Sacramento DWSC FY21 Specs.pdf

PDF 16 MB Posted

Attached to
SACRAMENTO DWSC MAINTENANCE DREDGING
Solicitation number
W912P721B0005
Issued by

About this file

This solicitation is for annual maintenance dredging of the Sacramento River Deep Water Ship Channel to a depth of 30 feet plus one additional foot of over-depth dredging. Dredged material will be transported to various upland disposal sites. The bid due date is June 11, 2021 at 12:00pm PDT. The bid opening will be conducted via Webex on the provided link one hour after the due date and time. This is a firm fixed price contract awarded through full and open competition. All questions should be directed to the specified Contracting Specialist at the Army Corps of Engineers Engineering District in San Francisco by the provided contact information. The project may be delayed, canceled or revised at any time during the solicitation, selection, evaluation, negotiation or final award process.

View the file

Other files

File Type Posted
OF 1419 W912P721B0005.pdf PDF
Sacramento RFI and Answers.pdf PDF
Placement Site Additional Detail.pdf PDF
S31_placement-site.pdf PDF
Update for RFI 25May.pdf PDF
Amendment 1 RFI.pdf PDF
W912P721B0005-SacramentoDWSCFY21_Plans.pdf PDF
W912P721B0005_Sacramento DWSC.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Specification Sections

W912P721B0005

S O L I C I T A T I O N

Sacramento DWSC FY21 Maintenance Dredging 100% - For Solicitation

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 32 01.00 10 PROJECT SCHEDULE

01 32 23 HYDROGRAPHIC SURVEY

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENT SAFETY REQUIREMENTS (DREDGING)

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM PIPELINE

HYDRAULIC DREDGE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION

ATTACHMENT LIST

ATTACHMENT

01 32 23 Survey QC Log 01 33 00 Submittal Register

01 57 19 CVRWQCB MemoranduCVRWQCB Memorandum

NMFS and USFWS Biological Opinions - Sacramento DWSC

Memorandum of Understanding with the Central Valley Regional Water Quality Control Board (CVRWQCB)

35 20 23 Dredge Material Disposal Site Log

Dredge Material Disposal Site Maps

W912P721B0005

S O L I C I T A T I

Sacramento DWSC FY21 Maintenance Dredging

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 32 01.00 10 PROJECT SCHEDULE

01 32 23 HYDROGRAPHIC SURVEY

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENT SAFETY REQUIREMENTS (DREDGING)

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM PIPELINE

HYDRAULIC DREDGE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

W912P721B0005

S O L I C I T A T I

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

08/11

PART 1 GENERAL

1.1 SUBMITTALS

1.2 PROJECT DESCRIPTION

1.2.1 Requirements

1.2.2 Constraints

1.3 MEETINGS

1.3.1 Pre-dredge Conference

1.3.2 Weekly Meetings

1.4 CONTRACTOR PERFORMANCE EVALUATIONS

1.5 PERMITS

1.6 PUBLIC SAFETY

1.7 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS

1.8 LAYOUT OF WORK

1.9 SAFETY OF STRUCTURES

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 11 00 Page 1 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

SECTION 01 11 00

SUMMARY OF WORK

08/11

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Fish Screen Apparatus Condition Report Operations and Water Quality Monitoring Plan

SD-01 Postconstruction Submittals

Water Quality Monitoring Records

1.2 PROJECT DESCRIPTION

The work includes annual maintenance dredging of the federal navigation channel in the Sacramento River Deep Water Ship Channel (DWSC).

