This Performance Work Statement (PWS) details a task order for the Special Operations Forces (SOF) Rapid Development Integration Facility (RDIF) to fabricate one B-52 PLLF1-11002-5 Very Low Frequency (VLF) Kit. The contractor will provide technical expertise, manpower, and materials to fabricate, assemble, inspect, acceptance test (ATP), and deliver the kit to the Defense Logistics Agency (DLA) at Warner Robins Air Force Base by 31 July 2027. Key contractor responsibilities include ensuring quality assurance, conducting proper inspections, ordering materials within five working days, providing weekly project updates, performing part fabrication, and maintaining a clean working area.
The PWS includes detailed performance objectives with specific thresholds and surveillance methods, covering precision machining, welding, heat treating, painting, sheet metal work, cable and wiring harness design, material purchasing, subsystem integration, and quality assurance. The work will be performed at Building 148, Wright-Patterson Air Force Base (WPAFB), OH, and the contractor's facility, with normal work hours Monday through Friday. Contractor personnel must maintain a SECRET security clearance and adhere to multiple military specifications for chemical treatment, anodizing, priming, and topcoating of components, as specified in extensive technical addendums detailing specific manufacturing and finishing processes.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8629-25-R-B007/FA8629-26-F-XXXX
Attachment 1, PWS
26 June 2025
Performance Work Statement (PWS)
For
Special Operations Forces (SOF) Rapid Development Integration Facility (RDIF)
B-52 VLF Kit
Task Order FA8629-26-F-BXXX
1.0 Description of Services: The Contractor shall provide one (1) B-52 PLLF1-11002-5
VLF Kit fabricated to the drawing package provided by the RDIF. The contractor shall provide the technical expertise, manpower and materials to fabricate, assemble, inspect, ATP, and deliver one (1) kit to DLA at Warner Robins AFB. Contractor personnel will perform in accordance with the terms, conditions, standards, and specifications contained in the RDIF Indefinite Delivery
Indefinite Quantity (IDIQ) Contract FA8629-26-R-B003.
2.0 Background: The B-52 program office has requested the RDIF to fabricate one (1) B-52
PLLF1-11002-5 VLF Kit for the B-52 aircraft platform.
3.0 Scope: The Contractor shall provide one (1) B-52 PLLF1-11002-5 VLF Kit fabricated to the drawing package provided by the RDIF, which includes the following drawings: VLF
Combined Drawings.
4.0 Program Management: The Contractor shall plan, organize and coordinate all task order activities to ensure compliance with Task Order requirements and the timely delivery of the required services and supplies.
5.0 Specific Tasks/Objectives:
The Contractor shall:
a) Ensure proper management and oversight to ensure quality assurance.
b) Ensure proper quality inspections and paperwork are accomplished.
c) Ensure all material is on order within five working days after Task Order award.
d) Ensure weekly updates to RDIF project manager on material status.
e) Perform part fabrication, finishing, inspecting and packaging.
f) Receive, track, stage, distribute materials to workstations/worksites and document (to include Certificate of Conformance),
g) Maintain clean working area, to include machinery/equipment utilized and Contractor workstations/worksites.
h) Deliver one (1) B-52 PLLF1-11002-5 VLF Kit to DLA at Warner Robins AFB: 370
Richard Ray Blvd. Robins AFB, GA 31098-1670.
26 June 2025
The RDIF shall:
a) Provide total program funding, facilities and tools/equipment based on the project proposal for execution and management.
b) Provide drawings.
a. For Boeing Specs use the cross-reference table in addendum a.
b. For RDIF redlines use the table in addendum b.
c) Coordinate all external efforts with the applicable engineers, equipment specialists, program managers, and item managers.
d) Provide Tinker supplied electrical cables part numbers D3-7619-5/699, D3-7619-5/1208, D3-7619-5/659, D3-7619-5/701, and D3-7619-5/714 to the contractor.
e) Use FA8629 as the DoDAAC for inspection/acceptance
6.0 Principal Place of Performance/Hours of Operation: Work in support of this task order will be performed at Building 148, WPAFB, OH and the contractor facility as required.
Normal workdays are Monday through Friday, except United States (U.S.) Federal holidays.
Workers normally work eight (8) hours per day, 40 hours per week, or as otherwise specified in this PWS.
7.0 Overtime: N/A
8.0 Security Requirements: Contractor personnel supporting this Task Order are required to maintain a SECRET security clearance in accordance with the RDIF IDIQ SF 1449, Section J, Attachment 5: Department of Defense Contract Security Classification Specification (DD 254).
9.0 Travel Requirements: N/A
10.0 Government Furnished Items: N/A
11.0 Required reports: N/A
12.0 Period of Performance/Delivery Schedule: 31 July 2027
13.0 Performance Standards: The following Performance Objectives and Thresholds identified in the RDIF IDIQ SF 1449, Section J, Attachment 1, Paragraph 5: Performance Work
Statement (PWS), and Surveillance Methods defined in RDIF IDIQ SF 1449, Section J, Attachment 7: Quality Assurance Surveillance Plan (QASP) apply to this Task Order.
