Santa_Cruz_Garage_Mod_Schedule_101425.pdf

PDF 60 KB Posted

Attached to
Soquel/Front & Locust Street Garage Elevator Repairs
Solicitation number
IFB No. PW-0257
Issued by
Santa Cruz County, San Francisco City, California

About this file

This is a project schedule for the Santa Cruz Garage Modernization project, developed by JE Sellen Consulting, LLC. The comprehensive timeline spans from Q4 2025 through Q1 2027 and outlines a multi-phase modernization effort for two locations: 601 Front Street and 1050 Cedar Street. The project schedule includes 14 distinct tasks ranging from bid administration and contract award to site work, modernization, state testing, and final consultant review. Key milestones include contract award on 1/7/26, field survey and engineering from 1/14/26 to 3/25/26, manufacturing and shipping over 18 weeks, and site modernization activities for both locations.

The schedule indicates a total project duration of approximately 15 months, with specific tasks allocated varying timeframes from 5 days to 10 weeks. Critical path activities include manufacturing and shipping (18 weeks), modernization of both street locations (8 and 7 weeks respectively), and associated state testing and permit processes. The document notes this is a sample schedule and actual dates may vary, with bidders advised to reference the Invitation For Bids document for precise timing. Contact information for JE Sellen Consulting is provided as (EE) 415-715-4678, printed on 10/14/25.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration

1 Bid Administration 8 wks

2 Contract Award & Deposit 5 days

3 Field Survey & Engineering 10 wks

4 Submittal Review & Approval 3 wks

5 Equipment Order 0 days

6 Manufacturing & Shipping (All) 18 wks

7 Delivery / Mobilization 0 days

8 Preparatory Site Work 3 wks

9 Modernize 601 Front Street 8 wks

10 State Test / Permit 2 wks

11 Interim Consultant Review 1 day

12 Modernize 1050 Cedar Street 7 wks

13 State Test / Permit 2 wks

14 Consultant Review & Punch 2 wks

11/12/25

1/7/26

1/14/26

3/25/26

NA

4/15/26

NA

8/19/26

8/19/26

10/28/26

11/11/26

11/11/26

12/30/26

1/13/27

S O N D J F M A M J J A S O N D J Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 Qtr 3, 2026 Qtr 4, 2026 Qtr 1, 2027

2026 2027

Task

Milestone

External Milestone

Deadline

Late

Progress

Manual Progress

Santa Cruz Garage Mod Schedule_101425

Printed: Tue 10/14/25 Contact: JE Sellen Consulting, LLC

(EE) 415-715-4678

rdericco Text Box *This is a sample schedule. Actual dates will vary. Bidders will note the Time For Completion section in the Invitation For Bids document.*