This document contains ten statements of work and technical specifications for plugging orphan oil wells located in Natrona County, Wyoming. The Bureau of Land Management Wyoming Field Office is soliciting plugging of ten wells in the former Pine Mountain Unit to federal standards, including setting cement plugs across all productive zones and sealing off open annuli to isolate hydrocarbon-bearing strata. Contractors will remove existing equipment from well sites and grade locations. Work must be completed within 180 days of award unless an extension is approved. BLM engineers will provide guidance and inspect work. Plugging plans specify casing details, plug placement depths and volumes, pressure testing requirements, perforation sealing procedures, and surface abandonment methods for each well.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bureau of Land Management, High Plains District, Wyoming Field Office: CFO Date: August 25, 2020

Statement of Work and Specifications – Plugging Pine Mountain Unit 10 wells

Project Name
Pine Mountain Unit 10 Well Plugging Project
Objectives
Plug 10 wells in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Holes must be static and casing must hold pressure after perforations are plugged.
Location
Work under this Contract is located in the former Pine Mountain Unit, Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.
Work Dates & Constraints
Project can begin on issuance of Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the 10 Pine Mountain Unit wells.

BLM shall furnish all records available and provide engineering guidance.

The project is to plug 10 wells to federal standards and remove pumpjacks (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Any damage done to private roads by contractor or their vendors shall be repaired at the contractors expense prior to completion of project.

Specifications

See attached plugging plans for individual well requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Statement of Work and Specifications – Plugging Federal 26-1

Project Name
Federal 26-1 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.

SWSE Section 26 T35N, R84W

Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Federal 26-1 well.

BLM shall furnish all records available and provide engineering guidance.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Federal 26-1

I. Plugging – Baseline Information:

The Federal 26-1 well, API 49-025-21251, is located in Natrona County, Wyoming, SWSE Section 26 T35N, R84W.

8.625” 24# surface casing @ 161’ in 12.25” hole.

5.5” 15.5# production casing @ 1968’ in 9.75” hole.

Perfs @ 1758’ – 1768’, 1918’ – 1944’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper and drill out plug @ 1907'. Run bit and scraper. Roll the hole. Tag bottom.

5. Set CICR at 1868'. Establish circulation. Pump 15 sx Class G through the retainer. Sting out and set 5 sx on top.

6. Set CICR at 1708'. Establish circulation. Pump 15 sx Class G through the retainer. Sting out and set 10 sx on top.

7. Pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

8. Perf at 211'. Set CICR at 111'. Squeeze 60 sacks Class G through retainer (circulate to surface up backside), set 15 sacks on top (fill casing to surface).

9. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Federal 26-1

c. WYW019621

d. SWSE Section 26 T35N, R84W

10. Remove pumpjack, rods, tubing, and scrap/trash from location. Rough grade location with backhoe.

Statement of Work and Specifications – Plugging Pine Midland 11-1

Project Name
Pine Midland 11-1 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.

SENW Section 11 T34N, R84W

Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Midland 11-1 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Midland 11-1

II. Plugging – Baseline Information:

The Pine Midland 11-1 well, API 49-025-05852, is located in Natrona County, Wyoming, SENW Section 11 T34N, R84W.

8.625” 28# surface shoe @ 161’ in 12.25” hole.

5.5” 14# production casing @ 1416’ in 7.875” hole.

Perfs from 1330’ – 1378’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set CICR at 1280'. Establish circulation. Pump 20 sx Class G through the retainer. Sting out and set 10 sx on top.

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 211'. Set CICR at 111'. Squeeze 54 sacks Class G through retainer (circulate to surface up backside), set 15 sacks on top (fill casing to surface).

8. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Midland 11-1

c. WYW03858

d. SENW Section 11 T34N, R84W.

9. Remove pumpjack, rods, tubing, and scrap/trash from location. Rough grade location with backhoe.

Statement of Work and Specifications – Plugging Pine Mountain 35-1

Project Name
Pine Mountain 35-1 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.

SWNE Section 35 T35N, R84W

Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Mountain 35-1 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Mountain 35-1

III. Plugging – Baseline Information:

The Pine Mountain 35-1 well, API 49-025-05881, is located in Natrona County, Wyoming, SWNE Section 35 T35N, R84W.

8.625” 28# surface shoe @ 105’ in 12.25” hole.

5.5” 15.5# production casing @ 1906’ in 7.875” hole.

