This is a Notice to Contractors issued by Sacramento County, California, for the SATS Tank Liquids Removal project (Contract #40997). The project involves removing liquid digestate from an above-ground storage tank and transporting it to an approved facility for disposal. The bid is scheduled for release on March 12, 2025, with a non-mandatory pre-bid meeting on March 19, 2025, at 8550 Fruitridge Road. Potential bidders must submit questions by March 21, 2025, at 12:00 pm, and the bid submission deadline is April 10, 2025, at 2:00 pm. The project requires a General Engineering Contractor with a Class A or Class B license, and the estimated construction cost is $170,000.00.
The pricing proposal includes four line items: mobilization/demobilization, liquid material removal/hauling/disposal (estimated at 65,000 gallons), an odor control plan, and odor control implementation. Bidders must submit electronic responses through the Sacramento County Electronic Bidding Portal and provide a bid guarantee of at least 10% of the total bid amount. Additional requirements include compliance with the California Air Resources Board's Advanced Clean Fleets Regulation for vehicles over 8,500 lbs, submission of a non-collusion declaration, and registration with the California Department of Industrial Relations. The contract will be awarded based on the base bid only, with no additional or deductive items considered.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTICE TO CONTRACTORS
40997
SATS TANK LIQUIDS REMOVAL
County of Sacramento
9660 Ecology Lane
Sacramento, CA 95827
RELEASE DATE: March 12, 2025
DEADLINE FOR QUESTIONS: March 21, 2025
RESPONSE DEADLINE: April 10, 2025, 2:00 pm
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://secure.procurenow.com/portal/saccounty https://secure.procurenow.com/portal/%7bproject.government.code%7d
County of Sacramento
NOTICE TO CONTRACTORS
SATS Tank Liquids Removal
1. Introduction
2. Notice to Contractors
3. Pricing Proposal
4. Vendor Submissions
Attachments:
A - 40997_SATS_Tank1_Digestate_Removal_PROJECT_DRAWINGS
B - 40997_SATS_Tank1_Digestate_Removal_SPECIAL_PROVISIONS
Notice to Contractors #40997 Title: SATS Tank Liquids Removal
1. Introduction
1.1. Summary
The Project includes, without limitation, furnishing all necessary labor, materials, equipment and other incidental and appurtenant Work necessary to satisfactorily complete the Project, as more specifically described in specifications. This Work will be performed in strict conformance with the specifications, permits from regulatory agencies with jurisdiction, and applicable regulations. The quantity of Work to be performed and materials to be furnished are approximations only, being given as a basis for the comparison of Bids. Actual quantities of Work to be performed may vary at the discretion of the County.
Project is for removal of liquid digestate from above ground storage tank 1, and transport to a SacSewer approved facility (or other approved facility) for proper disposal.
1.2. Contact Information
Project Contact:
Cristina Lupercio
Assistant Engineer
Email: lupercioc@saccounty.gov
Phone: (916) 876-8883
Procurement Contact:
Jesse Sanchez
Sr. Contract Services Officer
Email: sanchezj@saccounty.gov
Phone: (916) 876-6378
Department:
DGS: CAPSD - Construction
Department Head:
Joshua Green
Department Director
1.3. Timeline
Release Project Date March 12, 2025
Pre-Bid Meeting (Non-Mandatory) March 19, 2025, 10:00am
8550 Fruitridge Rd
Question Submission Deadline March 21, 2025, 12:00pm mailto:lupercioc@saccounty.gov tel:(916)876-8883 mailto:sanchezj@saccounty.gov tel:(916)876-6378
Question Response Deadline March 28, 2025, 5:00pm
Bid Submission Deadline April 10, 2025, 2:00pm
Bid Opening April 10, 2025, 2:00pm
2. Notice to Contractors
2.1. ADVERTISEMENT SUMMARY
Notice is hereby given that the County of Sacramento will receive sealed bids for the following project:
BID DATE: Thursday, April 10, 2025
SUBMIT BIDS TO: COUNTY OF SACRAMENTO. SUBMIT ELECTRONIC RESPONSES VIA THE SACRAMENTO
COUNTY ELECTRONIC BIDDING PORTAL (SACCOUNTYEBIDS). BIDDERS MUST ELECTRONICALLY SUBMIT
THEIR BID ONLINE NO LATER THAN 2:00 PM ON THE DAY OF THE BID. BID OPENING(S) WILL BE ONLINE
AT 2:00 PM AT THE FOLLOWING LINK: SACCOUNTYEBIDS.
