ATTACHMENT 3 - RDIF PRICE MATRIX.xlsx
XLSX spreadsheet 20 KB Posted
- Solicitation number
- FA8629-25-R-B007
About this file
The document is a pricing matrix (ATTACHMENT 3 - RDIF PRICE MATRIX.xlsx) for the USAF Rapid Development Integration Facility (RDIF) contract, detailing labor hours and potential material costs across fiscal years FY26-FY36. The matrix includes detailed labor categories with varying skill levels such as Administrative Support, Electricians, Quality Assurance Technicians, Sheet Metal Workers, CNC Operators/Machinists, Welders, Engineers/Scientists, Technicians, Professional Services, and a Program Manager, with projected labor hours ranging from 10 to 6,000 hours per category.
The pricing matrix shows estimated material purchases escalating from $2 million in FY26 to a peak of $4.5 million in FY30-FY32, then declining back to $2 million in FY36. This corresponds to the previously described competitive 8(a) set-aside IDIQ contract for the Air Force Life Cycle Management Center, which will have a five-year base period with five one-year option periods. The contract aims to support Air Force Irregular Warfare and C4ISR acquisition needs by establishing a prototype development center of excellence at Wright-Patterson Air Force Base.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hours
| RDIF TEP | |||||||||||||||||||||||
| Offeror Name: | Offeror DUNS or SAM UEI: | ||||||||||||||||||||||
| Estimated Labor Hours | Fully Burdened NTE Labor Rate | TEP Contribution | |||||||||||||||||||||
| Labor | FY26 | FY27 | FY28 | FY29 | FY30 | FY31 | FY32 | FY33 | FY34 | FY35 | FY36 | FY26 | FY27 | FY28 | FY29 | FY30 | FY31 | FY32 | FY33 | FY34 | FY35 | FY36 | |
| Administrative Support II | 100 | 200 | 200 | 200 | 200 | 200 | 200 | 200 | 200 | 200 | 100 | $ - 0 | |||||||||||
| Administrative Support III | 200 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 200 | $ - 0 | |||||||||||
| Administrative Support IV | 200 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 200 | $ - 0 | |||||||||||
| Electrician II | 250 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 250 | $ - 0 | |||||||||||
| Electrician III | 3000 | 6000 | 6000 | 6000 | 6000 | 6000 | 6000 | 6000 | 6000 | 6000 | 3000 | $ - 0 | |||||||||||
| Electrician IV | 1500 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 1500 | $ - 0 | |||||||||||
| Quality Assurance Technician III | 250 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 250 | $ - 0 | |||||||||||
| Quality Assurance Technician IV | 1000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 1000 | $ - 0 | |||||||||||
| Sheet Metal Worker II | 500 | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | 500 | $ - 0 | |||||||||||
| Sheet Metal Worker III | 1000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 1000 | $ - 0 | |||||||||||
| Sheet Metal Worker IV | 1000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 1000 | $ - 0 | |||||||||||
| CNC Operator/Machinist II | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | $ - 0 | |||||||||||
| CNC Operator/Machinist III | 250 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 500 | 250 | $ - 0 | |||||||||||
| CNC Operator/Machinist IV | 2000 | 4000 | 4000 | 4000 | 4000 | 4000 | 4000 | 4000 | 4000 | 4000 | 2000 | $ - 0 | |||||||||||
| Welder II | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | $ - 0 | |||||||||||
| Welder III | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | $ - 0 | |||||||||||
| Welder IV | 500 | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | 500 | $ - 0 | |||||||||||
| Engineer/Scientist | 50 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 50 | $ - 0 | |||||||||||
| Technician II | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | $ - 0 | |||||||||||
| Technician III | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | $ - 0 | |||||||||||
| Technician IV | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | $ - 0 | |||||||||||
| Professional Services II | 100 | 200 | 200 | 200 | 200 | 200 | 200 | 200 | 200 | 200 | 100 | $ - 0 | |||||||||||
| Professional Services III | 200 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 200 | $ - 0 | |||||||||||
| Professional Services IV | 200 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 200 | $ - 0 | |||||||||||
| Program Manager | 1000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 2000 | 1000 | $ - 0 | |||||||||||
| Total IDIQ Labor | $ - 0 |
Material Estimated Materials Purchased Material Markup TEP Contribution
| FY26 | $ 2,000,000.00 | $ - 0 | |
| FY27 | $ 3,500,000.00 | $ - 0 | |
| FY28 | $ 3,750,000.00 | $ - 0 | |
| FY29 | $ 4,000,000.00 | $ - 0 | |
| FY30 | $ 4,500,000.00 | $ - 0 | |
| FY31 | $ 4,500,000.00 | $ - 0 | |
| FY32 | $ 4,500,000.00 | $ - 0 | |
| FY33 | $ 4,000,000.00 | $ - 0 | |
| FY34 | $ 3,750,000.00 | $ - 0 | |
| FY35 | $ 3,500,000.00 | $ - 0 | |
| FY36 | $ 2,000,000.00 | $ - 0 | |
| Total IDIQ Material | $ - 0 |
| Live Task Order | |||
| Category | Hours | Rate | TEP Contribution |
| Administrative Support II | $ - 0 | $ - 0 | |
| Administrative Support III | $ - 0 | $ - 0 | |
| Administrative Support IV | $ - 0 | $ - 0 | |
| Electrician II | $ - 0 | $ - 0 | |
| Electrician III | $ - 0 | $ - 0 | |
| Electrician IV | $ - 0 | $ - 0 | |
| Quality Assurance Technician III | $ - 0 | $ - 0 | |
| Quality Assurance Technician IV | $ - 0 | $ - 0 | |
| Sheet Metal Worker II | $ - 0 | $ - 0 | |
| Sheet Metal Worker III | $ - 0 | $ - 0 | |
| Sheet Metal Worker IV | $ - 0 | $ - 0 | |
| CNC Operator/Machinist II | $ - 0 | $ - 0 | |
| CNC Operator/Machinist III | $ - 0 | $ - 0 | |
| CNC Operator/Machinist IV | $ - 0 | $ - 0 | |
| Welder II | $ - 0 | $ - 0 | |
| Welder III | $ - 0 | $ - 0 | |
| Welder IV | $ - 0 | $ - 0 | |
| Engineer/Scientist | $ - 0 | $ - 0 | |
| Technician II | $ - 0 | $ - 0 | |
| Technician III | $ - 0 | $ - 0 | |
| Technician IV | $ - 0 | $ - 0 | |
| Professional Services II | $ - 0 | $ - 0 | |
| Professional Services III | $ - 0 | $ - 0 | |
| Professional Services IV | $ - 0 | $ - 0 | |
| Program Manager | $ - 0 | $ - 0 |
Total Labor $ - 0
| Material | ||
| Material Markup | 0% | 0% |
| Total Material | $ - 0 |
Total Live Task $ - 0
Total Evaluated Price $ - 0