S02 Final Statement of Work.doc
DOC document 75 KB Posted
- Solicitation number
- 36C24124B0047
About this file
This document is a Statement of Work (SOW) for the Boiler Plant Steam Pressure Reducing Valve (PRV) Stations #1 and #2 Replacement Project at the VA Connecticut Healthcare System in West Haven, CT. The project's scope includes replacing the steam PRV stations to address calibration, adjustment, and safety issues due to the age and operating conditions of the existing equipment.
The contractor will be responsible for providing all labor, materials, and services to size, select, and install the new PRV stations, including piping, valves, instrumentation, and other associated components. Key requirements include submitting design drawings, performing field measurements, prefabricating offsite, completing installation tie-ins during a steam shutdown, and providing commissioning, radiographic testing, and documentation. The work must comply with all applicable federal, state, and local codes and standards, as well as VA design guides and specifications. The contract has a period of performance of 365 days from the notice to proceed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24124B0047 0006.docx | DOCX document | |
| 36C24124B0047 0005.docx | DOCX document | |
| 36C24124B0047 0004.docx | DOCX document | |
| 36C24124B0047 0003.docx | DOCX document | |
| 36C24124B0047 0002.docx | DOCX document | |
| S04 Sign-in Sheet Site Visit Walkthrough 07262024.pdf | ||
| 36C24124B0047 0001.docx | DOCX document | |
| S02 Specification 232111 02.docx | DOCX document | |
| S02 DVA Steam Heating Hot Water and Outside Distribution Systems Design Guide.pdf | ||
| S02 Wage Determination CT20240023 07052024.pdf | ||
| S02 VHA PCRA 2023 689-24-130 PRVs 1 and 2 Replacement located in Boiler Plant - Copy.pdf | ||
| S02 Construction Safety Guide Book.pdf | ||
| Sketch-01 - Copy.png | PNG image | |
| 36C24124B0047_2.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Boiler Plant Steam Pressure Reducing Valve (PRV) Stations #1 and #2 Replacement Project 689-24-130-BoilerPlant PRV Stations #1 and #2 Replacement
A. GENERAL INFORMATION
1. Title of Project: 689-24-130 BoilerPlant Steam PRV Stations #1 and #2 Replacement
2. Project Location: VA Connecticut Healthcare System, 950 Campbell Avenue, West Haven, CT 06516
3. Background: There have been repeated issues with calibration and adjustment of the steam PRV stations and have safety deficiencies due to age and operating conditions. The purpose of this project is to replace the stations and correct critical safety deficiencies.
4. Scope of Work: The contractor shall provide all labor, supervision, materials, equipment, tools, services necessary to size, select pressure reducing valves, shut-off valves, strainers, safeties, steam traps, flow meter and other associated steam and condensate components contained within the 2 steam pressure reducing stations located within the Boiler Plant.
a) Provide piping and instrumentation diagram, complete equipment schedule and sizing in PDF and CAD formats. Package shall be submitted to the VA within (30) days following the notice to proceed.
b) Perform all necessary field measurements and investigations to assure that the equipment and assemblies will meet contract requirements and will fit the space available.
c) Provide demolition plan, shop drawings, weld map, equipment list drawing and as built plans in PDF and CAD formats, approved by an independent engineer. The engineer shall be a subcontractor of the General Contractor and shall report to and be paid by the General Contractor.
d) All work shall be performed offsite. Prefabricate all piping, perform radiographic testing of 100% of the butt-welded joints and pressure test all piping (including header, spool pieces, steam trap assembly piping, etc.) offsite. All piping shall be assembled onsite at the VAMC, ensure to leak test all joints after the tie-ins.
e) Complete the steam PRV stations installation tie-ins during one steam shutdown. Steam shutdown shall only occur between May 1st through September 30th. 30 days advance notice required. Maximum duration – not to exceed Friday 7:00pm to Sunday 7:00pm. Cool down and reheat times shall be included in this time frame, approximately 2 hours each.
f) Butt weld all piping above 2-1/2” and above, Butt weld or socket weld all piping 2” or less diameter. Raised faced flanges or unions are required to permit ease of removal and servicing working parts without disturbing connecting piping. If threaded pipes required (shall be Schedule 80), request shall be in writing to COR for approval.
g) All threaded pipes shall be schedule 80.