Responses delivered by hand, fax, telephone, e-mail, or any postal carrier will not be accepted. If bidder uploads a file to SacCountyEbids, it is the bidder's responsibility to ensure the file is not corrupt or damaged. If County is unable to open an attachment because it is damaged, corrupt, infected, etc., it may disqualify bidder’s submission. See this training guide for assistance in entering your online response.
FOR: SATS Tank Liquids Removal
CONTRACT NUMBER: 40997
ESTIMATED CONSTRUCTION COST: $170,000.00
CONTRACTOR LICENSE REQUIRED: General Engineering Contractor, Class A or Class B
PRE-BID QUESTIONS DUE VIA Q&A: Date: Friday, March 21, 2025 No later than: 12:00 pm
PROJECT DESCRIPTION: The work to be performed under this contract includes the furnishing of all labor, materials, equipment, and other incidental work for: The contractor will be removing and hauling liquid waste content from some of the existing onsite facilities.
BASIS FOR AWARD: The basis for award shall be base bid only, with no additive or deductive items, or no consideration of additive or deductive items.
CONTRACT INFORMATION: Contract Documents are contained herein and include: Notice to
Contractors, the Sacramento County Standard Construction Specifications, the Special Provisions, the
Bid Proposal form and any attachments, exhibits, drawings, addenda, and/or documents provided by the Project Manager that pertain to this project.
• Contract Documents are available at: SacCountyEbids
• The Standard Construction Specifications, which are incorporated by reference in the Contract
Documents, may be downloaded at: https://saccountyspecs.saccounty.gov/Pages/default.aspx.
https://secure.procurenow.com/portal/saccounty http://help.procurenow.com/en/articles/5815468-opengov-procurement-vendor-training https://saccountyspecs.saccounty.gov/Pages/default.aspx
2.2. NON-MANDATORY PRE-BID MEETING
A non-mandatory pre-bid meeting will be held on Wednesday, March 19, 2025, at 10:00 am, 8550
Fruitridge Rd. The project engineers will be present to provide a project summary and to answer questions.
2.3. BID GUARANTEES
Each bid must be submitted on the bid forms provided in the Contract Documents; however, if none are provided, the surety may issue on its own paper. Each bid must also be accompanied by security in the form of a bid bond issued by a corporate surety, a certified check or cashier's check payable to the
Treasurer of Sacramento County, or cash for an amount not less than ten percent (10%) of the aggregate sum of the bid.
2.4. BONDS
The successful bidder shall be required to execute a material and labor Payment Bond and Performance
Bond, issued by a corporate surety, acceptable to the County of Sacramento, each for not less than one hundred percent (100%) of the contract price.
Pursuant to Public Contract Code, section 22300, the Contractor may, at its own expense, substitute securities for any money being withheld by the County to ensure performance under this contract. The
Contractor must notify the County of its intent to pursue this option prior to the issuance/execution of a contract.
2.5. LICENSE REQUIREMENTS
Award of this contract requires a valid California contractor's license with the classification identified above.
Public Contract Code, section 4104(a)(1), requires that any person making a bid must submit the name, location of the place of business, and the subcontractor’s license number on the bid form.
No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code, section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code, section 1725.5.
2.6. LABOR COMPLIANCE PROGRAM
The County of Sacramento received final approval from the Director of California Department of
Industrial Relations as a Labor Compliance Program effective March 15, 1994. All questions regarding this Labor Compliance Program and prevailing wage requirements should be directed to the Labor
Compliance Section at: 916-875-2711. In accordance with Section 1771.5 of the California Labor Code, the payment of the general prevailing rate of per diem wages or the general prevailing rate of per diem wages for holiday and overtime is not required for any public works project of $25,000 or less when the project is for construction work, or for any public works project of $15,000 or less when the project is for alteration, demolition, repair, or maintenance work.
This is a Construction project in accordance with Labor Code section 1771.5.
Pursuant to California Labor Code, section 1720 and following, and section 1770 and following, the successful bidder shall pay not less than the prevailing rate of per diem wages as determined by the
Director of the California Department of Industrial Relations. Copies of the prevailing wage determinations are on file at the office of the County of Sacramento Labor Compliance Program, 9700
Goethe Road, Suite D, Sacramento, CA 95827, and are also available at http://www.dir.ca.gov/DLSR/PWD.
