PROJECT: LODGING FOR CEFOP FACILIITES
Place: CNP Facilities in Finca Paraguay Caucasia, Antioquia, Colombia
Date: 12/8/2016
BASE BID
ITEM DESCRIPTION
MATERIAL
UNIT
MATERIAL
QUANTITY
MATERIAL
UNIT COST
LABOR UNIT
LABOR
QUANTITY
LABOR UNIT
COST
EQUIPMENT
UNIT
EQUIPMENT
QUANTITY
EQUIPMENT
UNIT COST
TOTAL COST TOTAL COST BY CHAPTER
A. GENERAL REQUIREMENTS $ 0.00
1 GENERAL REQUIREMENTS $ 0.00
01 32 16 00 20 Construction Progress Documentation $ 0.00
$ 0.00
01 33 00 Submittal Procedures $ 0.00
$ 0.00
01 50 00 Temporary Construction Facilities and Controls $ 0.00
$ 0.00
01 78 00 Execution and Closeout Submittals $ 0.00
$ 0.00
B. LODGING BUILDINGS: GENERAL LODGING, COMMANDER, OFFICERS, CDO, FEMALE LODGING AND SERVICE AREAS $ 0.00
3 CONCRETE $ 0.00
03 11 13.00 10 Stuctural Cast in place Concrete Forming $ 0.00
$ 0.00
03 20 00.00 10 Concrete Reinforcing $ 0.00
$ 0.00
03 30 00 Cast-in-Place Concrete $ 0.00
$ 0.00
4 MASONRY $ 0.00
04 20 00 Masonry $ 0.00
$ 0.00
5 METALS $ 0.00
05 23.16 Welding, Structural $ 0.00
$ 0.00
05 12 00 Structural Steel $ 0.00
$ 0.00
05 50 13 Metal: Miscellaneous and Fabrications $ 0.00
$ 0.00
05 50 14 Structural metal fabrications $ 0.00
6 WOODS, PLASTICS AND COMPOSITES $ 0.00
06 10 00 Rough Carpentry $ 0.00
$ 0.00
7 THERMAL AND MOISTURE PROTECTION $ 0.00
07 41 63 Fabricated Roof Panels assemblies $ 0.00
$ 0.00
07 60 00 Flashing and sheet metal $ 0.00
$ 0.00
07 92 00 Roof Joint Sealants $ 0.00
$ 0.00
8 OPENINGS $ 0.00
08 11 13 Steel Doors and Frames $ 0.00
$ 0.00
08 11 16 Aluminum doors and fames $ 0.00
$ 0.00
OFFICIAL BIDDING CHART
PSIB Page 1 of 4 San Jose del Guaviare
ITEM DESCRIPTION
MATERIAL
UNIT
MATERIAL
QUANTITY
MATERIAL
UNIT COST
LABOR UNIT
LABOR
QUANTITY
LABOR UNIT
COST
EQUIPMENT
UNIT
EQUIPMENT
QUANTITY
EQUIPMENT
UNIT COST
TOTAL COST TOTAL COST BY CHAPTER
08 51 13 Aluminum Windows $ 0.00
$ 0.00
08 71 00 Door Hardware $ 0.00
$ 0.00
08 81 00 Glazing $ 0.00
$ 0.00
08 87 23.13 Safety Films $ 0.00
$ 0.00
9 FINISHES $ 0.00
09 06 90 Color Schedule $ 0.00
$ 0.00
09 24 23 Stucco $ 0.00
$ 0.00
09 26 00 Veneer Plaster $ 0.00
$ 0.00
09 30 10 Ceramic, Quarry and Glass Tiling $ 0.00
$ 0.00
09 51 00 Acoustical Ceilings $ 0.00
$ 0.00
09 90 00 Paints and Coatings $ 0.00
$ 0.00
09 96 00 High Performance Coatings $ 0.00
$ 0.00
10 SPECIALTIES $ 0.00
10 14 00.20 Interior Signage $ 0.00
$ 0.00
10 21 13 Toilet Compartments $ 0.00
$ 0.00
10 28 13 Toilet Accessories $ 0.00
$ 0.00
10 44 16 Fire Extinguishers $ 0.00
$ 0.00
12 FURNISHINGS $ 0.00
12 21 13 Windows Blinds $ 0.00
$ 0.00
12 36 00 Countertops $ 0.00
$ 0.00
13 SPECIAL CONSTRUCTION $ 0.00
