This document outlines requirements for a federal contract to plug and cap 10 orphaned and abandoned oil wells located in Natrona County, Wyoming. The solicitation was issued by the Bureau of Land Management Wyoming Region under solicitation number 140L6221R0018. Work will involve furnishing labor, equipment, supplies and materials to plug and cap the wells according to specifications. The document provides general information on work locations, submittal requirements, quality assurance standards, environmental and safety regulations, project meetings, and measurement and payment terms. Contractors must adhere to all applicable federal, state and local rules in executing the well plugging work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Scarlett_Pine_Mtn_OW_P_A_01500__Temp_Fac_and_Controls.docx | DOCX document | |
| Sol_140L6221R0018.pdf | ||
| BidSched_ScarlettPineMtnOilWellPlug_SLHKP20210713.xlsx | XLSX spreadsheet | |
| Scarlett_Pine_Mtn_OW_P_A_01505__Mobilization.docx | DOCX document | |
| CFO_Orphan_Well_Scarlett_Pine_Mountain_Unit_Downhole_SOWs_plugging_1.docx | DOCX document | |
| ScarlettPineMtnOW_PA_17322OilandGasWell_PA_SLHKP20210713.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| DIVISION 1 | SECTION 1009 |
| GENERAL REQUIREMENTS | GENERAL INFORMATION AND REQUIREMENTS |
| DIVISION 1 | SECTION 1009 |
| GENERAL REQUIREMENTS | GENERAL INFORMATION AND REQUIREMENTS |
PART 1: GENERAL
1.1 SUMMARY
A. Description of Work: Furnishing labor, equipment, supplies, and materials, to plug, and cap with facility identification as stated in 43 CFR 3162.6, from 10 orphan and abandoned wells.
B. Location: Work under this Contract is located in Natrona County, Wyoming. The Work locations are described in the individual Statements of Work.
C. Work Data Sheet: Statement of Work Sheet designates the type and quantity of work required at each project site.
1.2 REFERENCES
A. Referenced Specifications/Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/standards referred to herein may be procured by the Contractor, from the following:
| ACI | American Concrete Institute | |
| P.O. Box 19150 | ||
| Detroit, MI 48219 |
| AGA | American Gas Association |
| 8501 East Pleasant Valley Road | |
| Cleveland, OH 44131 |
| AISC | American Institute of Steel Construction | |
| 1 E Wacker Dr., Suite 3100 | ||
| Chicago, IL 60601 |
| API | American Petroleum Institute | |
| 1220 L Street, N.W. | ||
| Washington, DC 20005 |
| AWS | American Welding Society, Inc. | |
| 550 Lejeune Rd. NW | ||
| Miami, FL 33126 |
| CFR | Code of Federal Regulations (Available from the Government Printing Office) |
| N. Capitol St. between G and H St., NW | |
| Washington, DC 20402 |
| Title 29 CFR Parts 1926/1910 | Construction Industry-OSHA 2207 | ||||
| Title 43 CFR Part 3160 | Onshore Oil and Gas Operations | ||||
| Onshore Oil and Gas Order No. 2 | Drilling Operations, Section III.G. Nov 18, 1988 Rev 1, Dec 9, 1988 | ||||
| Rev 2, Sep 27, 1989 | |||||
| Rev 3, Jan 27, 1992 | |||||
| Onshore Oil and Gas Order No. 6: | Hydrogen Sulfide Operations, Section III.C, Nov 23, 1990, Rev 1, Jan 17, 1992 |
| NCMA | National Concrete Masonry Association | |
| 2302 Horse Pen Rd. | ||
| Herndon, VA 22071 |
| OSHA | Occupational Safety and Health Administration |
| US Department of Labor | |
| 200 Constitution Ave., NW | |
| Washington DC 20210 |
| PCA | Portland Cement Association | ||
| 5420 Old Orchard Road | |||
| Skokie, IL 60077 |
1.3 DEFINITIONS/ACRONYMS
A. Approvals: Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's attention in writing. After approval of an item, submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.
B. CICR: Cast iron cement retainer.
C. MIRU: Move in, rig up.
D. POOH: Pull out of hole. Come out of the well bore.
E. RIH: Run in hole. Go into the well bore.
F. TOC: Top of cement. The height of the cement in the wellbore or annulus.
G. WOC: Wait on cement. Giving time for the cement to thicken to ensure the cement is properly set before proceeding.
1.4 SUBMITTALS
A. Scope: Submittals include design computations, shop drawings, manufacturers' literature, asbuilt drawings, samples, and maintenance manuals.
B. Requirements: Refer to specifications for submittals required. Allow at least ten (10) working days for review. Submittals shall be delivered to the Contracting Officer Representative.
| C. | Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows: | ||
| 1. | CM-1E Transmittal Form: All material submittals shall be transmitted using Bureau of Land Management form CM-1E. No action will be taken on a material submittal item unless accompanied by the transmittal form. | ||
| a. | Complete the Contractor portion on the form CM-1. | ||
| 1. | Ensure that cover sheet includes following information: | ||
| a. | Submittal Number | ||
| b. | Contract Number | ||
| c. | Specification section number and title, paragraph, and complete description of item being submitted. Be specific and clearly identify what is being submitted. When appropriate, reference a specific sheet and detail of the Drawings or specification number. | ||
| d. | Contractor signature, title, and date. | ||
| e. | Name and telephone number of the individual to contact for further information if other than Contractor. | ||
| b. | Submitted Information: Link submittal to cover sheet by contractor number, project name, and submittal number. Stamp is recommended but may be handwritten on each copy; ensure submittal stamp includes project name and contract number and blank space in which to write submittal number. Stamp or write this information on all copies. | ||
| c. | Provide a certified digital signature or scanned hard copy on form CM-1E where indicated. | ||
| d. | Attach all related documents in PDF format. | ||
| 2. | Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item. | ||
| 3. | Name file with submittal number or other unique identifier, including revision identifier. | ||
| 4. | Do not use the CM-1 Transmittal form for tracking Division 01 Submittals. These documents are posted and processed separately. |
1.5 CERTIFICATES OF CONFORMANCE
A. Requirements: The Contracting Officer may permit use, prior to sampling and testing, of materials when accompanied by Certificates of Conformance. Materials used based on a Certificate of Conformance may be sampled and tested. Installation of materials based on Certificates of Conformance shall not relieve the Contractor of responsibility for incorporating materials which conform to the requirements of the drawings and specifications. Material not conforming to those requirements will be subject to rejection, whether in place or not.
