SAF PWS for Camera System and Istallation.pdf
PDF 158 KB Posted
- Attached to
- 5th OG SAF Cameras
- Solicitation number
- 5OGRFQ0001
About this file
This is a Performance Work Statement (PWS) for the design, installation, configuration, and testing of a surveillance camera system at Minot Air Force Base, North Dakota, dated December 3, 2025. The contractor shall deliver a complete CCTV system for a Special Access Facility (SAF) including three vandal-proof 8 MP cameras mounted at pre-approved secure entrance locations, a 4-port PoE+ NVR with 1 hard drive, three 32-inch TAA-compliant Samsung display monitors, and all associated cabling and power conditioning equipment. The system must be NDAA-TAA compliant, standalone (not integrated with DoD networks), utilize secure non-public IP addresses with encrypted protocols, and include a central monitoring station in room 121K. All camera penetrations require nonconductive sleeves and fire caulk installation, with a locking equipment rack for hardware and power supplies in a provided communication closet.
The contractor must complete design, installation, configuration, and testing within 30 calendar days of Notice to Proceed, with onsite work not exceeding 10 duty days, and overall performance completion within 120 calendar days. Deliverables include a fully operational surveillance system with three cameras, central monitoring station with view and playback functionality, installation diagrams, admin credentials with brief staff training, minimum one-year warranty documentation, and final project sign-off. The contractor shall furnish all tools, materials, and personnel; no Government Furnished Equipment will be provided. Maintenance and support obligations extend beyond initial installation, including preventative maintenance six months post-completion and corrective maintenance response within 72 hours, with help desk support available Monday-Friday 8am-5pm. The contract includes options for up to four additional years of maintenance and support with price adjustments not exceeding 2.5% annually. All contractor personnel must coordinate base access through Security Forces and comply with strict security policies prohibiting transmitting devices; all project records become government property subject to Freedom of Information and Privacy Act requirements and Air Force Records Management directives.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
Surveillance Camera System for SAF – Minot AFB, ND
Date: 03 December 2025
1.0 Purpose
The purpose of this Performance Work Statement is to establish performance-based requirements for the delivery and installation of a door surveillance system for the Special Access Facility (SAF). The system shall support observation and situational awareness.
2.0 Background
The SAF was remodeled, and all camera systems were removed. The new systems will replace EOL equipment that was in place and give better views of the new entry/exit areas.
3.0 Scope
The contractor shall provide all resources required to design, install, configure, and test a complete camera system in the SAF, and a main monitoring station in room 121K. The system must be reliable, secure, and meet base infrastructure and cybersecurity requirements.
Security requirements are:
3 Vandal Proof 8 MP cameras will be mounted at specific locations outside of secure location entrances. All locations will be pre-approved by Special Security Officer, SSO. Penetrations will have nonconductive sleeves and fire caulk installed. Viewing Station will have all recording capabilities. Multiple monitoring locations as determined by the SSO. Locking equipment rack for ancillary hardware and power supplies will be installed in the provided communication closet.
NDAA-TAA Compliant CCTV System Description:
The CCTV System shall include a 4 Port PoE+ NVR, 1 HDD (Hard Drive), 1 - equipment enclosure, 3 - dome style 4K IP, autofocus cameras with mounting back boxes, a power conditioning, surge protection and uninterrupted power supply, 3- 32” TAA compliant Samsung display monitors, ceiling grid mounted with adjustable brackets and 4K - HDMI signal distribution cabling and equipment. The CCTV system will not be integrated into any pre-existing DOD network IT systems. The CCTV System will be a stand-alone monitoring system and may include a hard drive for recording.