1.2.1 Requirements

a. Dredge the specified dredge areas in the Sacramento DWSC to -30-ft MLLW plus 1-ft of allowable paid overdepth in Sacramento River DWSC.

b. Dredging operations in the Sacramento River DWSC shall begin at the downstream end of the channel.

c. If a second dredge plant is used, dredging operations can begin at the locations identified in aforementioned requirement. Multiple dredge plants shall not work in the same dredging reach.

d. Conduct water quality monitoring and sampling up and downstream of the dredge, at the dredged material placement sites, at any discharge locations and up and downstream those as required in the attached Memorandum of Understanding (MOU) with the Central Valley Regional Water Quality Control Board (CVRWQCB) and UFP-QAPP. Conduct dredging, material placement and discharge in a manner that meets water quality criteria in the MOU. Additional BMPs like discharge management and turbidity curtains may be required at some sites to meet the criteria.

e. The contractor shall conduct fish entrainment monitoring in accordance with Biological Opinions (BO's) issued by the U.S Fish and Wildlife Service (USFWS) and National Marine Fisheries Service (NMFS) for this project. See Section TEMPORARY ENVIRONMENTAL CONTROLS 01 57 19.

f. This project shall be dredged with a hydraulic cutterhead dredge plant(s) with a minimum 16-in diameter pipeline and 1,800 horsepower for the main pump engine.

SECTION 01 11 00 Page 2 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

g. Contractor is responsible for disposal site preparation and dredge material management, including conducting environmental inspections of dredge material placement sites prior to ground disturbance. See Section TEMPORARY ENVIRONMENTAL CONTROLS 01 57 19 for additional requirements.

h. Fish Screen Apparatus Condition Report - At the time of acceptance of the Government furnished fish screen apparatus, the contractor shall visually inspect the apparatus and document its pre-work condition with photographs. Within two days of acceptance, the contractor shall provide a report documenting its pre-work condition. The report shall contain a written narrative, supported by embedded digital photographs identifying the presence or absence of physical damage, corrosion or other problems with the fish screen apparatus.

i. The Contractor shall be responsible for the logistics of assembly and movement of the Government-furnished fish screen apparatus to the various dredged material placement sites, and movement of the apparatus within the sites. The Contractor will be responsible for repairing and maintaining the structural functionality of the Government-furnished fish screen apparatus when required. The Contractor will be responsible for pick up and return of the fish screen apparatus to the US Army Corps of Engineers Sausalito Bay Model or at Port of Stockton which will require a contractor supplied fork lift.

See Section TEMPORARY ENVIRONMENTAL CONTROLS 01 57 19-3.3.1.4 for additional requirements.

j. The Contractor's CQC Manager will provide a meeting agenda 24-hours prior to the scheduled weekly dredging meetings.

1.2.2 Constraints

a. The environmental work window for the Sacramento DWSC is from 1 August to 31 October. Dredging is prohibited prior to 1 August without authorization from the Contracting Officer or delegated representative. Pipeline assembly and disposal site preparation is allowed prior to 1 August.

b. Dredging operations are prohibited after 31 October in the Sacramento DWSC without authorization from the Contracting Officer or delegated representative.

c. All diesel-powered equipment must meet California Air Board emissions requirements.

d. Contractor is allowed a total take of not more than 5 delta smelt (a listed endangered species) from the Sacramento River DWS Channel for the entire contract.

e. Contractor must meet the turbidity limits and other requirements in the Memorandum of Understanding (MOU) with the Central Valley Regional Water Quality Control Board (CVRWQCB). See Section TEMPORARY

ENVIRONMENTAL CONTROLS 01 57 19.

SECTION 01 11 00 Page 3 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

1.3 MEETINGS

1.3.1 Pre-dredge Conference

After award of contract, a pre-dredging conference will be held at such time and location as determined by the Contracting Officer or delegated representative for purposes of discussing and developing mutual understanding between the Contracting Officer or delegated representative and the Contractor's Representatives regarding the terms, conditions, and requirements of the contract. Members of the conference from the Government will include the quality assurance staff, the Contracting Officer or delegated representative, and construction staff. Members from the Contractor shall include the dredge master, chief hydrographic surveyor, and the quality control staff. The discussion will include, but will not be limited to, the following:

- Contractor supervisory and quality control project staff

- Correspondence procedures

- Accident Prevention Plan

- Operations and Water Quality Monitoring Plan

- Fish Entrainment and Biological Resources Monitoring Work Plan

- Pollution control program

- Quality Control and Hydrographic Surveying

- Project scheduling and payment procedures

- Resident Management System (RMS-QC)

- Other subjects that may be of interest to the contracting parties

- Schedule of Weekly Meeting

1.3.2 Weekly Meetings

Weekly construction/survey/coordination/progress meetings shall be held between the Contractor, Contracting Officer or delegated representative, and Government personnel. Minutes of the weekly meeting shall be prepared by the Contactor’s CQC Manager and submitted to the Administrative Contracting Officer or delegated representative within 24 hrs.