Perfs @ 1750’ – 1820’, 1829’ – 1835’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set CICR at 1700'. Establish circulation. Pump 20 sx Class G through the retainer. Sting out and set 10 sx on top

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 155'. Circulate 50 sacks Class G (approx) to surface inside and outside casing. Top off as needed.

8. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Midland 35-1

c. WYW019621

d. SWNE Section 35 T35N, R84W

Statement of Work and Specifications – Plugging Pine Mountain 35-2

Project Name
Pine Mountain 35-2 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static, and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.
Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Mountain 35-2 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Mountain 35-2

IV. Plugging – Baseline Information:

The Pine Mountain 35-2 well, API 49-025-21673, is located in Natrona County, Wyoming, SWNE Section 35 T35N, R84W.

8.625” 24# surface shoe @ 162’ in 12.25” hole.

5.5” 14# production casing @ 1712’ in 7.375” hole.

Open hole completion from 1712’ – 1844’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set balance plug from TD to 1644' (42 sx Class G). WOC and tag plug.

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 212'. Set CICR at 112'. Squeeze 50 sacks Class G through retainer (circulate to surface up backside), set 14 sacks on top (fill casing to surface).

8. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Mountain 35-2

c. WYW019621

d. SWNE Section 35 T35N, R84W

Statement of Work and Specifications – Plugging Pine Mountain 35-3

Project Name
Pine Mountain 35-3 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perforations are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.

NENE Section 35 T35N, R84W

Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Mountain 35-3 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Mountain 35-3

V. Plugging – Baseline Information:

The Pine Mountain 35-3 well, API 49-025-20297, is located in Natrona County, Wyoming, NENE Section 35 T35N, R84W.

10.75” surface shoe @ 201’ in 12.5” hole.

5.5” 14# production casing @ 1787’ in 8” hole.

Open hole completion from 1787’ – 1810’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set balance plug from TD to 1610' (30 sx Class G). WOC and tag plug.

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 251'. Set CICR at 151'. Squeeze 105 sacks Class G through retainer (circulate to surface up backside), set 18 sacks on top (fill casing to surface).

8. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Mountain 35-3

c. WYW019621

d. NENE Section 35 T35N, R84W

Statement of Work and Specifications – Plugging Pine Mountain 35-4

Project Name
Pine Mountain 35-4 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.

SENE Section 35 T35N, R84W

Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Mountain 35-4 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Mountain 35-4

VI. Plugging – Baseline Information:

The Pine Mountain 35-4 well, API 49-025-20213, is located in Natrona County, Wyoming, SENE Section 35 T35N, R84W.

10.75” 44# casing shoe @ 160’ in 12.5” hole.

5.5” 13# casing shoe @ 1796’ in 8.25” hole.

Open hole completion from 1796’ – 1806’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set Class G balanced plug from 1,796' to 1,676' (approx. 20 sx).

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 210'. Set CICR at 110'. Squeeze 75 sacks Class G through retainer, set 15 sacks on top. Top off cement at surface (inside and out) as needed.

8. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Mountain 35-4

c. WYW0170071

d. SENE Section 35 T35N, R84W

Statement of Work and Specifications – Plugging Pine Mountain 35-5

Project Name
Pine Mountain 35-5 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.

SENE Section 35 T35N, R84W

Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Mountain 35-5 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Mountain 35-5

VII. Plugging – Baseline Information:

The Pine Mountain 35-5 well, API 49-025-05791, is located in Natrona County, Wyoming, SENE Section 35 T35N, R84W.

8.625” 24# surface shoe @ 128’ in 12.25” hole.

5.5” 14# production casing @ 1820’ in 7.875” hole.

Perfs from 1764’ – 1813’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set CICR @ 1,714'. Establish circulation and squeeze 20 sx Class G through retainer, sting out and set 10 sx on top.

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 178'. Circulate approx. 52 sx Class G inside casing and out to surface. Top off cement at surface (inside and out) as needed.

8. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Mountain 35-5

c. WYW0170071

d. SENE Section 35 T35N, R84W

Statement of Work and Specifications – Plugging Pine Mountain 35-6

Project Name
Pine Mountain 35-6 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.

NESE Section 35 T35N, R84W

Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Mountain 35-6 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Mountain 35-6

VIII. Plugging – Baseline Information:

The Pine Mountain 35-6 well, API 49-025-05785, is located in Natrona County, Wyoming, NESE Section 35 T35N, R84W.

8.625” 24# surface shoe @ 153’ in 13.75” hole.

5.5” 14# production casing @ 1796’ in 7.875” hole.