13 48 00 Siesmic Protection Miscellaneous Equipment $ 0.00
$ 0.00
22 PLUMBING $ 0.00
22 00 00 Plumbing, General Purpose $ 0.00
$ 0.00
23 HEATING, VENTILATING, AND AIR CONDITIONING $ 0.00
23 00 00 Air Supply, Distribution, Ventilation and Exhaust Systems $ 0.00
$ 0.00
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS $ 0.00
$ 0.00
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS $ 0.00
$ 0.00
PSIB Page 2 of 4 San Jose del Guaviare
UNIT
MATERIAL
QUANTITY
MATERIAL
UNIT COST
LABOR UNIT
LABOR
QUANTITY
LABOR UNIT
COST
EQUIPMENT
UNIT
EQUIPMENT
QUANTITY
EQUIPMENT
UNIT COST
TOTAL COST TOTAL COST BY CHAPTER
23 23 00 REFRIGERANT PIPING $ 0.00
$ 0.00
23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT $ 0.00
$ 0.00
26 Electrical $ 0.00
26 00 00.00 20 Basic Electrical Materials and Methods $ 0.00
$ 0.00
26 05 00.00 40 Common Work Results for Electrical $ 0.00
$ 0.00
26 05 19.00 10 INSULATED WIRE AND CABLE $ 0.00
$ 0.00
26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES $ 0.00
$ 0.00
26 08 00 APPARATUS INSPECTION AND TESTING $ 0.00
$ 0.00
26 09 13 Power Monitoring System $ 0.00
$ 0.00
26 09 23.00 40 LIGHTING CONTROL DEVICES $ 0.00
$ 0.00
26 20 00 Interior Distribution System $ 0.00
$ 0.00
26 24 16.00 40 Panelboards $ 0.00
$ 0.00
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION $ 0.00
$ 0.00
26 41 01.00 40 Lightning Protection System $ 0.00
$ 0.00
26 51 00 Lighting $ 0.00
$ 0.00
C. EXTERIOR WORKS $ 0.00
31 Earthwork $ 0.00
31 00 00 Earthwork $ 0.00
$ 0.00
31 11 00 Clearing and Grubbing $ 0.00
$ 0.00
31 23 00.00 20 Excavation and Fill $ 0.00
$ 0.00
31 60 00 Foundation Preparation $ 0.00
$ 0.00
32 Exterior Improvements $ 0.00
32 16 13 Concrete Sidewalks and Curbs and Gutters $ 0.00
$ 0.00
32 92 23 Sodding $ 0.00
$ 0.00
33 Utilities $ 0.00
33 11 00 Water Distribution $ 0.00
$ 0.00
33 30 00 Sanitary Sewer $ 0.00
$ 0.00
33 40 00 Storm Drainage Utilities $ 0.00
PSIB Page 3 of 4 San Jose del Guaviare
UNIT
MATERIAL
QUANTITY
MATERIAL
UNIT COST
LABOR UNIT
LABOR
QUANTITY
LABOR UNIT
COST
EQUIPMENT
UNIT
EQUIPMENT
QUANTITY
EQUIPMENT
UNIT COST
TOTAL COST TOTAL COST BY CHAPTER
$ 0.00
33 71 02 Underground Electrical and Telecomunications Distribution $ 0.00
$ 0.00
BID OPTION #1: MULTIFUNTIONAL COURT $ 0.00
O1 Multifuntional Court $ 0.00
O1.01 Civil Work $ 0.00
$ 0.00
O2.01 Electrical Work $ 0.00
$ 0.00
D. MARKUPS $ 0.00
D TOTAL DIRECT COST PHYSICAL ADECUATION WORKS $ 0.00
D Administration % $ 0.00 D Unforenseens % $ 0.00 D Profit % $ 0.00 D TAX(Over the profit value) % $ 0.00
T TOTAL COSTS (Base bid+Bid Opt#1) $ $ 0.00
PSIB Page 4 of 4 San Jose del Guaviare