1.4 CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. The USACE uses the web-based Construction Contractor Performance Assessment Reporting System (CPARS) to document contractor's performance and prepare performance reports. After an evaluation (interim or final) is written up by the USACE, the Contractor may access, review and comment on the evaluation for a period of 30 days.

Accessing and using CPARS requires Public Key Infrastructure (PKI) certification. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. This certification is purchased from an External Certificate Authorities (ECA) vendor. Contractor access to CPARS is required for Contractor participate in the performance evaluation process. PKI certification is required for Contractor access to CPARS. PKI certification is the sole responsibility of the Contractor. Current information about the PKI certification process and known PKI vendors can be found on the web site: http://www.cpars.gov/ .

SECTION 01 11 00 Page 4 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

1.5 PERMITS

The Contractor shall obtain and comply with all licenses and permits required by Federal, State, and local laws, codes, and regulations unless otherwise specified in these contract documents. The Government has provided the requirements of the Water Quality Certification in accordance with the Clean Water Act, and the requirements of the Coastal Zone Management Act Consistency Notification. The Contractor shall comply with these requirements and provisions in these contract specifications included in Sections TEMPORARY ENVIRONMENTAL CONTROLS 01 57 19 and

DREDGING 35 20 23.

1.6 PUBLIC SAFETY

The Contractor shall provide guard personnel as required to provide protection in the interest of public safety. Whenever the Contractor's operations create a condition hazardous to the public, he shall furnish at his own expense and without cost to the Government, such guards as are necessary to give adequate warning to the public of any dangerous conditions to be encountered, and he shall furnish, erect, or maintain such lights, signs and other devices as are necessary to prevent accidents and to avoid damage or injury to the public. Flagmen and guards, while on duty and assigned to give warning to the public that the dredging is being accomplished, and of any dangerous conditions to be encountered as a result thereof, shall be equipped with appropriate safety equipment and a red flag. Signs, flags, lights, and other warning and safety devices shall conform to applicable city, county, and state requirements. Should the Contractor appear to be negligent in furnishing adequate warning and protective measures, the Contracting Officer or delegated representative will direct attention to the existence of a hazard, and the necessary warning and protective measures shall be furnished and installed by the Contractor without additional cost to the Government. The installation of any general illumination shall not relieve the Contractor of his responsibility for furnishing and maintaining all devices necessary to provide protection to all parties concerned.

1.7 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS

The Contractor's attention is directed to the possible existence of pipelines or public utilities or private improvements shown or not shown on the drawings which may be buried within the limits of the work or adjacent thereto. The Contractor shall take care to preserve and protect any such improvements from injury or damage during construction operations. Utilities or improvements, whether buried or not, which cannot be determined to exist through visual inspection by the Contractor, if inadvertently damaged by the Contractor's operations, shall be promptly repaired or replaced by the Contractor, and an equitable adjustment in the amount due under the contract will be made as provided in the contract.

The Contractor shall notify the Contracting Officer or delegated representative immediately if any utility or structure has been damaged by the Contractor. The Contractor shall assume full responsibility for reimbursing the owners for any damage to their properties, utilities, or improvements, or interference with their services caused through the dredging operations. The Contractor is not relieved from the responsibility set forth in "FAR 52.236-3, Site Investigation and Conditions Affecting the Work" except as provided above.

SECTION 01 11 00 Page 5 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

1.8 LAYOUT OF WORK

The Contractor shall lay out his work from Government-established monuments and gages as shown on the drawings and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at his own expense, all templates, platforms, equipment, markers and labor as may be required in laying out any part of the work from the gages established by the Government. The Contractor is responsible for the execution of the work to such lines, grades and gages as may be established or indicated by the Government. Contractor shall maintain and preserve all monuments and other marks established by the Government until authorized to remove them. Contractor shall check the accuracy of monuments as the Government does not guarantee their accuracy.

