S02 Salem Lobby Renovation - Bid Documents - Specifications.pdf
PDF 5 MB Posted
- Attached to
- Z1DA--Renovate Main Lobby Federal contract opportunity
- Solicitation number
- 36C24626B0027
About this file
SUMMARY: BID DOCUMENTS - SPECIFICATIONS
This is a comprehensive set of bid documents and specifications for the Salem VA Medical Center Building 143 Lobby Renovation project (Project No. 658-24-104), prepared for the Department of Veterans Affairs by ThinkForm Design Architect LLC and Above Group, Inc. The project is located at 1970 Roanoke Boulevard, Salem, VA 24153, with an anticipated construction period of 365 days divided into four phases.
The specifications cover all divisions of work required for a complete lobby renovation including: selective demolition and removal of existing structures; cast-in-place concrete infill; cold-formed and structural metal framing; wood and finish carpentry; thermal and moisture protection systems; door hardware and accordion folding doors; comprehensive finishes including ceramic/porcelain tiling, resilient flooring, gypsum board, acoustical ceilings, painting, and wall treatments; plumbing fixtures and water distribution systems; HVAC systems with commissioning requirements; electrical installations with interior and emergency lighting; fire suppression and alarm systems; and specialized construction requiring seismic restraint and infection control risk mitigation. The renovation includes updates to multiple spaces: Building 143 Lobby areas (BA-102, BF-101-103, CB-1 through CB-45, CG-25); restrooms (BA-100, BA-101, BB-100, BB-101, BB-121, BB-153); and associated corridors and waiting areas. The documents establish detailed quality control requirements, construction sequencing tied to medical center operations (24/7 functioning), comprehensive safety and health protocols including TB screening and dust control measures, full commissioning of mechanical and electrical systems, extensive testing and balancing requirements, operator training, and a one-year warranty period with defined warranty service priorities. Contractors must comply with all applicable federal regulations, OSHA standards, VA security procedures, and infection control protocols throughout the construction period.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FAR 52.222-90.pdf | ||
| S06 36C24626B0027 0002.pdf | ||
| S05 658-24-104 Questions and Answer_ Renovate Main Lobby.pdf | ||
| S05 ICRA Requirements _ Renovate Main Lobby.pdf | ||
| S05 658-24-104 Mob Area sheets A101. A111. A112.pdf | ||
| S06 36C24626B0027 0001.pdf | ||
| S04 Site Visit 4-17-2026_ Main Lobby.pdf | ||
| S02 36C24626B0027 Renovate Main Lobby.pdf | ||
| S02 Salem Lobby Renovation - Bid Documents - Drawings.pdf | ||
| VAAR 852.204-70_PIV of Contractor Personnel.pdf | ||
| 36C24626B0027.docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID DOCUMENTS
SPECIFICATIONS
BUILDING 143 LOBBY RENOVATION
AT
Salem VAMC
PREPARED FOR
DEPARTMENT OF VETERANS AFFAIRS
1970 ROANOKE BLVD., SALEM, VA 24153
03 February 2026
Project No.: 658-24-104
PREPARED BY
THINKFORM DESIGN ARCHITECT LLC
207 EAST BAY STREET SUITE 311 CHARLESTON SOUTH CAROLINA 29401
PH: 855.821.0274 I ThinkFormArchitects.com
ABOVE GROUP, INC
305 EAST DR SUITE H, MELBOURNE, FL 32904
PH: 321.345.9026 I abovegroupinc.com/
THIS PAGE INTENTIONALLY LEFT BLANK
08-01-2025 VAMC Salem – Building 143 Lobby Renovation BID DOCUMENTS Project No. 658-24-104 03 FEBRUARY 2026
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 10 Table of Contents 08-01 00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects 01-24 01 33 23 Shop Drawings, Product Data, and Samples 06-25 01 35 26 Safety Requirements for Major Projects 05-24 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 04-22 01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
