SB1341-17-RP-0022_-_Attachment_III_-_Evaluation_Criteria.docx
DOCX document 18 KB Posted
- Attached to
- Electrical Motor BPA
- Solicitation number
- SB134117RP0022
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI_Answers.docx | DOCX document | |
| Guidelines_for_OFPM_Contractors.docx | DOCX document | |
| Motor_List.docx | DOCX document | |
| SB1341-17-RP-0022-_Attachment_II_-_Applicable_Provisions_and_Clauses.docx | DOCX document | |
| SB1341-17-RP-0022_-_Attachment_I_-_Combined_Synopsis_Solicitation.docx | DOCX document | |
| Revised_SoW.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SB134117RP0022
Attachment III – Evaluation Criteria
Evaluation Criteria: Acceptable/Unacceptable
1. Technical Capability: Offeror shall submit no more than ten (10) single sided pages demonstrating their ability to provide the following three motors, including specifications for the motors.
Qty. Description HP Phase Voltage Frame RPM Nominal
1 ODP (GE) 150 3 480 444T 1800
1 ODP (Toshiba) 125 3 480 445T 1190
1 ODP (GE) 100 3 480 404T 1760
2. Offeror shall show the capability to provide at a minimum 75% of the motor list in attachment IV. Offeror shall provide pricing for each motor listed in attachment IV.
3. Price: Offeror shall submit detailed pricing breakdown for the three motors identified above.
BASIS FOR AWARD:
This is a competitive best value source selection utilizing Lowest Price Technically Acceptable (LPTA) source selection procedures in accordance with FAR 15.101-2 for award of this agreement. The evaluation process shall proceed as follows:
1. By submission of an offer, the Offeror accepts all solicitation requirements, including terms and conditions, representations and certification and technical requirements related to this agreement.
2. The Government intends to award up to three (3) blanket purchase agreements without discussions with respective Offerors. The Government, however, reserves the right to conduct discussions if deemed in its best interest.
3. Evaluation Criteria: Acceptable/Unacceptable. Offeror must submit specifications and a detailed cost breakdown of all motors listed above.
4. Offerors must be acceptable in criteria one (1) and two (2) to be found technically acceptable for award.