1.9 SAFETY OF STRUCTURES

The Contractor shall use reasonable and proper care in the prosecution of the work to assure the stability of piers and other structures lying on or adjacent to the site of work, insofar as they may be jeopardized by the dredging operations and on account of moving or mooring of equipment. The Contractor shall make good all damages resulting from the moving and mooring of his equipment and from dredging operations insofar as such damages may be caused by variations in locations and/or depth of dredging below that ordered by the Contracting Officer or delegated representative.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 6 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

1.2 PAYMENT

1.3 SUBMITTALS

1.4 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera

2.1.2.2 Other than Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Procurement Activities

3.3.4 Mandatory Tasks

3.3.5 Government Activities

3.3.6 Activity Code Structure

3.3.7 Standard Activity Coding Dictionary

3.3.7.1 Workers per Day (WRKP)

3.3.7.2 Responsible Party Coding (RESP)

3.3.7.3 Area of Work Coding (RESP)

3.3.7.4 Modification Number (MODF)

3.3.7.5 Bid Item Coding (BIDI)

3.3.7.6 Phase Work Coding (PHAS)

3.3.7.7 Category of Work Coding (CATW)

3.3.7.8 Feature of Work Coding (FOW)

3.3.8 Contract Milestones and Constraints

3.3.8.1 Project Start Date Milestones and Constraint

3.3.8.2 End Project Finish Milestone and Constraint

3.3.8.3 Interim Completion Dates and Constraints

3.3.8.3.1 Start Phase

3.3.8.3.2 End Phase

3.3.9 Calendars

3.3.10 Open Ended Logic

3.3.11 Default Progress Data Disallowed

3.3.12 Out of Sequence Progress

3.3.13 Added and Deleted Activities

SECTION 01 32 01.00 10 Page 1 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

3.3.14 Original Durations

3.3.15 Leads, Lags, and Start to Finish Relationships

3.3.16 Retained Logic

3.3.17 Percent Complete

3.3.18 Remained Duration

3.3.19 Cost Loading of Closeout Activities

3.3.20 Early Completion Schedule and the Right to Finish Early

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

3.4.3 Periodic Schedule Updates

3.5 SUBMISSION REQUIREMENTS

3.5.1 Data Electronic Files

3.5.2 Narrative Report

3.5.3 Schedule Reports

3.5.3.1 Activity Report

3.5.3.2 Logic Report

3.5.3.3 Total Float Report

3.5.3.4 Earnings Report by CLIN

3.5.3.5 Schedule Log

3.5.4 Network Diagram

3.5.4.1 Continuous Flow

3.5.4.2 Project Milestone Dates

3.5.4.3 Critical Path

3.5.4.4 Banding

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 PERIODIC SCHEDULE UPDATE MEETINGS

3.6.1 Periodic Schedule Update Meetings

3.6.2 Update Submission Following Progress Meeting

3.7 WEEKLY PROGRESS MEETINGS

3.8 REQUEST FOR TIME EXTENSIONS

3.8.1 Justification of Delay

3.8.2 Time Impact Analysis (Prospective Analysis)

3.8.3 Forensic Schedule Analysis (Retrospective Analysis)

3.8.4 Fragmentary Network (Fragnet

3.8.5 Time Extension

3.8.6 Impact to Early Completion Schedule

3.9 FAILURE TO ACHIEVE PROGRESS

3.9.1 Artificially Improving Progress

3.9.2 Failure to Perform

3.9.3 Recovery Schedule

3.10 OWNERSHIP OF FLOAT

3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS

-- End of Section Table of Contents --

SECTION 01 32 01.00 10 Page 2 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

1.2 PAYMENT

Separate payment will not be made for providing and maintaining an effective project schedule, and all associated costs will be included in applicable bid schedule prices.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Preliminary Project Schedule; G, 01 32 01.00 10-3.4.1

