S02 SOW 517-19-302 Renovate MedSurg for Patient Privacy FINAL .pdf

PDF 97 KB Posted

Attached to
Z1DA--Renovate Medical Surgical Ward for Patient Privacy
Solicitation number
36C24523B0003
Issued by

About this file

This scope of work document outlines requirements for a renovation project at the Beckley VA Medical Center in West Virginia. The project involves demolishing approximately 10,000 square feet of existing space on the third floor to construct a new 13-room medical/surgical patient unit with doctors' offices, nursing stations, and support facilities. A 3,000 square foot greeting and staff area will also be built near the main elevators. Renovations will include architectural, HVAC, plumbing, electrical, and structural work. Three bid items are specified, with Bid Item I representing the base project and Bid Items II and III representing deductive alternates that remove portions of the work. The project is to be completed within 400 calendar days to minimize disruptions to hospital operations. Strict protocols are outlined for infection control, contractor screening, and phasing the work.

View the file

Other files

File Type Posted
36C24523B0003 0007.docx DOCX document
S06 drawing FA601.pdf PDF
S06 Drawing E-002.pdf PDF
S06 Follow-Up RFIs 06.16.2023.pdf PDF
S02 Drawing Part6_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing Part7_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing DVA_Clinical_Addition_II_A-22.pdf PDF
36C24523B0003 0006.docx DOCX document
S05 Answers for Reno Med Surg RFI .pdf PDF
S02 Drawing Part8_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawings Part9_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing Part11_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing Part3_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing DVA_Clinical_Addition_II_A-21.pdf PDF
S02 Drawing 32 01 H10.pdf PDF
S02 Drawing Part1_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing 32 01 H9.pdf PDF
S02 517-19-302_Addendum 1 - Specs Vol II - 10-23.pdf PDF
S02 Drawing Part2_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing Part5_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing DVA_Clinical_Addition_II_A-09.pdf PDF
S02 517-19-302_Addendum 1 - Specs Vol III - 26-28.pdf PDF
S02 517-19-302_Addendum 1 - Specs Vol I - 00 -09.pdf PDF
S02 Drawing Part4_517-19-302_Addendum 1 - Drawings.pdf PDF
S02 Drawing Part10_517-19-302_Addendum 1 - Drawings.pdf PDF
36C24523B0003 0005.docx DOCX document
36C24523B0003 0004.docx DOCX document
36C24523B0003 0003.docx DOCX document
36C24523B0003 0002.docx DOCX document
S04 Pre-Bid Site Visit Sign In.pdf PDF
36C24523B0003 0001.docx DOCX document
S04 Pre Bid Agenda Renovate Med Surg.pdf PDF
S02 Final Contract Docs - Drawings_82-91.pdf PDF
S02 Final Doc - Specs - Volume II .pdf PDF
S02 Final Contract Docs - Drawings_1-12.pdf PDF
S02 Final Doc - Specs - Volume I .pdf PDF
S02 Final Doc - Specs - Volume III .pdf PDF
S02 Final Contract Docs - Drawings_13-28.pdf PDF
S02 Final Contract Docs - Drawings_38-43.pdf PDF
S02 Final Contract Docs - Drawings_57-64.pdf PDF
S02 Final Contract Docs - Drawings_44-56.pdf PDF
S02 Final Contract Docs - Drawings_65-72.pdf PDF
S02 Final Contract Docs - Drawings_92-98.pdf PDF
S02 Wage Determination 1-5-23 .pdf PDF
36C24523B0003.docx DOCX document
S02 Final Contract Docs - Drawings_73-81.pdf PDF
S02 Final Contract Docs - Drawings_29-37.pdf PDF
S02 Final Contract Docs - Drawings_99-end.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

517-19-302 Beckley VA Medical Center

Renovate Medical Surgical Ward for Patient Privacy

SCOPE OF WORK

517-19-302

LOCATION: Work performed under this scope will be conducted at the Beckley VA Medical

Center (VAMC) located at 200 Veterans Ave., Beckley, WV 25801. Work will be conducted in

Building 1, primarily on the 3rd floor.