DIVISION 05 – METALS
05 40 00 Cold-Formed Metal Framing 01-21 05 50 00 Metal Fabrications 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17 06 20 00 Finish Carpentry 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 81 00 Applied Fireproofing 07-23 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22 07 95 13 Expansion Joint Cover Assemblies 01-21
Project No. 658-24-104 03 FEBRUARY 2026
00 01 10-2
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 08 - OPENINGS
08 35 13.13 Accordion Folding Doors 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 30 13 Ceramic/Porcelain Tiling 01-21 09 51 00 Acoustical Ceilings 12-18 09 67 23.50 Resinous Terrazzo Flooring (RES-5) 01-21 09 84 33 Sound-Absorbing Wall Units 01-21 09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21 10 21 13 Toilet Compartments 01-21 10 26 00 Wall and Door Protection 01-21 10 28 00 Toilet, Bath, and Laundry Accessories 01-21
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
12 32 00 Manufactured Wood Casework 01-21 12 36 00 Countertops 12-23
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components
01-21
DIVISION 14– CONVEYING EQUIPEMENT
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16 21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 01-23 22 05 23 General-Duty Valves for Plumbing Piping 09-20
Project No. 658-24-104 03 FEBRUARY 2026
00 01 10-3
SECTION NO DIVISION AND SECTION TITLES DATE
22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 40 00 Plumbing Fixtures 05-24
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23 23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 31 00 HVAC Ducts and Casings 03-23 23 37 00 Air Outlets and Inlets 03-23
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 09 23 Lighting Controls 11-22 26 27 26 Wiring Devices 26 51 00 Interior Lighting 03-24
DIVISION 27 – COMMUNICATIONS
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
DIVISION 33 – UTILITIES
DIVISION 34 – TRANSPORTATION
DIVISION 48 – Electrical Power Generation
05-01-20
Project No. 658-24-104 03 FEBRUARY 2026
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
SHEET # SHEET TITLE
GENERAL
G001 COVER SHEET
G002 INTERIM LIFE SAFETY MEASURES, NOTES, & ABBREVIATIONS
G003 INFECTION CONTROL RISK ASSESSMENT
G004 OVERALL PHASING AND STAGING
G005 PHASE 1 & 2
G006 PHASE 3 & 4
G007 INFECTION CONTROL DETAILS
G008 PARTITION TYPES & SECTION DETAILS
GENERAL
S-001 GENERAL NOTES AND ABBREVIATIONS
SS101 STRUCTURAL PLANS AND DETAILS
ARCHITECTURAL
AD101 BASEMENT LOBBY DEMOLITION PLAN
AD102 BASEMENT CORRIDORS DEMOLITION PLAN
AD111 BASEMENT DEMOLITION RCP
AD112 BASEMENT CORRIDORS DEMOLITION RCP & ROOF PLAN
A101 BASEMENT PLAN - LOBBY
A102 BASEMENT PLAN - CORRIDORS
A111 BASEMENT RCP - LOBBY
A112 BASEMENT RCP - CORRIDORS
A131 CAFE & RESTROOMS ENLARGED PLANS & TOILET ACCESSORIES
A301 CONCOURSE/ CAFE ELEVATIONS & 3D VIEW
A401 INTERIOR ELEVATIONS
A501 CASEWORK / HANDRAIL/ WALL PROTECTION DETAILS
A502 EXPANSION JOINT DETAILS
A508 SEISMIC RCP DETAILS
A601 FINISH & DOOR LEGEND, SCHEDULE, NOTES & DETAILS
A602 BASEMENT FINISH PLAN - LOBBY & FINISH BOARD
Project No. 658-24-104 03 FEBRUARY 2026
00 01 15 - 2
A603 BASEMENT FINISH PLAN - CORRIDORS
A604 BASEMENT EQUIPMENT PLAN
A801 3D RENDERINGS
FIRE PROTECTION
FP001 FIRE PROTECTION LEGENDS & SYMBOLS
FP100 FIRE PROTECTION - SPRINKLER ZONES - EXISTING
FX101 FLOOR PLAN - FIRE PROTECTION - DEMOLITION - LOBBY
FX102 FLOOR PLAN - FIRE PROTECTION - DEMOLITION - CORRIDORS