Initial Project Schedule; G, 01 32 01.00 10-3.4.2

Periodic Schedule Updates; G, 01 32 01.00 10-3.4.3

1.4 PROJECT SCHEDULER QUALIFICATIONS

Each schedule submittal shall identify the Project Scheduler who was responsible for the preparation of the schedule submittal and all required updating and production of reports. The Project Scheduler must have a minimum of 2 years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

SECTION 01 32 01.00 10 Page 3 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other than Primavera

Contractor shall furnish two scheduling software licenses, two computers, and training for two Government employees in the use of the software if the contractor chooses to use software other than Primavera P6. These computers will be stand-alone and not connected to Government network.

Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates completed for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling is the responsibility of the Contractor. Contractor management personnel must actively participate in development and maintenance of an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer or delegated representative.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the

SECTION 01 32 01.00 10 Page 4 Apr 21, 2021

W912P721B0005

S O L I C I T A T I disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer or delegated representative directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer or delegated representative may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer or delegated representative will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission, review and acceptance of features require design completion Submission, review and acceptance of design packages.

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of as-built drawings.

f. Contractor's pre-final inspection.

g. Correction of punch list from Contractor's pre-final inspection.

SECTION 01 32 01.00 10 Page 5 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

h. Government's pre-final inspection.

i. Correction of punch list from Government's pre-final inspection.

j. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 Activity Code Structure

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the RMS CM web site: http://rms.usace.army.mil.

The SDEF format is as follow:

FIELD ACTIVITY CODE LENGTH DESCRIPTION

1 WRKP 3 WORKERS PER DAY

2 RESP 4 RESPONSIBLE PARTY

3 AREA 4 AREA OF WORK

4 MODF 6 MODIFICATION NUMBER

5 BIDI 6 BID ITEM (CLIN)

6 PHAS 2 PHASE OF WORK

7 CATW 1 CATEGORY OF WORK

8 FOW 20 FEATURE OF WORK*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields.The notation shown is for Primavera P6.Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.7 Standard Activity Coding Dictionary

The Contractor shall develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer or delegated representative, will result in its disapproval. The Contracting Officer or delegated representative will consider, but is not limited to, the

SECTION 01 32 01.00 10 Page 6 Apr 21, 2021

W912P721B0005

S O L I C I T A T I following characteristics and requirements to determine appropriate level of detail:

3.3.7.1 Workers per Day (WRKP)

Assign Workers per Day for all field or direct work activities, if directed by the Contracting Officer or delegated representative. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.7.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to, Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code.

Examples of acceptable activity code values are: DOR (for the designer of record);ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.7.3 Area of Work Coding (RESP)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings. Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.3.7.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer or delegated representative. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.7.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.7.6 Phase Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are design phase, procurement phase, and construction phase. Each activity can

SECTION 01 32 01.00 10 Page 7 Apr 21, 2021

W912P721B0005

S O L I C I T A T I have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.7.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to, design, design submittal, design reviews, review conferences, permits, construction submittals, construction submittal, procurement, fabrication, weather sensitive installation, non- weather sensitive installation, start-up, and testing activities.

Each activity can have no more than one Category of Work Code.

3.3.7.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY CONTROL. An activity can have only one Feature of Work Code.

3.3.8 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer or delegated representative for approval on a case by case basis.

3.3.8.1 Project Start Date Milestones and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.8.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.

The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

SECTION 01 32 01.00 10 Page 8 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

3.3.8.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.8.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.8.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.9 Calendars

Schedule activities on a Calendar to which the activity logically belongs.

Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non- work periods identified including weekends and holidays.

Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.

3.3.10 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer or delegated representative's approval.

3.3.11 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report (Dredge Daily Report) will result in disapproval of the Contractor's schedule.

3.3.12 Out of Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer or delegated representative. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.

SECTION 01 32 01.00 10 Page 9 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

3.3.13 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer or delegated representative. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer or delegated representative approval.

3.3.14 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer or delegated representative.

3.3.15 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

3.3.16 Retained Logic

Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.

3.3.17 Percent Complete

Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.

3.3.18 Remained Duration

Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.

