This document is a Request for Information (RFI) spreadsheet for a VA Medical Center restroom renovation project at the Malcom Randall VA Medical Center. The project involves renovating common area restrooms across multiple floors and buildings, with specific requirements including ICRA (Infection Control Risk Assessment) compliance, potential asbestos and lead abatement, HVAC modifications, and bathroom infrastructure updates. Key project parameters include a 730-day performance period, a 365-calendar day completion timeline from Notice to Proceed, and a daily liquidated damages rate of $768.96.
The RFI addresses 54 detailed questions covering technical specifications, project logistics, safety protocols, and construction requirements. Critical elements include contractor responsibilities for phasing (no more than three restrooms under construction simultaneously), maintaining alternate bathroom access, service elevator usage, HVAC system modifications, and strict infection control measures. The project requires specialized roles including a superintendent, Site Safety and Health Officer (SSHO), and Quality Control/Quality Assurance personnel, with specific restrictions on role combinations. The renovation will involve demolition, potential hazardous material remediation, and installation of new fixtures, with alternates for existing locker reuse.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24825R0119 0003 RFI Responses.pdf | ||
| 06 - 573-20-604 RCAR_ALT BID PROPOSAL.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI List
| # | RFIs/QUESTIONS | Government Responses | SME |
| 1 | Please identify the level of ICRA Requirements for each set of Restrooms. | Class IV per page 01 35 26-15 unless reduced by the VA. | VA |
| 2 | If there is no available ability to achieve “Outdoor Exhaust” what is the VA exhaust requirements or air treatment requirements. | The contractor will be responsible to provide any additional ducting need for the exhaust required for HEPA filtering | AE |
| 3 | Can a qualified single individual simultaneously perform the roles of Superintendent, SSHO and QC? | No. | VA |
| 4 | Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO? | Yes, the superintendent can fulfil the responsibilities of the SSHO. | VA |
| 5 | If no to the question above, will the SSHO need to be full-time for this project? | See response to #4. | VA |
| 6 | Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC? | No. QA/QC must be another qualified individual fulfilling a full-time role. | VA |
| 7 | If no to the question above, will the QA/QC need to be full time for this project? | See response to #6. | VA |
| 8 | Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC? | No. | VA |
| 9 | Please confirm the issued drawing set is the latest and complete set. | The bid set has been named "final contract submittal" with a date of 3/21/2024 | VA |
| 10 | Please confirm the current design documents meet current VA TIL guidelines. | Yes, as directed by the VA for compliance. | AE |
| 11 | Please provide the latest wage determination for this project’s county. | FL20250194 | CO |
| 12 | Past Performance: If we have a PPQ, requested for another opportunity, that is less than 12 months old, can we use it within our proposal? Or will a new PPQ need to be requested? | The vendor should make the determination on whether to submit a PPQ from another project or request a new PPQ. | CO |
| 13 | Is the use of temporary plastic wall panels (such as STARC panels) acceptable? | See SOW 7.5. | VA |
| 14 | Will the contractor be required to carry a terminal cleaning of the project area, or will only a construction cleaning be required? | Contractor must perform thorough construction cleaning. VA only performs terminal cleaning per 01 35 26 Section 1.12 Subsection 4 paragraph b.1 on section page 17. | VA |
| 15 | Does this project require formal commissioning? | Yes, per 01 91 00 and specs referenced in it. The commissioning agent must be hired by the contractor as part of this contract. | AE |
| 16 | Who is responsible for contracting the commissioning agent? | See response to #15. | AE |
| 17 | Please confirm order of precedence for the contract documents. Does SOW prevail over the specifications and construction drawings? | See Far 52.215-8. | CO/VA |
| 18 | Will the VA confirm whether the existing lockers to be reused under Alternate # 1 are in acceptable condition for reinstallation? | Alternate No. 1 states the existing lockers will be reused. Price the alternate accordingly. | VA |
| 19 | What is the finish and color selection for the phenolic wall panels? | To be selected by VA Interior Designer based on finish schedule on sheet A603. | AE |
| 20 | Is there a required manufacturer or model number for cubicle curtain tracks? | There is a shower curtain rod called out on sheet A603 in the equipment and accessory schedule. Cubicle curtain tracks should be submitted for review to comply with the specifications with locations noted. | AE |
| 21 | Is the intent to install new trap primers in all floor drains, or only at locations with new fixtures? | Only new ones | AE |
| 22 | Can the Owner confirm the required GPM and pressure ratings for the thermostatic mixing valves? | Use code requirments and ASSE 1070 Standards for each fixture. | AE |
| 23 | Please confirm duct leakage testing is only required on new ductwork. | Only new ones | AE |