2.7. ADVANCED CLEAN FLEETS REGULATION
Vehicles with a gross vehicle weight rating greater than 8,500 lbs. and light-duty package delivery vehicles operated in California may be subject to the California Air Resources Board
(CARB) Advanced Clean Fleets regulations. Such vehicles may therefore be subject to requirements to reduce emissions of air pollutants. For more information, see CARB Advanced
Clean Fleets and Advanced Clean Fleets Regulation & Advisories | California Air Resources
Board.
The apparent low bidder shall provide copies of valid Certificates of Reported Compliance as described in California Code of Regulations, title 13, ("13 CCR") section 2449(n) for the bidder’s fleet, and fleets of any listed subcontractors, of vehicles subject to 13 CCR section 2449 which may be use in performance of this project.
If the apparent low bidder’s fleet, or any subcontractor’s fleet, is exempt or is not subject to the regulation bidder shall clearly indicate the applicable exemption in the bidder’s response. For more information, see CARB Advanced Clean Fleets Regulation Exemptions and Extensions
Overview | California Air Resources Board.
Certificates of Reported Compliance and/or exemptions must be submitted by the apparent low bidder by 4:00PM on Monday following Bid Opening and must be received by the County prior to contract award.
2.8. QUESTIONS
Direct pre-bid questions to the Project Manager, Cristina Lupercio, via the Q&A tab in the portal. ALL
PRE-BID QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN Friday, March 21, 2025 BY 12:00
pm. Questions received after that time will not be answered. Responses will be by addenda to the bid documents.
The County of Sacramento reserves the right to reject any or all bids, to waive any informality in any bid, and to determine which bid, in their judgment, is the lowest responsive bid of a responsible Bidder.
https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets/advanced-clean-fleets-regulation-advisories https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets/advanced-clean-fleets-regulation-advisories https://ww2.arb.ca.gov/resources/fact-sheets/advanced-clean-fleets-regulation-exemptions-and-extensions-overview https://ww2.arb.ca.gov/resources/fact-sheets/advanced-clean-fleets-regulation-exemptions-and-extensions-overview
3. Pricing Proposal
Line Item Description Quantity Unit of
Measure Unit Cost Total
1 Mobilization/Demobilization 1 LS
2 Tank 1 - Liquid Material Removal, Hauling & Disposal
65,000 GAL
3 Odor Control Plan 1 LS
4 Odor Control Implementation 1 LS
TOTAL
4. Vendor Submissions
4.1. What form of Bid Guaranty will Contractor be submitting?* Bid security must be a bidder bond, a certified check or cashier’s check payable to the Treasurer of the
County of Sacramento, or cash. Bids secured by personal checks or personal guarantees will be rejected.
☐ Scanned copy of Fully Executed Bid Bond
☐ E-bid Bond (Use Surety 2000)
☐ Cashier's or Certified Check
☐ Cash
*Response required
4.2. Bid Guaranty
Upload a scanned copy of your fully executed bid bond here if Contractor is submitting a scanned bid bond.
3. E-Bid Bond
Please enter your Bid Bond information from Surety2000 below If Contractor is submitting an E-Bid
Bond
4.3. Non-collusion Declaration*
The undersigned declares:
I am an authorized representative with binding authority for my company, the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on the date this bid is submitted.
☐ Please confirm
*Response required
4.4. Designation of Subcontractors - Unit Price Contracts*
Please download the below documents, complete, and upload.
• DESIGNATION_OF_SUBCONTRACTO...
*Response required
4.5. Bid Item Percentage Listing on Designation of Subcontractor form* Bidder shall certify that the bidder entered the PERCENTAGE OF BID ITEM SUBCONTRACTED in Column
(C) of the Designation of Subcontractor form NOT the percentage of total bid.
☐ Please confirm
*Response required
4.6. Type of Business*
☐ C Corporation
☐ S Corporation
☐ Limited Liability C Corporation
☐ Partnership
☐ Limited Liability Partnership
☐ Sole Proprietor/Individual
☐ Other
*Response required
4.7. Type your Legal Company Name Here*
State your Company's Name Here. This will be verified against the California Secretary of State's
Website.