26 June 2025
PERFORMANCE
OBJECTIVE
BASIC PWS
REFERENCE
PERFORMANCE
THRESHOLD
SURVEILLANCE
CNC and manual mills, lathes, and grinding associated with precision machining
PWS 5.2.2 >Perform precision machining in accordance with current industry standards.
Sampling
Welding, heat treating, painting, and plating
PWS 5.2.3 >Perform these tasks in accordance with current industry standards.
Sampling
Sheet metal components and assembly
PWS 5.2.4 >Perform these tasks in accordance with current industry standards.
Sampling
Cables and wiring harnesses (Design and assembly)
PWS 5.3.3 >Design, fabricate, test, and document cable and wiring harnesses.
100% Inspection
Purchasing material support such as raw materials, fabricated piece parts, mechanical and electrical components, integrated subsystems and other hardware
PWS 5.4.1 > Orders placed on time.
> On time deliveries of ordered products.
Sampling
Integration (Mechanical and electrical subsystems)
PWS 5.4.2 > Perform electrical subsystem integration.
> Perform mechanical subsystem integration.
100% Inspection
Quality assurance/In-process inspection/FAA certification
PWS 5.4.5 > 100% detection of poor workmanship.
100% Inspection
Program Management PWS 5.4.12 > Keep customer informed.
> Timely and accurate
Interaction
Addendums:
a. Cross Reference Table
26 June 2025
Flag Note/Boeing Spec Process/Alt Process
FN# 2.48 Chemical treat in accordance with MIL-C-5541, Type II, Class 3
FN# 2.59 Chemical treat to meet the requirements of MIL-C-5541, Class 1A. On all parts except AGM-86 aluminum castings, apply MIL-PRF-23377, Type I, Class C or MIL-PRF-85582, Type I, Class C1 or C2 to a dry film thickness of
0.0006 inch minimum in accordance with MIL-F-18264. On AGM-86 aluminum castings, apply the primer to a minimum dry film thickness of
0.0012 inch. Do not use MIL-PRF-85582 on IUS.
FN# 2.959 Anodize in accordance with MIL-A-8625 Type I or Type IC (preferred), Class 1 and prime with MIL-PRF-23377, Type I, Class C or MIL-PRF-85582, Type I, Class C1 or C2 to a minimum dry film thickness of 0.0006 inch in accordance with MIL-F-18264.
FN# 12.37 Apply MIL-PRF-23377, Type I, Class C orMIL-PRF-85582, Type I, Class C1 or C2 to a minimum dry film of 0.0006 inch in accordance with MIL-F-18264.
FN# 12.6589-17925 Topcoat with MIL-PRF-85285, Type I or Type II for ground equipment to a minimum dry film thickness of 0.0015 inch in accordance with MIL-F- 18264. 17925 is Insignia White
FN# 12.6589-36251 Topcoat with MIL-PRF-85285, Type I or Type II for ground equipment to a minimum dry film thickness of 0.0015 inch in accordance with MIL-F- 18264. 36251 is Gray
FN# 12.6589-37038 Topcoat with MIL-PRF-85285, Type I or Type II for ground equipment to a minimum dry film thickness of 0.0015 inch in accordance with MIL-F- 18264. 37082 is Black
BAC5004 MIL-STD-403C
BAC5009 MIL-STD-403C
BAC5018 MS33540 and/or SAE-AS567
BAC5034 MIL-STD-2073
BAC5117-6 MIL-STD-464
BAC5300 NAVAIR 01-1A-1, SECT. 8
BAC5307 MIL-STD-130
BAC5423 ASTM E1417
BAC5884 MIL-A-8625
BACD2074 N/A
BACD2097 N/A
BAC5117-1 MIL-STD-464
BAC5152 SAE-AS50881
BAC5153 SAE-AS50881
BAC5154 SAE-AS50881
BAC5155 SAE-AS23053
BAC5157 SAE-AS50881
BAC5158 SAE-AS50881
BAC5159 SAE-AS50881
BAC5162 SAE-AS50881
BAC5162-47 MIL-DTL-38999
BAC5485 ESD TR20.20
26 June 2025
b. RDIF Redlines
Drawing PN Description Replaced by
BMS13-47 Type I, Class3, Grade B, Color 6 Blue Tape M23053/5-108-6 BMS13-47 Type 1, Class3, Grade B, Color 2 Red Tape M23053/5-108-2 BMS13-47 Type 1, Class3, Grade B, Color 7 Violet Tape M23053/5-108-7 BMS13-47 Type I, Class3, Grade B, Color 4 Yellow Tape M23053/5-108-4