| 24 | What is the required balancing tolerance (e.g., ±10%) for HVAC diffusers per the TAB requirements? | Yes, 10% | AE |
| 25 | Please confirm if the new HVAC outlets and inlets must match existing types or can contractor submit alternates for approval? | Match Existing unless the existing is not available, then submit alternatives. | AE |
| 26 | Does the fire stopping system require third-party tested assemblies for all wall penetrations, including for low-voltage cabling? | Yes. See Specs 07 84 00-2 1.5C | AE/VA |
| 27 | Bathroom EB46-1 was locked. COR advised to RFI photos of this bathroom if needed. | See the HazMat Reports, Appendix D, Photographs on specification pdf page 454 following 02 82 11, Traditional Asbestos Abatement. | AE |
| 28 | Please clarify the locations requiring lead or Asbestos Abatement. | See the HazMat Reports at the end of 02 82 11, Traditional Asbestos Abatement. There are full reports and plans. | AE |
| 29 | Are the lockers in the locker rooms staying or being demolished and replaced? | Yes they are being removed and replaced per Final drawings. The Alternate No. 1 lists an option to reuse the existing lockers. | AE |
| 30 | Several restrooms appear too small to meet current ADA standards. Will the VA please confirm the intent is to only demo the wall finishes and not upgrade wall layouts to meet ADA? | Yes. Complete per the issued plans and specifications. | AE |
| 31 | Will the VA please provide a phasing plan for the project? | The contractor is responsible for defining the means and methods for the project. They must ensure that sufficient alternate bathrooms are available on each floor at all times, with the nearest restroom for each gender being no more than 200 feet away. The contractor is expected to work on multiple restrooms across different floors and buildings simultaneously. However, a phasing plan must be submitted as part of the project schedule for evaluation and approval by the VA COR. It is expected that no more than three restrooms will be handed over to the contractor at any given time. However, this depends on the number of restroom fixtures, the square footage, and the phasing plan developed by the contractor. Additional restrooms will not be handed over to the contractor until the restrooms currently under construction have been completed and accepted by the VA. |
Proper signage and notification are required for each bathroom that will be closed and for the alternate bathroom available to the public. The contractor must provide and maintain tabloid-sized, plastic/laminated signage.
| The contractor must obtain prior authorization from the COR at least 30 calendar days before closing a restroom. | VA | |||
| 32 | How many restrooms total can taken down concurrently? | See response to #31. | VA | |
| 33 | How many restrooms on each floor can be taken down concurrently? | See response to #31. | VA | |
| 34 | Mini Split in Restroom B211-1: Is this to be replaced or removed entirely? | Remove and replace. See Note 1 on M104 and 8/M401. | AE | |
| 35 | The liquidated damages addendum was not with the documents provided. Please provide a copy of the liquidated damages addendum | The Liquidated Damages Clause will be added to the solicitation and award document. The daily rate is $768.96 | CO | |
| 36 | Please define if the COR specified is provided by the VA as per section 2.2 or is to be provided by the contractor. If the COR specified in this note is required to be from the contractor, are they required to be on site full time in the same manner as the superintendent or can they be full time regarding this project and be located offsite / at contractors office? | The office requirements listed in 01 00 00-37 section 1.17 is not required. | AE/VA | |
| 37 | Factor 4 - Note that work shall be completed within 365 calendar days from the NTP. Section 11 of the SF 1442 indicates at 730 day performance period. Please confirm the 730 day performance period. | 730 days is the correct period of performance. | VA | |
| 38 | Specs 01 35 26 Safety Requirements, section 1.14 Note D. Per this spec section, temporary walls will need to be constructed at all non-fire rated partitions for the demo portion of work, see the below example. This requirement will impact cost and duration for construction of fire rated walls in sections that currently do not contain fire rated assemblies. Similarly, construction of these temporary barriers will not increase dust control or mitigation. Is the Owner willing to remove this requirement so as to allow construction activities to be limited to only the areas of work as noted on the drawings? | All ICRA requirements must be satisfied per VA and NFPA requirements. Construction actvities must be appropriately sealed. Non fire rated hard walls are acceptable. | VA | |
| 39 | Is the hospital's HVAC system made up of 100% fresh/outside air? | No, It has return duct systems. | AE | |
| 40 | Can the existing HVAC exhaust ducting be utilized in discharging the negative air from the negative air machines? | Construction area is to be filtered through the negative pressure machine with a HEPA filter into the hall | VA | |
