Scarlett_Pine_Mtn_OW_P_A_01505__Mobilization.docx

DOCX document 21 KB Posted

Attached to
SCARLETT PINE MTN OIL WELL PLUGGING
Solicitation number
140L6221R0018
Issued by

About this file

This document is a specification section for mobilization and demobilization requirements for a Bureau of Land Management well plugging project in Scarlett Pine Mountain, Wyoming. The specification covers preparatory work and operations necessary to mobilize personnel, equipment, supplies, and incidentals to the project site, as well as for work that must be performed prior to beginning activities on site. No direct payment will be made for moves between project sites, which contractors must include in pricing for other contract items. Payment for mobilization will be made as a lump sum under Pay Item 01505 (01). The related federal contract opportunity is solicitation number 140L6221R0018 for the Scarlett Pine Mountain Oil Well Plugging project, issued by the Department of the Interior Bureau of Land Management Wyoming Region as an unspecified solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION 1SECTION 01505
GENERAL REQUIREMENTSMOBILIZATION/DEMOBILIZATION

PART 1: GENERAL

1.1 SUMMARY

A. Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies, and incidentals to the project site; and for other work and operations which must be performed, or costs incurred prior to beginning work on the various items on the project site. This specification does not include moves between project sites.

PART 2: PRODUCTS

(There are no applicable requirements.)

PART 3: EXECUTION

(There are no applicable requirements.)

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT:

A. Units: The work described in this section will not be measured for payment.

4.2 BASIS OF PAYMENT:

B. Payment: No direct payment for moves between project sites will be made. The Contractor shall include consideration for moves between project sites in the bid price for other items of the Contract. Prices and payment will be full compensation for the work described in this section. Payment will be made under:

Pay Item Description Pay Unit

01505 (01) Mobilization Lump Sum