Perfs from 1786’ – 1794’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set CICR @ 1736'. Squeeze 15 sx Class G thru retainer, sting out and set 10 sx on top.

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 203'. Set CICR at 103'. Squeeze 50 sacks Class G (approx) through retainer, set 10 sacks on top. Circulate to surface inside and outside casing. Top off cement at surface (inside and out) as needed.

8. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Mountain 35-6

c. WYW0170071

d. NESE Section 35, T35N, R84W

Statement of Work and Specifications – Plugging Pine Mountain 35-8

Project Name
Pine Mountain 35-8 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.
Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Mountain 35-8 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Mountain 35-8

IX. Plugging – Baseline Information:

The Pine Mountain 35-8 well, API 49-025-09662, is located in Natrona County, Wyoming, SWNE Section 35 T35N, R84W.

13.375” 40# surface shoe @ 195’ in 17.5’ hole.

8.625” 24# production casing @ 2218’ in 12.25” hole.

Perfs @ 1810’ – 1820’, 1857’ – 1925’.

Packer @ 689’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set CICR @ 600'. Establish circulation and squeeze 25 sx Class G through retainer, sting out and set 13 sx on top.

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 245'. Set CICR @ 145'. Squeeze 70 sx Class G through retainer, sting out and place 10 sx on top.

8. Perf @ 100'. Circulate 75 sx Class G inside and out to surface. Top off cement as needed.

9. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Mountain 35-8

c. WYW019621

d. SWNE Section 35, T35N, R84W

Statement of Work and Specifications – Plugging Pine Mountain 35-9

Project Name
Pine Mountain 35-9 well plugging
Objectives
Plug well in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.
Location
Work under this Contract is located in Natrona County, Wyoming approximately 5 miles southwest of Natrona, Wyoming.

NWNE Section 35 T35N, R84W

Work Dates & Constraints
Project can begin on issuance of the Notice to Proceed (NTP) and must be completed within 180 days of contract unless CO approves of extension.
Prescription
Contractor will furnish rig, personnel, and all material needed to complete plugging of the Pine Mountain 35-9 well.

The project is to plug well to federal standards and remove pumpjack (if any), rods and tubing from location. Flowlines shall be cut off and left exposed to be flushed and capped during surface reclamation. Surface ownership is fee.

Specifications

See attached plugging plan for requirements.

Other Notes
Plugging must be witnessed by CFO inspectors. Any changes to procedure must be approved by BLM engineers prior to doing work.

Project Contacts

Plugging Requirements – Pine Mountain 35-9

X. Plugging – Baseline Information:

The Pine Mountain 35-9 well, API 49-025-05888, is located in Natrona County, Wyoming, NWNE Section 35 T35N, R84W.

10” 40# surface shoe @ 110’, unknown hole size.

8” 28# casing @ 410’, unknown hole size.

7” 24# casing @ 602’, unknown hole size.

5.5” 17# production casing @ 1765’ in 7” hole.

Well was plugged 12/1962. Well was re-entered 3/1967 and drilled out to 1805’.

Open hole completion from 1765’ – 1805’.

II. Plugging Objectives:

The project is to plug well to federal standards, remove pumpjack, rods, and tubing. Surface ownership is fee.

III. Plugging Requirements:

Well shall be plugged in accordance with Onshore Order #2 standards, especially plugging across all productive zones, thief zones, and open annuli. Hole must be static and casing must hold pressure after perfs are plugged.

1. All cement plugs shall be minimum 15.8 ppg Class G neat.

2. A minimum 9 ppg mud/brine shall be placed between plugs.

3. All balance plugs shall be tagged before setting the next plug.

4. Pull rods and tubing. Run in hole with bit and scraper. Roll the hole. Tag bottom.

5. Set balance plug from TD to 1685' (30 sx Class G). WOC and tag plug.

6. If hole is static, pressure test casing to 500 psi for 30 minutes. If any loss of pressure, run in hole with packer, locate and squeeze holes.

7. Perf at 460'. Set CICR at 360'. Squeeze 40 sacks Class G through retainer, set 10 sacks on top.

8. Perf at 125'. Circulate cement (Class G) to surface up all open annuli and inside 5.5" casing. Top off if needed.

9. Cut off well head 4 ft below surface, weld on steel plate. The following shall be inscribed on the plate:

a. BLM

b. Pine Mountain 35-9

c. WYW0220510

d. NWNE Section 35, T35N, R84W