| 41 | Please specify the specific required EDMS software. If there is not a specific software, can the government please provide examples of acceptable software’s. | The contractor may use any desired EDMS software. The software must have the capacity for the COR to forward or delegate review of submittals, RFI's, etc. to other staff members at the VA. At the end of the project, the contractor will be responsible to provide to the VA a digital copy of all documentation (reports, checklists, submittals, RFIs, etc.). | VA | |
| 42 | Will the contractor be permitted to set multiple 20’ storage containers in the provided contractor area parking spots for the use of material storage and jobsite operations for the duration of construction mobilization? | No. See SOW Section 4.1. | VA | |
| 43 | Does the project have a designated elevator for construction use in accessing different floors. If so, where is it located? | Service elevators are designated for use by contractors. Patient elevator use not permitted. | VA | |
| 44 | On AD 104 sheet of drawings indicates two doors in room B211and B212-2 as frame and door being demoed. On A401 it does not indicate new doors being installed. On sheet A601 finishes it shows doors B211-1, B212-2, B211-A and B212-A as being replaced with doors are there four doors being replaced? | See Door & Frame Schedule on A601. | AE | |
| 45 | As indicated in reports testing of PCB, asbestos and microbial growth is indicated as being present in materials that will be demoed, there is no mention of an Industrial Hygienist or remediation company in specifications if the contractor would encounter such hazards. What protocol would the government require? | See 02 82 11 in Volume 1 of the specs. The detailed Haz Mat Report follows that section. The CPIH/CIH is mentioned 41 times in the specs which the GC is required to provide. | AE | |
| 46 | AHERA Survey – Could you please provide a copy of the AHERA asbestos survey for this project? We would like to reference it in order to verify square footage and properly scope the abatement work. | See 02 82 11-1, in Volume 1 of the specs. 02 82 11 - 2. Quantities and methods of abatement are in there, reports after that section, and more information is in 02 83 33. | AE | |
| 47 | Asbestos Sampling – Is there a requirement to hire a third-party contractor to perform new asbestos sampling or testing, or is the existing AHERA survey sufficient? | No, only if more hazmat is discovered. | AE | |
| 48 | Storage Access – Will the contractor be provided with access to storage space within the facility, or will we be required to place a connex or similar container externally? Please confirm any site restrictions related to this. | See answer to question 42. | VA | |
| 49 | Safety Plan and JHAs – We understand a project-specific Accident Prevention Plan, including Job Hazard Analysis (JHAs), must be submitted after award and prior to the preconstruction meeting. Please confirm if any other safety-related documentation is required. | ICRA, PCRA and other safety documents will be required. Other incidental permits such as: Above ceiling, hot work, and fire alarm device impairment may be required for submission depending on the nature of work being done. | VA | |
| 50 | Staff Restroom Pull Cords – It was noted that pull cords are not required for staff restrooms. Could you confirm whether this applies to all staff restrooms covered under this scope? | Contractor will not be adding pull cords to any restrooms that do not currently have them. | VA | |
| 51 | Blueprints Request – We kindly request a printed, medium-size set of the project drawings for field reference. If preferred, we are available to pick them up from the Engineering/FMS department at the Tampa VA, as referenced by Mr. Carter (COR). | Government did not commit to providing hard copies, only digital copies, as provided previously by the CO. | CO | |
| 52 | Contract Modification Procedure – In the event of unforeseen conditions discovered during demolition (e.g., unexpected structural or hazardous material issues), could you please confirm the appropriate process for initiating a contract modification or change order? While VAAR 852.243-70 is referenced in the documents, a project-specific point of contact or protocol would be helpful to clarify expectations. | The process to clarify any situation in the project will be through the RFI process. | CO | |
| 53 | The requirements of 01 00 00-31, 1.26 PHOTOGRAPHIC DOCUMENTATION, can be substantially reduced to reflect the interior nature and small size of the project. Do you want to address this or wait for the GC to ask about it? | It is expected that the contractor must include progress of the project in their daily reports. | VA | |
| 54 | The RFP has a single line-item pricing requirement, but the specifications section 01 00 00 has the following and is requesting alternate pricing. How do you wish this to be provided or will you be modifying the pricing page? |
01 00 00 -2
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items.
B. ALTERNATE NO.1: BASE BID except delete new lockers and reuse the existing lockers with the base and bulkhead shown in the drawings at the locker rooms.
C. Provide unit costs for each asbestos removal items type, lead removal items and site preparation, and PCB caulk removal items as listed and directed in 028211 and in the “Asbestos and Lead Containing Paint Survey Report”, “Limited Mold Assessment Report” and “Limited PCBs in Caulk Survey Report”, all dated May 2022 and prepared by GLE. See attached ALT Bid Proposal CO