This Performance Work Statement (PWS) details a surveillance camera system installation for the Special Access Facility (SAF) at Minot Air Force Base in North Dakota. The project requires a contractor to design, install, configure, and test a complete camera system with specific technical requirements, including 3 vandal-proof 8 MP cameras, a 4-port PoE+ NVR, 1 HDD, equipment enclosure, 3 Samsung 32" display monitors, and a standalone monitoring system that is NDAA-TAA compliant and does not integrate with existing DOD network systems.

The 60-day period of performance includes full system installation, security compliance, user training, and documentation delivery. The contractor must meet strict security protocols, including coordinating base access, using secure IP addresses, and following encryption standards. The contract includes a base year with options for up to 4 additional maintenance and support years, featuring preventative maintenance, corrective maintenance within 72 hours, help desk support, and monthly reporting. The project is managed by the Department of the Air Force Global Strike Command, with a solicitation number of F3C1PS5216AW03, focusing on upgrading vault camera infrastructure with comprehensive technical and operational specifications.

View the file

Other files

File Type Posted
EAL Access Information.docx DOCX document
Camera Upgrade Combo-Final_Redacted.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement (PWS) Surveillance Camera System for SAF – Minot AFB, ND Date: 28 Aug 2025

1.0 Purpose

The purpose of this Performance Work Statement is to establish performance-based requirements for the delivery and installation of a door surveillance system for the Special Access Facility (SAF). The system shall support observation and situational awareness.

2.0 Background

The SAF was remodeled, and all camera systems were removed. The new systems will replace EOL equipment that was in place and give better views of the new entry/exit areas.

3.0 Scope

The contractor shall provide all resources required to design, install, configure, and test a complete camera system in the SAF, and a main monitoring station in room 121K. The system must be reliable, secure, and meet base infrastructure and cybersecurity requirements.

· Security requirements are:

3 Vandal Proof 8 MP cameras will be mounted at specific locations outside of secure location entrances. All locations will be pre-approved by Security personnel. Penetrations will have nonconductive sleeves and fire caulk installed. Viewing Station will have all recording capabilities. Multiple monitoring locations as determined by Security director. Locking equipment rack for ancillary hardware and power supplies will be installed in the provided communication closet.

· NDAA-TAA Compliant CCTV System Description:

The CCTV System shall include a 4 Port PoE+ NVR, 1 HDD (Hard Drive), 1 - equipment enclosure, 3 - dome style 4K IP, autofocus cameras with mounting back boxes, a power conditioning, surge protection and uninterrupted power supply, 3- 32” TAA compliant Samsung display monitors, ceiling mounted with adjustable brackets and 4K - HDMI signal distribution cabling and equipment. The CCTV system will not be integrated into any pre-existing DOD network IT systems. The CCTV System will be a stand-alone monitoring system and may include a hard drive for recording.

4.0 Performance Objectives and Standards

Performance Objective
Performance Standard
Acceptable Quality Level (AQL)
Design & install camera system
Cameras cover all entry/exit doors
100% door coverage
Monitor station setup
Display monitors show real-time and playback video for all doors
No more than 1 system malfunction during test
Compliance with network/security standards
Coordination with Comm/CE, secure login, encrypted protocols
All applicable base and DoD requirements met
User training and documentation
Ensure that Security staff personnel are trained on system functions
Training completed within 2 business days of install

5.0 Deliverables

0. Fully operational surveillance system with 3 installed door cameras

0. One central monitoring system with view functionality

0. Installation layout/diagram for government records

0. Admin credentials and brief security staff training

0. Warranty documentation (1-year minimum)

0. Project sign-off upon successful final inspection

6.0 Government Furnished Property and Services

No Government Furnished Equipment (GFE) will be provided. Contractor must furnish all tools, materials, and personnel necessary to complete the work.

7.0 Period of Performance

The period of performance will be 60 days.

8.0 Security and Access

0. Contractor personnel must coordinate base access through Security Forces.

0. All personnel must comply with safety and security policies while on site. There are no transmitting devices including cell phones, blue tooth devices, two way radios, key fob or other transmitting devices.

0. Camera systems must use secure, non-public IP addresses and encrypted protocols.

9.0 RECORDS MANAGEMENT:

All records, files, documents, regardless of media (e.g., paper, electronic, etc.) as described in the PWS, that are the responsibility of the contractor and will become the property of the Government and shall remain so upon termination or completion of the contract. The contractor shall keep these items current and maintain and dispose of them in accordance with the requirements established in Air Force Instruction (AFI) 33-322, Records Management Program, and the Air Force Records Disposition Schedule, which can be provided by the Base Records Manager or CO upon request. Records shall be turned over to the Government upon completion of the contract unless otherwise stated. All records are subject to the Freedom of Information and Privacy Act. The Minot AFB Installation Records Management Office (5 BW/IPR), 701-723-7917, will provide assistance and training to the contractor to ensure compliance with Federal record keeping requirements.

10.0 Quality Assurance

Government oversight will be conducted using periodic inspections and a final acceptance review. Any deficiencies must be corrected at no additional cost.

11.0 Maintenance and Support

a. Preventative Maintenance: The contractor shall perform preventative maintenance on a one time basis six months after install completion and acceptance by owner/user. This shall include:

· Cleaning of camera lenses and housings.

· Inspection of cabling and connections.

· Verification of camera aiming and focus.

· Software updates and security patches.

· Testing of backup power systems.

b. Corrective Maintenance: The contractor shall provide corrective maintenance services to repair any system malfunctions or failures within 72 hours of notification. This shall include:

· Troubleshooting and diagnosis of problems.

· Repair or replacement of faulty components.

· Restoration of system functionality.

c. Help Desk Support: The contractor shall provide help desk support to answer questions and resolve issues related to the camera system. Support shall be available Monday-Friday 8am-5pm.

d. Reporting: The contractor shall provide a monthly report summarizing maintenance activities, system performance, and any issues encountered.

12.0 Option Years for Maintenance and Support

This section outlines the requirements for maintenance and support services during the option year periods. The Government/Organization reserves the right to exercise options for up to 4 option years. The terms and conditions for maintenance and support during the option years shall be the same as those specified in Section maintenance and support:

a. Preventative Maintenance Schedule: The preventative maintenance schedule will continue through each option year.

b. Corrective Maintenance Response Times: The corrective maintenance response times will remain in effect during each option year.

c. Help Desk Support Availability: The help desk support availability outlined will remain in effect during each option year.

e. Scope Changes: The Government/Organization reserves the right to request minor scope changes to the maintenance and support services during the option years. Any such changes shall be mutually agreed upon in writing and shall be subject to a price adjustment, if necessary.

f. Option Exercise: The Government/Organization will provide written notification of its intent to exercise an option year at least 60 days prior to the expiration of the current contract year.