Questions_and_Answers_2.docx
DOCX document 16 KB Posted
- Attached to
- Pease ANGB, NH Furniture Build Out
- Solicitation number
- S5105A-15-R-0006
- Issued by
-
Defense Contract Management Agency
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers.docx | DOCX document | |
| Pease_bldg_145_Propose_layout_Plan_Rev_3.pdf | ||
| PEASE_MAP.pdf | ||
| DIRECTIONS_for_Site_visit.docx | DOCX document | |
| Pricing_Sheet.xlsx | XLSX spreadsheet | |
| S5105A-15-R-0006.pdf | ||
| Pease_bldg_145_Demo_PlanR1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers 2
1) The description of the workstations include a 64"H storage tower, however it is not shown in the floor plan. Are these to be included in our pricing, and therefore shall we reduce the size of the work surface to allow a storage tower to fit?
Answer: Since the storage tower description is in the PWS, the contractor will have to provide a price for the storage tower for the standard cubicle height panels. Any minor changes to the layout can be discussed at the pre-commencement meeting with the inspector.
2) For the scope of the contractor's work, is the following included?
a) Removal of Walls & Doors Per RFQ. Is patching and filling openings part of the scope.
Answer: Yes
b) Relocating Doors Per RFQ.
Answer: Yes
c) Removal of Carpet & Tiles?
Answer: Yes
d) Installation of New Carpet Tiles? Are we to supply Carpet?
Answer: Yes
e) Removal of all ceiling tiles and installing of new insulated ceiling tiles?
Answer: Yes, if the ceiling tiles cannot be matched.
f) Is there a loading zone for access/delivery?
Answer: No loading dock, everything is on ground level.
g) Are we to provide a dumpster for removal?
Answer: Yes
h) Are we studding and sheet rock patching?
Answer: Yes
i) What is the ceiling height?
Answer: Unknown, ceiling grid height should have been obtained during walk-thru. However, the ceiling height is believed to be 9 feet in the existing space, but it will be the responsibility of the awardee to check all dimensions/measurements in the existing space before start of construction.
j) Are you keeping the ceiling grids and just replacing tiles?
Answer: Only if the ceiling grid can be maintained after the walls are removed.
File details come from the government source that posted it. Updated .