This is a Statement of Work (SOW) for the installation of school-age playground surfacing at Cannon Air Force Base, New Mexico. Cannon AFB seeks a contractor to provide, deliver, and install new poured-in-place surfacing at Building 1434, School Age Program, 334 D.L. Ingram Ave., Cannon AFB, NM 88101. The work involves removing existing tan surfacing and installing compliant replacement material that meets all applicable safety and accessibility standards.
The contractor must ensure the playground surfacing meets Consumer Product Safety Commission (CPSC), ASTM International, Americans with Disabilities Act (ADA), and UFC 4-740-14 requirements. The surfacing shall provide adequate fall protection for equipment serving children ages 5-12 and support ADA accessibility. Installation must result in a complete, safe, and fully functional system meeting manufacturer specifications. The contractor is responsible for site clearance of existing surfacing, material delivery, installation, daily cleanup, and leaving the site free of debris upon project completion. Work hours must comply with base access and safety requirements. The contractor shall respond to warranty claims within 72 hours and complete corrective actions within 5 business days; failure to respond will result in government declaration of non-responsiveness and contractor liability for all costs incurred by the government in correcting deficiencies. Government performance evaluation will follow the Quality Assurance Surveillance Plan (QASP). The SOW includes an aerial photograph showing the general space use plan and playground location at the School Age Program facility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
INSTALLATION OF SCHOOL AGE PLAYGROUND
CANNON AFB NM
1. INTRODUCTION: Cannon AFB is seeking a contractor to provide, deliver, and install new poured-in-place surfacing located at Bldg. 1434, School Age Program, 334 D.L. Ingram Ave., Cannon AFB, NM 88101. Requirements will consist of new poured-in-place over old tan surfacing on the playground. The contractor shall provide a fully compliant, safe, and durable playground surfacing system meeting all applicable safety and accessibility standards.
2. PERFORMANCE PERIOD: The contractor shall complete all required outcomes within the performance period established in the contract.
3. GENERAL SCOPE OF WORK: the contractor shall ensure the playground surfacing meets all CPSC, ASTM, ADA, and UFC 4-740-14 requirements.
4. GOVERNMENT OVERSIGHT: The Government will evaluate contractor performance in accordance with the with the Quality Assurance Surveillance Plan (QASP).
5. DESIGN REQUIREMENTS: Materials shall be durable, maintainable, and compliant with all applicable codes.
6. QUALITY OF WORK: All deliverables shall be complete, accurate, and sufficient to support installation and compliance verification.
7. REMOVAL OF OLD EQUIPMENT: The contractor shall ensure the site is cleared of existing surfacing and prepared for installation in accordance with applicable standards.
8. DETAILED PLAYGROUND REQUIREMENTS
• Surfacing shall provide adequate fall protection for equipment serving children ages 5-
12.
• The design shall support ADA accessibility.
9. INSTALLATION OF PLAY STRUCTURE: Installation shall result in a complete, safe, and fully functional surfacing system meeting manufacturer specifications and all applicable standards.
10. STANDARD WORKDAY/WEEK: Contractor work hours shall comply with base access and safety requirements.
11. CLEANUP: The contractor shall leave the site clean, safe, and free of debris at the end of each workday and upon project completion.
11.1 WARRANTY. Contractor shall provide warranty claims within 72 hours and complete corrective actions within 5 business days. If the contractor fails to respond within the time frame indicated above, the government shall declare the contractor non-responsive and shall take all actions necessary to correct the problem with government resources. All costs incurred as a result of the government taking this action, shall be properly accounted for and charged back to the contractor.
12. AREA: Below is a general space use plan.
File details come from the government source that posted it. Updated .