SCHE B Tower RFP final.docx
DOCX document 18 KB Posted
- Attached to
- MPSCS - Rainbow Lake Tower Re-location
- Solicitation number
- RFP-171-200000001871-1
- Issued by
- Macomb County, Michigan
About this file
This is a Schedule B Pricing document for the State of Michigan's Request for Proposal No. 171 200000001871 regarding the MPSCS Communication Site Relocation project at Rainbow Lake. The document outlines the pricing submission requirements for contractors bidding on the disassembly, transportation, and reassembly of a communications site.
The pricing schedule must be submitted in a modifiable format (Microsoft Word or Excel), with an optional additional PDF version. The proposal must include all costs, including one-time charges, setup fees, shipping and handling, per piece pricing, and palletizing. Quick payment terms are encouraged, with contractors able to specify discount percentages for early payment. The pricing structure is broken down into three main components: disassembly, transportation, and reassembly, which must be itemized separately and combined into a total bid amount.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Cut Down Sample Raw Land Site - Lattice Tower.pdf | ||
| Tower terms final.docx | DOCX document | |
| MPSCSC 2104 Mt Clemons RFP 642020 FINAL .docx | DOCX document | |
| RFP cover vqw Tower final .docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF MICHIGAN
Request For Proposal No. 171 200000001871
MPSCS - Communication Site Relocation (Rainbow Lake)
SCHEDULE B
PRICING
1. The Contractor must provide a pricing schedule for the proposed Contract Activities using the pricing format listed below. The pricing schedule should be submitted in a modifiable format (e.g.. Microsoft Word or Excel); however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.
2. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State (e.g., shipping and handling, per piece pricing, and palletizing).
3. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.
Quick payment terms: ________ % discount off invoice if paid within ________ days after receipt of invoice.
4. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.
| ITEM |
| $ AMOUNT |
Disassembly
Transportation
Reassembly
Total Bid Amount
File details come from the government source that posted it. Updated .