FP101 FLOOR PLAN - FIRE PROTECTION HAZARD CLASSIFICATION - NEW- LOBBY
FP102 FLOOR PLAN - FIRE PROTECTION - HAZARD CLASS - NEW - CORRIDORS
FP501 FIRE PROTECTION DETAILS
PLUMBING
P-001 PLUMBING NOTES, LEGEND, & SYMBOLS
P-101 BASEMENT FLOOR PLAN - PLUMBING - NEW WORK
P-401 ENLARGED FLOOR PLAN NORTH - PLUMBING
P-402 ENLARGED FLOOR PLANS NORTHEAST - PLUMBING
P-403 ENLARGED FLOOR PLANS SOUTH - PLUMBING
P-404 ENLARGED FLOOR PLANS CAFE - PLUMBING
P-501 PLUMBING SCHEDULES AND DETAILS
MECHANICAL
M-001 MECHANICAL NOTES, LEGENDS, & SYMBOLS
MD101 FLOOR PLAN - MECHANICAL - DEMOLITION - LOBBY
MD102 FLOOR PLAN - MECHANICAL - DEMOLITION - CORRIDORS
MH101 FLOOR PLAN - MECHANICAL - NEW WORK - LOBBY
MH102 FLOOR PLAN - MECHANICAL - NEW WORK - CORRIDORS
M-501 MECHANICAL SCHEDULES AND DETAILS
ELECTRICAL
E-001 ELECTRICAL LEGENDS & SYMBOLS
E-002 ELECTRICAL GENERAL NOTES
ED101 FLOOR PLAN - LIGHTING - DEMOLITION
ED102 FLOOR PLAN - ELECTRICAL EQUIPMENT - DEMOLITION
EL101 FLOOR PLAN - LIGHTING - NEW WORK
EP101 FLOOR PLAN - ELECTRICAL EQUIPMENT - NEW WORK
Project No. 658-24-104 03 FEBRUARY 2026
00 01 15 - 3
E-501 ELECTRICAL DETAILS
E-601 ELECTRICAL DIAGRAM
E-801 ELECTRICAL SCHEDULES
E-802 ELECTRICAL SCHEDULES
Grand total: 59
- - - END - - -
11-01-21
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for renovate Main Lobby – Building 143 as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the COR
C. Offices of ThinkFor Architects, as Architect-Engineers, will render certain technical services during construction.
Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, BASE BID: Work includes selective demolition and renovations for the renovation in a full cosmetic of the
Main lobby Building 143 located in the basement floor.
1. Scope of work: Provide renovation of the areas below as
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -2 detailed in the construction package including contract drawings, contract specifications for upgrade to the following areas:
a. Building 143 Lobby BA-102, BF-101, BF-102, BF-103 CB-
1, CB-2 CB-4, CB-5, CB-7, CB-8, CB-8A, CB-9, CB-10,
CB-11, CB-12, CB-13, CB-13A, CB-14, CB-15, CB-45, CG-
25 removal and replacement of ceiling tiles, flooring, and baseboard, removal of wallpaper, new column finishes, remove and replace handrails, wall guards, and corner protectors. Renovation of restrooms BA100, BA101, BB100, BB101, BB-121 and BB153.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -3
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees.
This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The
General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation.
See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -4
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of
“sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b) “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.
Access shall be restricted to picking up and dropping off materials and supplies.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -5
2. A limited number of permits shall be issued for General
Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical
Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The
Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the
Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -6 from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR .
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -7
Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the
COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -8
The Approximate Total Construction Period Is 365 Days.
PHASE 1:
1. Phase 1a (15 days) - plan-east portion of corridor cb-
45 and lobby cb-5.