4.0 Performance Objectives and Standards
Performance Objective Performance Standard Acceptable Quality Level
(AQL)
Design & install camera system Cameras cover all entry/exit doors 100% door coverage
Monitor station setup Display monitors show real-time and playback video for all doors
No system malfunction during test
Compliance with network/security standards
Coordination with Comm/CE, secure login, encrypted protocols
All applicable base and DoD requirements met
User training and documentation Ensure that Security staff personnel are trained on system functions
Training completed within 2 business days of install
Project completion timeline
Install, test, and turnover completed
Within 30 calendar days of Notice to Proceed
5.0 Deliverables
Fully operational surveillance system with 3 installed door cameras
One central monitoring system with view functionality
Installation layout/diagram for government records
Admin credentials and brief security staff training
Warranty documentation (1-year minimum)
Project sign-off upon successful final inspection
6.0 Government Furnished Property and Services
No Government Furnished Equipment (GFE) will be provided. Contractor must furnish all tools, materials, and personnel necessary to complete the work.
7.0 Period of Performance
The period of performance shall not exceed 120 calendar days from date of award. Onsite work should not exceed 10 duty days.
8.0 Security and Access
Contractor personnel must coordinate base access through Security Forces.
All personnel must comply with safety and security policies while on site. There are no transmitting devices including cell phones, blue tooth devices, two way radios, key fob or any other devices that transmits or receives.
Camera systems must use secure, non-public IP addresses and encrypted protocols.
9.0 RECORDS MANAGEMENT
All records, files, documents, regardless of media (e.g., paper, electronic, etc.) as described in the PWS, that are the responsibility of the contractor and will become the property of the Government and shall remain so upon termination or completion of the contract. The contractor shall keep these items current and maintain and dispose of them in accordance with the requirements established in Air Force Instruction (AFI) 33-322, Records Management Program, and the Air Force Records Disposition Schedule, which can be provided by the Base Records Manager or CO upon request. Records shall be turned over to the Government upon completion of the contract unless otherwise stated. All records are subject to the Freedom of Information and Privacy Act. The Minot AFB Installation Records Management Office (5 BW/IPR), 701-723-7917, will provide assistance and training to the contractor to ensure compliance with Federal record keeping requirements.
10.0 Quality Assurance
Government oversight will be conducted using periodic inspections and a final acceptance review. Any deficiencies must be corrected at no additional cost.
11.0 Maintenance and Support
a. Preventative Maintenance: The contractor shall perform preventative maintenance on a one time basis six months after installation completion and acceptance by owner/user. This shall include:
o Cleaning of camera lenses and housing.
o Inspection of cabling and connections.
o Verification of camera aiming and focus.
o Software updates and security patches.
o Testing of backup power systems.
b. Corrective Maintenance: The contractor shall provide corrective maintenance services to repair any system malfunctions or failures within 72 hours of notification. This shall include:
o Troubleshooting and diagnosis of problems.
o Repair or replacement of faulty components.
o Restoration of system functionality.
c. Help Desk Support: The contractor shall provide help desk support to answer questions and resolve issues related to the camera system. Support shall be available Monday-Friday 8am-5pm.
d. Reporting: The contractor shall provide a monthly report summarizing maintenance activities, system performance, and any issues encountered.
12.0 Option Years for Maintenance and Support
This section outlines the requirements for maintenance and support services during the option year periods. The Government/Organization reserves the right to exercise options for up to 4 option years. The terms and conditions for maintenance and support during the option years shall be the same as those specified in Section maintenance and support:
a. Preventative Maintenance Schedule: The preventative maintenance schedule outlined i will continue through each option year.
b. Corrective Maintenance Response Times: The corrective maintenance response times will remain in effect during each option year.
c. Help Desk Support Availability: The help desk support availability outlined will remain in effect during each option year.
d. Price Adjustment: The price for maintenance and support services during each option year may be adjusted based on [Specify the basis for price adjustment, e.g., the Consumer Price Index (CPI) for North Dakota, a fixed percentage increase, or a mutually agreed-upon price adjustment].
The maximum price increase for any option year shall not exceed 2.5% The Contractor shall provide a detailed justification for any proposed price increase at least 90 days prior to the exercise of the option.
e. Scope Changes: The Government/Organization reserves the right to request minor scope changes to the maintenance and support services during the option years. Any such changes shall be mutually agreed upon in writing and shall be subject to a price adjustment, if necessary.
f. Option Exercise: The Government/Organization will provide written notification of its intent to exercise an option year at least 60 days prior to the expiration of the current contract year.
File details come from the government source that posted it. Updated .