| B. | Format: The Certificate of Conformance provided by the supplier shall: |
| 1. | State that the named product conforms to the Contract requirements. |
| 2. | Either be accompanied with a certified copy of the test results or certify that such test results are on file with the manufacturer and will be furnished to the Contracting Officer upon request. |
| 3. | Provide the name and address of the manufacturer, the testing agency, and the date of tests. |
| 4. | Set forth the means of identification which will permit field determination of the product delivered as being the product covered by the certification. |
1.6 QUALITY ASSURANCE
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.
B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.
C. Measurements: Where approved manufacturer's diagrams and shop drawings give specific measurements or roughin dimensions for equipment, these dimensions shall take precedence over dimensions indicated on the drawings.
D. Equipment: Prior to ordering equipment, verify dimensions and functions of equipment proposed for use including the electrical service requirements. Be certain the equipment is compatible with the structural and architectural features of the work, avoids conflicts with equipment of other crafts, and that it will fit in the space provided.
1.7 DELIVERY, STORAGE, AND HANDLING
A. Delivery: Protect products incorporated into the work from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated. The containers shall bear the referenced specification number, type, and class as applicable.
B. Storage: Provide temporary storage facilities for products. Storage shall comply with the manufacturer's instructions. The storage area shall permit access for inspection and handling.
C. Handling: Load and unload products protecting them from damage.
1.8 PROJECT/SITE CONDITIONS
A. Access to the Work: Access to the work site is scatter throughout the oil fields. Each specific location is in the work data sheets. Operations shall be scheduled during natural daylight hours. The work area is available to the Contractor during these hours.
B. Environmental Considerations: Spills of (oil, fuel, concrete slurry, etc.) occurring during the work of this project shall be excavated to a minimum depth of twelve (12) inches beyond contaminated material and removed from the work location. Prescribed measures to prevent water pollution to nearby water resources shall be strictly observed.
1.9 SEQUENCING AND SCHEDULING
A. Work Schedule: The schedule shall be submitted at the prework conference. When requested, submit an updated schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate.
PART 2: PRODUCTS
(There are no applicable requirements.)
PART 3: EXECUTION
3.1 PROJECT MEETINGS
| A. | PreWork Conference: |
| 1. | Will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract. |
| 2. | The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting. |
| 3. | Be prepared to summarize and explain procedures planned for the project and present the submittals requested in the specifications. |
| B. | Progress Meetings: |
| 1. | To be held at the project site, or as determined by the Contracting Officer. |
| 2. | May be called by either the Contracting Officer or the Contractor. Request shall state who should attend and include an agenda. |
| C. | Final Inspection: |
| 1. | To be held at the project site, or as determined by the Contracting Officer. |
| 2. | Notify the Contracting Officer in writing at least three (3) working days before the completion date so the Government can schedule final inspection. |
| 3. | The superintendent shall be present during this inspection. |
3.2 PREPARATION
A. Work Layout: The Government will provide measurements, if necessary, for the work executed under the Contract. Baseline monuments or benchmarks disturbed or removed during construction shall be reset by the Contractor at the Contractor's expense.
B. Work Limits: Will be established by the Contracting Officer.
3.3 PROJECT IDENTIFICATION
A. Requirements: Furnish and install a Well and Facility Identification at the location designated by the Contracting Officer. The installation shall be in accordance with 43 CFR 3162.6 Well facility and identification. The name of the operator will be listed as “BLM”.
3.4 SALVAGEABLE ITEMS
A. Requirements: Salvageable items shall become the property of the Contractor. Items which have become the property of the Contractor shall be removed from the work site.
3.5 DISPOSAL OF DEBRIS
A. Requirements: Items or debris not designated as salvage for the Government shall become the property of the Contractor. Disposal of materials in a legal manner and payment of fees required is the Contractor's responsibility. Sale of material onsite is not authorized. When hazardous materials are encountered during demolition operations, comply with applicable federal, state, and local regulations, laws, and ordinances concerning removal, handling, and protection against exposure or environmental pollution. Burning of removed materials is not permitted on the work site.
3.6 WARRANTY
| A. | Requirements: Materials, labor, welding, and equipment furnished under this Contract shall be covered by the most favorable warranties (one year) given to customers for such materials, labor, or equipment. The rights or remedies provided herein are in addition to and do not limit rights afforded to the Government by other clauses of this Contract. With respect to warranties, expressed or implied, from manufacturers or suppliers for materials or equipment furnished under the Contract the Contractor shall: |
| 1. | Obtain warranties that would be given in normal commercial practices. |
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: The work described in this section will not be measured for payment.
4.2 BASIS OF PAYMENT
A. Payment: No direct payment for the work described under this section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.
END OF SECTION