2. Phase 1b (30 days) - cafe ba-102 and portion of lobby cb-5.
3. Phase 1c (20 days) - men's toilet ba-101, women's toilet ba-100, and corridor cg-25.
4. Phase 1d (10 days) - plan-north portion of corridor cg-25. This phase can occur concurrently with any of the above phases of work if necessary.
5. Phase 1e (5 days) - plan-north portion of corridor cb-45. This phase can occur concurrently with any of the above phases of work if necessary.
6. Phase 1f (1 day) - plan-east portion of corridor cb-
45. This portion is to commence and be completed entirely during off hours of operation. This entrance is to be entirely open and functional during normal business hours. Spaces to be punched prior to removal of temporary construction barriers. Once completed and approved by the va, this phase of work will be occupied asap, and gc can move onto the next phase.
(typical after each phase.)
PHASE 2:
1. Phase 2a (12 days) - plan-south portion of lobby cb-
2. Phase 2b (20 days) - family toilet and waiting cb-12
3. Phase 2c (12 days) - waitng cb-13 and receipton cb-1
4. Phase 2d (12 days) - waiting cb-14.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -9
5. Phase 2e (20 days) - men's toilet bb-121, women's toilet bb-101, and plan-west portion of corridor cb-
15. This phase can occur concurrently with phase 2b.
6. Phase 2f (10 days) - plan-west portion of corridor cb-15.
7. Phase 2g (2 days) - plan-west portion of corridor cb-15 and plan-east portion of stair 6.
8. Phase 2h (10 days) - plan-east portion of vestibule cb-1, entrance cb-2, and plan south portion of lobby cb-5.
9. Phase 2i (10 days) - plan south portion of corridor cg-25.
PHASE 3:
1. PHASE 3A (12 DAYS) - PLAN-NORTH PORTION OF LOBBY CB-
2. PHASE 3B (12 DAYS) - PLAN-WEST PORTION OF WAITING
CB-10, CONSULT BF-102 AND CONSULT BF 103.
3. PHASE 3C (12 DAYS) - PLAN-EAST PORTION OF WAITING
CB-10 AND CONSULT BF-101.
4. PHASE 3D (12 DAYS) - WAITING CB-9.
5. PHASE 3E (10 DAYS) - PLAN-EAST PORTION OF CORRIDOR
CB-45.
6. PHASE 3F (10 DAYS) - PLAN-EAST PORTION OF CORRIDOR
CB-45.
7. PHASE 3G (10 DAYS) - PLAN-WEST PORTION OF VESTIBULE
CB-1 AND ENTRANCE CB-2. THIS PHASE CAN OCCUR
CONCURRENTLY WITH ANY OF THE ABOVE PHASES IN PHASE
3.
8. PHASE 3H (20 DAYS) - PLAN-SOUTH PORTION OF LOBBY CB-
5 AND INFO CB-4.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -10
9. PHASE 3I (10 DAYS) - PLAN-EAST PORTION OF CORRIDOR
CB-15.
10. PHASE 3J (10 DAYS) - PLAN-EAST PORTION OF
CORRIDOR CB-15.
11. PHASE 3K (10 DAYS) - PLAN-EAST PORTION OF
CORRIDOR CB-15.
12. PHASE 3L (10 DAYS) - PLAN-EAST PORTION OF
CORRIDOR CB-15.
PHASE 4:
1. PHASE 4A (10 DAYS) - PLAN-WEST PORTION OF CORRIDOR
CB-45.
2. PHASE 4B (12 DAYS) - WAITING CB-7 AND PLAN-WEST
PORTION OF CORRIDOR CB-45.
3. PHASE 4C (12 DAYS) - WAITING CB-8 AND RECEPTION CB-
8A.
4. PHASE 4D (2 DAYS) - PLAN-WEST PORTION OF STAIR 6.
5. PHASE 4E (2 DAY)- EXTENT OF PRESSURE WASHING
EXTERIOR, SEE 1/AD101.
J. Building No.143 will be occupied during performance of work but immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -11 such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
K. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or
Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -12
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center
Director’s prior knowledge and written approval. Refer to
Electrical specification Sections for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical
Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -13 which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;
so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -14
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by
Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING
SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-
4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.