GENERAL: The project scope involves the demolition and renovation of approximately 10,000 gross square feet of existing former Medical Surgical space in use as clinic area to accommodate a new Med/Surg unit with 13 patient rooms with bathrooms. The new space includes patient rooms, doctors’ offices, space for nursing staff, pharmacology areas as well as the various support facilities required by the medical staff. Also included is 3,000 square feet at the main bank of elevators which will provide a greeting, scheduling and staff area that will serve the entire 3rd floor.

PROJECT OUTLINE: This scope of work (SOW) is intended to provide the general contractor a description of work to be completed. Please refer to drawings and specifications for more detailed information. The information provided in the SOW includes but is not limited to the following:

Architectural

This project will construct a new med/surg patient unit on the 3rd floor. The work required in the second-floor ceiling will be done in small areas and timed appropriately to minimize disruption of the existing space. This work can also be performed “off hours” when necessary. Work will be scheduled through the VA COR and the VA’s contracting officer. During construction of the center area, the access to the administrative area will be through the North and South access points. Access to the ICU will have to be altered non-sequentially as construction progresses.

Partitions, doors and frames, ceiling and floor finishes, and wall mounted accessories will be removed back to the existing CIP concrete structure. There is a 2” floor topping shown on the original drawings. This will be removed at the new patient bathroom locations to allow the floor to have a positive pitch to drains.

New partitions constructed of metal studs and GWB will be constructed in a new configuration based on the program developed. The new med/surg unit will consist of 12 patient rooms and one (1) SCI patient room. One (1) of the patient rooms will be an isolation room with an anteroom. Also, the center of the third floor will be renovated in the same manner by reconfiguring the existing ramp to the administrative wing. A 3rd floor greeting, and scheduling area will be constructed to direct and control patient and visitor flow to the four parts of the third floor.

New mechanical equipment will be installed on several roofs on new steel dunnage which will be flashed into the existing roofing materials.

HVAC

The HVAC system for the 3rd floor renovated space will consist of a new rooftop VAV air handler, 1-RTU-4, placed on the roof of the 1st floor mechanical room, along with new ductwork, supply VAV boxes and return air dampers. The supply VAV boxes shall be provided with reheat. The reheat water will be supplied from a new steam to water heat exchanger.

The new AHU will be located on the 1st floor roof of Mechanical Room 1A-113 mounted on rooftop dunnage. Chilled water supply and return as well as steam condensate return are being routed from Mechanical Room 1A-113 to that AHU. The steam supply line and air distribution ductwork from this unit is to be routed through the 3rd floor exterior wall. The new steam to water shell-and-tube heat exchangers will be mounted in room 3A-111A. Reheat piping to the

VAV boxes will be routed from the reheat boiler to each VAV box.

The existing make-up air unit, 1-MAU -15, will remain and, after the project is completed, this unit will only serve the 4th floor. Since the unit currently serves both the 3rd and 4th floors, it will need to remain in operation during the 3rd floor renovations, to serve the 4th floor systems.

The air flow is split approximately equally between the 3rd and 4th floors. It will need to be rebalanced to approximately 40% of the current capacity during construction and rebalanced after the renovations are complete.

Currently, the main outside air duct from 1-MAU-15, wraps around outside the south and west sides of the building and enters through Room 3A-108. The main duct splits in 3A-108. One branch passes through and enters the 3rd floor corridor ceiling to serve the 3rd floor systems.

The other branch rises through the 4th floor slab to room 4A-108 and then into the 4th floor corridor ceiling to serve the 4th floor systems. The entry into the 3rd floor will be eliminated and the duct will enter the fourth floor above the window at the end of the Corridor to join with the existing distribution feeding the 4th Floor. A new plant steam source, duct-mounted humidifier will be provided to replace the clean steam generator that is currently located in

Maintenance Room 3A-108.

The new 3rd floor Med Surg system has been designed to accommodate pandemic situations. To add this functionality, a bag-in/bag-out HEPA filter and fan has been included in the new system.

The HEPA filter and fan are both mounted on the 6th floor roof. The HEPA filter is the type allowing filter change-out without taking the fan out of service.