3.3.19 Cost Loading of Closeout Activities

Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).

SECTION 01 32 01.00 10 Page 10 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

3.3.20 Early Completion Schedule and the Right to Finish Early

An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.

a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and man-hours) and the Government agreeing that the schedule is reasonable and achievable.

b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met, nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.

3.4 PROJECT SCHEDULE SUBMISSIONS

Provide the submissions as described below. The data, reports, and network diagrams required for each submission are contained in paragraph

3.5 SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.

Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.

3.4.1 Preliminary Project Schedule Submission

Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Activity code any activities that are summary in nature after the first 90 calendar days with Bid Item (CLIN) code (BIDI), Responsibility Code (RESP) and Feature of Work code (FOW).Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.

SECTION 01 32 01.00 10 Page 11 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

3.4.2 Initial Project Schedule Submission

Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.

3.4.3 Periodic Schedule Updates

Update the Project Schedule on a regular basis, monthly at a minimum.

Provide a draft Periodic Schedule Update for review at the schedule update meetings as prescribed in the paragraph PERIODIC SCHEDULE UPDATE MEETINGS.

These updates will enable the Government to assess Contractor's progress.

a. Update information including Actual Start Dates (AS), Actual Finish Dates (AF), Remaining Durations (RD), and Percent Complete is subject to the approval of the Government at the meeting.

b. AS and AF dates must match the date(s) reported on the Contractor's Quality Control Report for an activity start or finish.

3.5 SUBMISSION REQUIREMENTS

Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:

3.5.1 Data Electronic Files

Provide one set of data in electronic format in RMS containing the current project schedule and all previously submitted schedules in the format of the scheduling software (e.g. .xer). Also include in the data electronic file, the Narrative Report and all required Schedule Reports. Label each data file indicating the type of schedule (Preliminary, Initial, Update), full contract number, Data Date and file name. Each schedule must have a unique file name and use project specific settings.

3.5.2 Narrative Report

Provide a Narrative Report with each schedule submission. The Narrative Report is expected to communicate to the Government the thorough analysis of the schedule output and the plans to compensate for any problems, either current or potential, which are revealed through that analysis.

Include the following information as minimum in the Narrative Report:

a. Identify and discuss the work scheduled to start in the next update period.

b. A description of activities along the two most critical paths where the total float is less than or equal to 20 work days.

c. A description of current and anticipated problem areas or delaying factors and their impact and an explanation of corrective actions taken or required to be taken.

d. Identify and explain why activities based on their calculated late dates should have either started or finished during the update period but did not.

SECTION 01 32 01.00 10 Page 12 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

e. Identify and discuss all schedule changes by activity ID and activity name including what specifically was changed and why the change was needed. Include at a minimum new and deleted activities, logic changes, duration changes, calendar changes, lag changes, resource changes, and actual start and finish date changes.

f. Identify and discuss out-of-sequence work.

3.5.3 Schedule Reports

The format, filtering, organizing and sorting for each schedule report will be as directed by the Contracting Officer or delegated representative. Typically, reports contain Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and Percent Complete. Provide the reports electronically in .pdf format. The following lists typical reports that will be requested:

3.5.3.1 Activity Report

List of all activities sorted according to activity number.

3.5.3.2 Logic Report

List of detailed predecessor and successor activities for every activity in ascending order by activity number.

3.5.3.3 Total Float Report

A list of all incomplete activities sorted in ascending order of total float. List activities which have the same amount of total float in ascending order of Early Start Dates. Do not show completed activities on this report.

3.5.3.4 Earnings Report by CLIN

A compilation of the Total Earnings on the project from the NTP to the data date, which reflects the earnings of activities based on the agreements made in the schedule update meeting defined herein. Provided a complete schedule update has been furnished, this report serves as the basis of determining progress payments. Group activities by CLIN number and sort by activity number. Provide a total CLIN percent earned value, CLIN percent complete, and project percent complete. The printed report must contain the following for each activity: the Activity Number, Activity Description, Original Budgeted Amount, Earnings to Date, Earnings this period, Total Quantity, Quantity to Date, and Percent Complete (based on cost).