They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -15
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the
Government are noted on drawings or in specifications as items to be stored. Items that remain property of the
Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the
Contractor and be removed by Contractor from Medical
Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.
When rooms and spaces are vacated by the Department of
Veterans Affairs during the alteration period, such items
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -16 which are NOT required by drawings and specifications to be either relocated or reused will be removed by the
Government in advance of work to avoid interfering with
Contractor's operation.
4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl
(PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental
Protection Agency (EPA) and the Department of
Transportation (DOT) as outlined in Code of Federal
Regulation (CFR), Titled 40 and 49 respectively. The
EPA's Toxic Substance Control Act (TSCA) Compliance
Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform Hazardous Waste
Manifest (EPA Form 8700-22), along with the Uniform
Hazardous Waste Manifest Continuation Sheet (EPA Form
8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the
Manifest to the Medical Center's Chief.
a) Copies of the following listed CFR titles may be obtained from the Government Printing Office:
40 CFR 261 ....Identification and Listing of Hazardous
Waste
40 CFR 262 ....Standards Applicable to Generators of
Hazardous Waste
40 CFR 263 ....Standards Applicable to Transporters of
Hazardous Waste
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -17
40 CFR 761 ....PCB Manufacturing, Processing, Distribution in Commerce, and use
Prohibitions
49 CFR 172 ....Hazardous Material tables and Hazardous
Material Communications Regulations
49 CFR 173 ....Shippers - General Requirements for
Shipments and Packaging
49 CRR 173 ....Subpart A General
49 CFR 173 ....Subpart B Preparation of Hazardous
Material for Transportation
49 CFR 173 ....Subpart J Other Regulated Material;
Definitions and Preparation
TSCA ..........Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting
Officer.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -18
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL
CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage
Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and
Responsibilities," which is included in General Conditions.
A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the
(appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -19 specified. Some requirements involve the Contractor's method of operations and operations planning and the
Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -20 left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by
Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -21
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21
Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting
Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the
Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the
Contractor, subcontractors, manufacturers or suppliers involved.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -22
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of
Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and
Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -23
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment
Bonds must remain effective throughout the construction period
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the
Government at the contractor’s expenses, the Contracting
Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -24 cause for the Contracting Officer to proceed against the
Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the
Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the
Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service
Requirements:
E. Following oral or written notification by the Contracting
Officer, the Contractor shall respond to construction warranty service requirements in accordance with the
“Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -25 any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within
4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within
8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
1) Fire suppression systems.
2) Fire alarm system(s).
b) Code 1-Air Conditioning Systems
1) Air conditioning leak in part of the building, if causing damage.
2) Air conditioning system not cooling properly.
c) Code 1 Doors
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -26
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
d) Code 1-Electrical
1) Power failure (entire area or any building operational after 1600 hours).
2) Security lights.
3) Smoke detectors.
e) Code 2-Electrical
1) Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).
f) Code 1-Gas
1) Leaks and pipeline breaks.
g) Code 1-Heat
1) Power failure affecting heat.
h) Code 1-Plumbing
1) Hot water heater failure.
2) Leaking water supply pipes
i) Code 2-Plumbing
1) Flush valves not operating properly
2) Fixture drain, supply line or any water pipe leaking.
3) Toilet leaking at base.
j) Code 3- Plumbing
1) Leaky faucets.
k) Code 3-Interior
1) Floors damaged.
2) Paint chipping or peeling.
3) Casework damaged.
l) Code 1-Roof Leaks
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -27
1) Damage to property is occurring.
m) Code 2-Water (Exterior)
1) No water to facility.
n) Code 2-Water (Hot)
1) No hot water in portion of building listed.
o) Code 3
1) All work not listed above.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating.
Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -28
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on
Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by
COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -29 determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the
Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the
Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
Project No. 658-24-104 03 FEBRUARY 2026
01 00 00 -30
1.15 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The
Contractor shall carefully conserve any utilities furnished without charge.
B. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .