No. 21000000xxxx Graffiti Removal Contract Taylor TSC
SCHEDULE B
PRICING MATRIX
1. The Contractor must provide a pricing schedule for the proposed Contract Activities using the table shown below. The pricing schedule should be submitted in a modifiable format (e.g. Microsoft Word or Excel); however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.
2. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State (e.g., shipping and handling, per piece pricing, and palletizing).
3. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.
Quick payment terms: ________ % discount off invoice if paid within ________ days after receipt of invoice.
4. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.
| ITEM DESCRIPTION | UNIT | QUANTITY* | PRICE PER UNIT (Vendor Completes) | TOTAL COST (Vendor Completes) |
| Performance Based Graffiti Abatement | Month | 36 | ||
| High Priority Removal | Sft | 10,000 | ||
| As-Needed Graffiti Removal, Blast Cleaning | Sft | 30,000 | ||
| As-Needed Graffiti Removal, Paint Over | Sft | 30,000 |
TOTAL $0.00
Old EE
| ITEM DESCRIPTION | UNIT | QUANTITY | PRICE PER UNIT | TOTAL COST |
| Pavt Repr, Rem | Square Yard | 330 | $30.00 | $9,900.00 |
| Pavt Repr, Nonreinf Con, 10 inch | Square Yard | 330 | $100.00 | $33,000.00 |
| Sawcut, Intermediate | Feet | 280 | $5.00 | $1,400.00 |
| Cement | Ton | 6 | $10.00 | $55.00 |
| Joint, Contraction, Crg | Foot | 530 | $12.00 | $6,360.00 |
| Joint, Contraction, Cp | Foot | 265 | $10.00 | $2,650.00 |
| Sawing and Sealing Longit Pavt Joints | Foot | 41,200 | $1.00 | $41,200.00 |
| Sawing and Sealing Trans Pavt Joints | Foot | 900 | $1.00 | $900.00 |
| Lane Tie, Epoxy Anchored, #5 Bars | Each | 220 | $5.00 | $1,100.00 |
| Lighting For Night Work | Lump Sum | 1 | $5,000.00 | $5,000.00 |
| Sign, Portable, Changeable Message, Furn | Each | 2 | $3,000.00 | $6,000.00 |
| Sign, Portable, Changeable Message, Oper | Each | 2 | $1.00 | $2.00 |
| Barricade, Type III, High Intensity, Lighted, Furn | Each | 10 | $60.00 | $600.00 |
| Barricade, Type III, High Intensity, Lighted, Oper | Each | 10 | $1.00 | $10.00 |
| Cold Milling HMA Surface | Square Yard | 9,000 | $5.00 | $45,000.00 |
| Hand Patching | Ton | 1,500 | $67.00 | $100,500.00 |
| Lighted Arrow, Type C, Furn | Each | 3 | $542.00 | $1,626.00 |
| Lighted Arrow, Type C, Oper | Each | 3 | $69.00 | $207.00 |
| Minor Traffic Devices | Lump Sum | 1 | $4,000.00 | $4,000.00 |
| Non-Chloride Accelerator | Gallon | 220 | $10.00 | $2,200.00 |
| Pavt Joint and Crack Repr, Det 7 | Foot | 12,000 | $10.00 | $120,000.00 |
| Pavt Mrkg, Waterborne, 4 inch, White | Foot | 10,000 | $1.00 | $10,000.00 |
| Plastic Drum, High Intensity, Furn | Each | 200 | $23.00 | $4,600.00 |
| Plastic Drum, High Intensity, Oper | Each | 200 | $1.00 | $200.00 |
| Sign Cover | Each | 8 | $50.00 | $400.00 |
| Sign, Type B, Temp, Prismatic, Furn | Square Foot | 850 | $5.45 | $4,632.50 |
| Sign, Type B, Temp, Prismatic, Oper | Square Foot | 850 | $1.00 | $850.00 |
| Witness, Log, Layout, $1,000.00 | Dlr | 1,000 | $1.00 | $1,000.00 |
| Chanelizing Device, 42 inch, furnished | each | 350 | $15.00 | $5,250.00 |
| Chanelizing Device, 42 inch, operated | Each | 350 | $1.00 | $350.00 |
| TOTAL | $408,992.50 |