*Response required
4.8. Contractors State License Board (CSLB) Number*
Please enter your License Number here. This will be verified against the state database
*Response required
4.9. Contractors State License Board (CSLB) License Expiration Date * Enter your CSLB license expiration date:
4.10. Contractors State License Board (CSLB) License Classifications* Enter your current CSLB license classifications:
https://government-project.s3.us-west-2.amazonaws.com/17213/fc3a4145-e6ee-47da-97f2-00cbed9173b9_DESIGNATION_OF_SUBCONTRACTORS.docx?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4ITZMXRM2%2F20250312%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20250312T153928Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEHYaCXVzLXdlc3QtMiJHMEUCIQDsOs1UKYxbNV0CakPUBygJkw3Drizy0O%2FHl%2FRS1fnwOAIgDY0f7LQKgPd%2B1ywR3%2BNtYDYzetX2GfH9U83N7Nt8rwQqjAUIv%2F%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FARACGgw4OTIzNjQ2ODc2NzIiDL9WNLsi1ZmduSFneyrgBIoZdsbfQRiau1%2BfG2NVFdBsQ%2F0njjF0eEuWdNSrVQtW08vfrUyKPfVckgf8vmysou3NzRVFUZsAjl3KUnLRQ6WNBv5bAZEY%2BPczAcN7Bmcu%2B5enR5gAhM%2BhNjH80CYQd6byyZFLwzofldoNFyhpwqnJDFZctyaEqeARtM4QmohgIw3%2FRIAyDh79Q3SuphEFORRFpcswZLY7RBSgvYE3yFQ0Qr2E%2Bdmg4Viue9KdpwTrXwrOCj8wKUJVWDbBrl98lgf%2FuxSRx6Fi%2F2DQldth%2FWP12Pve80XsZMXIZ94kMs%2Bubsa0MC32pLA8AfInrDVwxWK%2FI5OTbCGw6UNty3%2FBlSp%2FxfkLz6s8dRNkOebfTiT1RWe5bErE5tIAYixQIGVok8yI4UlcHWiYpTgtOQHtAWW47LSKTqU3eHNZDb3aMwLs6frs4Bb%2BsnmmnKir7yVAmjYpNk78rkt6SSr0Hnx%2FzSoYlDJCPLznQSO2RgX%2BiJTHLdM7xMDLWbIVFJ%2Fj%2BAMiNrwTO1OoIIPyfhhywE4lIEA7lT4itFXVZOSkRvgCFbwwv359GdEdV9J72VrkWiJAfm33iR743TxiEsjxsVcskqv1bGw7VFfXlX7t63hHOhvWwhq8aflFMuAJovll4C76llKHrpGPxD87H3z7%2FU92MmcHsZmbQgVBYK6s8B6IUFY%2Fy%2Fb00bPAeu1HZJyGsF0pPI0UrPP3mnXOljistF3GOLyAbuIjFqq08M3VazwT3R4%2FI0ikiHj5rMCgH%2BOFQcAnQb55ef5q144GmfjmjCbPTgg5PbIECKcWOg3X%2F93jfjgfMKmnxr4GOpsBEvEsZAS9voL5T69uUbTeSIHwFefFMWt2zq5ezUqzzXbZ5zW7By4Dw9TB68H0y5kPNQwGQJ%2FsFhB%2BE%2BfKj7PHPfCjNYj67DbP5kCEjRjy1A%2FrFEHSdLv8%2BoX0J49fnnaWLEtCe%2Bk6xFFKp9er4KjFfpT72nTmLGTyf7SFHkLpLoGqbZL2HYdSiD4%2BKMt44NnVP3kuiG9ubWbMgwg%3D&X-Amz-Signature=b22b2e0d5d3972f4b285eed9fdc7fb47ee7df3ec0f62cf52ae66c76afb0bbdbc&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22DESIGNATION_OF_SUBCONTRACTORS.docx%22&x-id=GetObject
4.11. California Department of Industrial Relations Registration* Please enter your Public Works Contractor Registration Number. This will be verified against the state database.
*Response required
4.12. Provide the full contact name, title, and e-mail of the signatory for your firm. Provide contact information (full name, e-mail, phone number) for the contract manager for your firm in order to distribute Contract Documents, if awarded, including other recipients requiring a copy.* signatory: name, title, email contract manager/admin: name, email, phone
*Response required
4.13. CARB Certification/Exemption*
Please review the Notice to Contractors, section 2.7 and provide either an exemption or certification as an upload in response to this solicitation.
☐ Please confirm
*Response required
4.14. I hereby certify under penalty of perjury that the above statements are true.*