An Airborne Infection Isolation Room is being added as one of the 3rd floor patient suites. As part of the design, a bag-in/bag-out HEPA filter and redundant fans are being added as part of the system. Similar to the pandemic mode equipment, the HEPA filter and redundant fans are being mounted on the 6th floor roof. However, in the isolation room HEPA filter, the system will need to be taken out of service to change-out the filters.

All new HVAC systems and equipment will be added to the BAS for control purposes.

Plumbing, Medical Gas and Fire Protection

The existing plumbing systems will be demolished up to the risers. New plumbing will be installed from the risers to all new plumbing fixtures in each of the patient bathrooms, patient room sinks, staff and visitor bathrooms and other staff facilities. Some risers will need to be relocated. New vents and drains will also need to be installed. Consequently, modifications are required in the second-floor ceiling to accommodate the drains. Shutoff valves for the hot and cold-water supplies will need to be added; these will be located in the ceiling of the 3rd floor.

Medical gases required at outlets will be supplied from the existing medical gas distribution systems located above the ceiling. Existing piping will be demolished, and new med gas distribution piping will be installed from the headers to the med gas outlets located at the patient headboards The existing zone valve boxes, within the renovated area, will need to be removed and replaced to suit the new architectural layout. The zone valve boxes will be located for ready access by Fire Department and Nursing staff. Existing building master alarm and new local area panels for the medical gas system shall be utilized.

The existing Fire Sprinkler System shall be demolished back to the existing risers zone valve assembly. New distribution and sprinkler heads shall be installed throughout the new facility.

Electrical

Existing lighting fixtures, wiring devices, panelboards, wiring, and low voltage systems (paging speakers, telecommunication devices, physical access control devices, fire alarm devices, and nurse call devices) within the 3rd floor area of work will be demolished. Certain electrical panelboards will remain within the 3rd floor area of work. Certain branch circuit loads may remain and recircuited to the new branch panelboards. Existing fire alarm terminal cabinet and extender panel shall maintain its condition and operational during construction. Fire alarm terminal cabinet and extender panel are located in the 3rd floor IT room.

New powered equipment, lighting fixtures, wiring devices (lighting control devices, receptacles, etc.), and branch panelboards, including wiring and conduit will be installed by the electrical contractor. New circuit breakers will be installed in existing MCC equipment to serve the new

HVAC equipment. Retained branch circuit loads may be recircuited to the new branch panelboards.

New tele/data devices, cabling and cable tray will be installed and tied back into the existing 3rd floor IT room. The new cable tray and conduit transition will be grounded back to the existing grounding system in the 3rd floor IT room.

New fire alarm initiating devices and notification appliances will be installed and tied back into the existing fire alarm terminal cabinet and extender panel.

New PA speakers will be installed and tied back to the existing PA system. Existing PA system is located in the 3rd floor IT room.

The existing antennas for the wireless pharmacy distribution system (wireless access point) shall be removed for the renovation and reinstalled in their current locations.

New nurse call devices and associated equipment, wiring, and conduit will be installed throughout the renovated space. All components will be connected back to the existing head end nurse call system.

Structural

The structural scope of work involves the installation of the support steel and curbing as it relates to the mechanical equipment, ductwork, and patient lift systems.

BID ITEMS:

Bid Item I, (Base Bid):

General Construction: Renovate Medical Surgical Ward for Patient Privacy:

Work includes the demolition and renovation of approximately 10,000 gross square feet of existing former Medical Surgical space in use as clinic area to accommodate a new

Med/Surg unit with 13 patient rooms with bathrooms. The new space includes patient rooms, doctors’ offices, space for nursing staff, pharmacology areas as well as the various support facilities required by the medical staff.

Electrical Work: Work includes all labor, material, equipment, and supervision to perform the required electrical construction work on this project including the removal of existing lighting, receptacles, wiring panelboards, within the 3rd floor area of work. New equipment, lighting, receptacles, and distribution panels will be installed by the contractor.

New tele/data systems and devices will be installed and tied back into the existing 3rd floor telecom demarcation room. New fire alarm devices will be installed and tied back into the existing fire alarm system.

New PA speakers will be installed and tied back to the existing PA system. The existing antennas for the wireless pharmacy distribution system shall be removed for the renovation and reinstalled in their current locations. New nurse call devices shall also be installed with various components located throughout the renovated space. The new devices shall be wired back to the existing Nurse Call system.