3.5.3.5 Schedule Log

Provide a Scheduling/Leveling Report generated from the current project schedule being submitted.

3.5.4 Network Diagram

The Network Diagram is required for the Preliminary, Initial and Periodic Updates. Depict and display the order and interdependence of activities

SECTION 01 32 01.00 10 Page 13 Apr 21, 2021

W912P721B0005

S O L I C I T A T I and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:

3.5.4.1 Continuous Flow

Show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated earned value on the diagram.

3.5.4.2 Project Milestone Dates

Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.

3.5.4.3 Critical Path

Show all activities on the critical path. The critical path is defined as the longest path.

3.5.4.4 Banding

Organize activities using the WBS or as otherwise directed to assist in the understanding of the activity sequence. Typically, this flow will group activities by major elements of work, category of work, work area and/or responsibility.

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

With each schedule submission, provide a SVC diagram showing 1) Cash Flow S- Curves indicating planned project cost based on projected early and late activity finish dates, and 2) Earned Value to-date.

3.6 PERIODIC SCHEDULE UPDATE MEETINGS

3.6.1 Periodic Schedule Update Meetings

Conduct periodic schedule update meetings for the purpose of reviewing the proposed Periodic Schedule Update, Narrative Report, Schedule Reports, and progress payment. Conduct meetings at least monthly within five days of the proposed schedule data date. Provide a computer with the scheduling software loaded and a projector which allows all meeting participants to view the proposed schedule during the meeting. The Contractor's authorized scheduler must organize, group, sort, filter, perform schedule revisions as needed and review functions as requested by the Contractor and/or Government. The meeting is a working interactive exchange which allows the Government and Contractor the opportunity to review the updated schedule on a real time and interactive basis. The meeting will last no longer than 8 hours. Provide a draft of the proposed narrative report and schedule data file to the Government a minimum of two workdays in advance of the meeting. The Contractor's Project Manager and scheduler must attend the meeting with the authorized representative of the Contracting Officer or delegated representative. Superintendents, foremen and major subcontractors must attend the meeting as required to discuss the project schedule and work. Following the periodic schedule update meeting, make corrections to the draft submission. Include only those changes approved by the Government in the submission and invoice for payment.

SECTION 01 32 01.00 10 Page 14 Apr 21, 2021

W912P721B0005

S O L I C I T A T I

3.6.2 Update Submission Following Progress Meeting

Submit the complete Periodic Schedule Update of the Project Schedule containing all approved progress, revisions, and adjustments, pursuant to paragraph SUBMISSION REQUIREMENTS not later than 4 work days after the periodic schedule update meeting.

3.7 WEEKLY PROGRESS MEETINGS

Conduct a weekly meeting with the Government (or as otherwise mutually agreed to) between the meetings described in paragraph entitled PERIODIC SCHEDULE UPDATE MEETINGS for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities for the upcoming two weeks. Use the current approved schedule update for the purposes of this meeting and for the production and review of reports. At the weekly progress meeting, address the status of RFIs, RFPs and Submittals.

3.8 REQUEST FOR TIME EXTENSIONS

Provide a justification of delay to the Contracting Officer or delegated representative in accordance with the contract provisions and clauses for approval within 10 days of a delay occurring. Also prepare a time impact analysis for each Government request for proposal (RFP) to justify time extensions.

3.8.1 Justification of Delay

Provide a description of the event(s) that caused the delay and/or impact to the work. As part of the description, identify all schedule activities impacted. Show that the event that caused the delay/impact was the responsibility of the Government. Provide a time impact analysis that demonstrates the effects of the delay or impact on the project completion date or interim completion date(s). Evaluate multiple impacts chronologically; each with its own justification of delay. With multiple impacts consider any concurrency of delay. A time extension and the schedule fragnet becomes part of the project schedule and all future schedule updates upon approval by the Contracting Officer or delegated representative.

3.8.2 Time Impact Analysis (Prospective Analysis)

Prepare a time impact analysis for approval by the Contracting Officer or delegated representative based on industry standard AACE 52R-06.