S63500 00011621 Addendum_2.pdf

PDF 158 KB Posted

Attached to
FLAT CREEK FUELS REDUCTION PILE BURNING
Solicitation number
S-63500-00011621
Issued by
Union County, Oregon

About this file

This document is an addendum to an Invitation to Bid (ITB) issued by the Oregon Department of Fish and Wildlife (ODFW) for the Flat Creek Fuels Reduction Pile Burning project. The project requires a contractor to burn approximately 203 acres of piles that were created during the summer and fall of 2023 at the Phillip W. Schneider Wildlife Area. The addendum provides clarifications to questions raised during the mandatory pre-bid conference, including the required amount of pile consumption, allowance for complete underburning in steep areas, and the estimated number of piles per acre. The addendum also clarifies the bid submission process, indicating that bids should be submitted electronically through OregonBuys.

ODFW estimates the project to be approximately $30,000. The addendum does not provide any additional details on pricing terms, set-asides, incumbents, funding requirements or sources, or other salient information.

View the file

Other files

File Type Posted
S63500 00011621 bid tab.xls XLS spreadsheet
ITB S63500-00011621.pdf PDF
Notice of Intent to Award~6.pdf PDF
20241010171635029.pdf PDF
Flat Creek Fuels Reduction Map~1.pdf PDF
ITBAttB - ITB Att F S63500 00011621.pdf PDF
00011622 SignInRoster.pdf PDF
Exhibit A Sample Contract 735-351-24 .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 1 ITB S-63500-00009653

Date: October 16, 2024

Oregon Department of Fish and Wildlife

ADDENDUM #2

ITB S-63500-00011621

Flat Creek Fuels Reduction Pile Burning

ODFW CLARIFICATIONS AND RESPONSE(S) TO QUESTIONS

The following provides ODFW’s answers to questions asked during the Mandatory Pre-Bid conference held on October 9, 2024, and received from prospective Offerors. The information provided below is for clarification purposes only and does NOT constitute a change to the solicitation documents or requirements.

1. QUESTION: How much of the pile needs to be burned?

RESPONSE: 80% of the pile being burned needs to be consumed.

2. QUESTION: When working in the steep hillside area of the project will a complete underburn be allowed?

RESPONSE: Yes, as long as it can be completed safely and contained inside the property line.

No slop over or escapement will be allowed.

3. QUESTION: How many piles are there per acre?

RESPONSE: 15-20 piles per acre on average.

CLARIFICATIONS

1. ITB Location: 3.2.1 Bid Format, it states that “Bidder shall submit its Bid both on electronic thumb drive media and hard copy,” but in 3.2.2.1 Delivery Through OregonBuys, it states that “Bid submission should be electronically through OregonBuys.” Is this an either-or option for submitting the bid information? ITB Location: 3.2.1 Bid Format, it states that “Bidder shall submit its Bid both on electronic thumb drive media and hard copy,” but in 3.2.2.1 Delivery Through OregonBuys, it states that “Bid submission should be electronically through OregonBuys.” Is this an either-or option for submitting the bid information?

Bids should be submitted through Oregon Buys.

2. ODFW estimates this project to be approximately $30K.

END OF CLARIFICATIONS