Mechanical Work: Work includes all labor, material, equipment, and supervision to perform the required Mechanical construction work on this project including the demolition of existing fan coil units and other HVAC equipment along with the installation of new ductwork, VAV boxes, Air Handling Unit, steam-to-hot water heat exchanger system for VAV reheat coils, HEPA filters, and isolation and pandemic mode fans.

Modifications to the existing make-up air unit 1-MAU-15 and exhaust fans 1-EF-4 & 5 shall be included to sustain the areas of the Hospital that are outside of the construction area of work. All new plumbing fixtures, piping, medical gas systems, and fire protection systems shall be installed as well.

Construction duration for Bid Item 1 is 400 calendar days for all bid items after the Notice to Proceed.

Bid Item II: Deduct Alternate No. 1: Contractor shall perform all work as described herein

(Bid Item 1 [Base Bid]) except deduct the interior architectural finishes and plumbing, mechanical and electrical work associated with the elevator lobby as indicated in the contract documents. Construction duration for Bid Item II is 370 calendar days after the Notice to

Proceed.

Bid Item III: Deduct Alternate No. 2: Contractor shall perform all work as described in (Bid

Item 1 [Base Bid]) except deduct all work associated with Bid Item II and deduct all existing plumbing piping within the 3rd floor area of work including sanitary drainage, vent and domestic water risers is to be removed and/or replaced as part of the base bid. Deduct alternative 2 excludes the removal and replacement of existing risers unless it is indicated to be relocated.

The VA makes every effort to keep drawings current to existing conditions, however, sometimes changes and updates do not get recorded. In accordance with FAR 52.236-3 (Site Investigation and Conditions Affecting the Work), it is the Contractor’s responsibility to perform field investigations and verify all dimensions, as well as, the site plan information. Construction duration for Bid Item III is 350 calendar days after the Notice to Proceed.

PHASING:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR’S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish the work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.

The Contractor may schedule work Monday through Friday, 0800-1600, not including federal holidays, unless otherwise specified herein. Any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. For work occurring during the regular work week, utility/alarm shut-off can be coordinated between the hours of

0800-1600, Monday through Friday.

For specific phasing details see drawings and specifications.

SITE INFORMATION:

Covid-19 Screening:

Contractors will be treated in the same manner with respect to screening as VA employees and visitors to VA facilities. Screening procedures may vary from location to location. If a contractor refuses screening, they can be denied access to the facility. 38 C.F.R. §

1.218(a)(1) vests the Secretary or his designee with authority to close facilities or portions of facilities that are under the charge and control of VA to the public. This includes the authority to prohibit contractors from entering VA facilities, if they refuse to undergo screening measures.

Additionally, FAR 52.212-4(q) requires contractors to comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under contracts for commercial services and supplies. Also see these FAQs under the “Stop Work” topic for guidance regarding non-performance.

The VA is dedicated to protecting its employees and Veterans from COVID-19. For public health and safety reasons, screening requirements have been implemented in facilities that the contractor may need to access to perform work. Contractors must adhere to these screening procedures the same as VA employees and visitors to the facility. Refer to the CDC website for

Resources for Businesses and Employers.

CONTRACTOR REQUIRMENTS:

Contractor shall be required to maintain a safe environment consistent with VA and OSHA requirements. Ensure that all contractors and subs meet and abide by all government regulations and requirements to include the 10-hour OSHA training for all workers and mandatory 30-hour OSHA certificate for the project superintendent.

Contractor will be required to remove and insure proper disposal of all materials.

Contractor will be working around an occupied healthcare facility in operation 24 hours a day and care will be taken to keep work areas clean and contained.

Contractor shall read and adhere to VA specifications and requirements and provide the necessary sub-contractors skills, materials and labor required to complete the project.

The work required for this project will be performed in accordance with the contract documents, drawings and specifications that are subject to the VA requirements. This includes privacy training, safety training, TB test and all other VA requirements. The VA will provide their existing drawings/documents only as a reference guide. The project is to be completed within the

VA schedule specified in the contract documents.