h) Flanges shall be forged steel weld neck flanges.
i) Steam Trap shall have raised faced flanged ends.
j) Pressure Reducing Valves in steam PRV Stations shall have stainless steel diaphragm.
k) Specification SECTION 23 21 11, BOILER PLANT PIPING SYSTEMS and sections listed under 1.2 Related work shall be based as the main specifications. The most stringent requirements shall always apply including unedited sections.
l) Provide removable insulation jackets for the new PRVs and steam trap assemblies.
m) Provide aluminum jacket over insulation from zero to 6 feet above floor.
n) Trap failure indications and feedback of all flow meters shall be tied into building automation system.
o) Provide an approved independent commissioning agency. The commissioning agency shall be a subcontractor of the General Contractor and shall report to and be paid by the General Contractor and identified by the General Contractor within sixty (60) days after the Notice to Proceed. The commissioning process shall encompass and coordinate the written PRV station startup procedure, system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training.
p) Provide an approved independent testing firm regularly engaged in radiographic testing to perform the radiographic examination of pipe joint welds on behalf of the VA. Testing firm shall be a subcontractor of the General Contractor and shall report to and be paid by the General Contractor and identified by the General Contractor within sixty (60) days after the Notice to Proceed. To receive approval onsite radiographic testing for tie-in welds, provide:
1. Up-to-date radiation safety training and certification.
2. Current NRC [or Agreement State] License to possess and use the source(s) they plan to bring to onsite testing.
3. Agreement with the CT DEEP in terms of using their source(s) in the State of CT.
4. Radiation Safety Officer to respond to emergencies in a timely manner.
5. Multiple radiation detectors that are up-to-date and in calibration, to monitor themselves, the source, and the perimeter for radiation doses.
6. Passed ‘leak testing’.
7. Written emergency response plan in case the radioactive source doesn’t retract back into its shield, or for other emergencies.
8. A security plan to prevent loss or theft of the radioactive material.
9. Written method/plan for determining the size of the restriction area and provide drawing showing the restriction area. Evaluation of the restricted area needs to include floors above, and adjacent to the radiation imaging areas.
10. Signs, ropes, and other barriers to clearly define the restricted areas to keep people away.
q) Perform radiographic testing of 100 percent of the welds. All radiographs shall be reviewed and interpreted by an ASNT Certified Level III radiographer, employed by the testing firm, who shall sign the reading report.
r) Ensure construction materials meet the domestic content requirements to comply with the Buy America Act (See FAR Subpart 25.2)..
s) Provide Construction work plan, Schedule, Safety Plan (Accident Prevention Plan), Waste Disposal Plan, OSHA worker certifications and training, Welder Qualification, Safety Data Sheets (SDS), weld X-ray inspection report and pressure test data from start to finish recorded by digital pressure recorder with full record and data to be provided to the VA.
t) Material submittals shall include the applicable VA specification section with applicable paragraph identification and shall include clear identification of specific materials proposed for project.
1. Manufacturers’ Literature and Data including: Full item description and optional features and accessories of the complete system including, but not limited to, dimensions, weights, materials applications, standard compliance, model numbers, size and capacity. Submit Pipe and tubing, with specification, class or type, and schedule. Pipe fittings, including miscellaneous adapters and special fittings. Flanges, gaskets and bolting, Valves of all types, Strainers, Gauges, insulation, and all other steam system components.
The project shall be accomplished in compliance with all applicable standards and codes specified in the VA Design Guides and Manuals and all applicable VA requirements. VA specifications can be found at the VA Technical Information Library: Technical Information Library (TIL) - Office of Construction & Facilities Management (va.gov).
The most stringent requirements of the SOW, local codes or the specifications requirements shall always apply. Any conflicts shall be brought to the attention of the COR.
REFERENCES BUT NOT LIMITED TO:
· DVA Steam, Heating Hot Water, and Outside Distribution Systems design manual, May 1, 2024 , Volume 1 STEAM BOILERS (Steam Generating Systems)
· DVA HVAC design NOVEMBER 1, 2017, Rev. March 1, 2024.
· DVA Steam Pressure Reducing Station detail.
· DVA Steam Trap Assembly detail.
· ASME Boiler & Pressure Vessel Code.
· ASME B31.1 – Power Piping.
· International Mechanical Code.
· 01 00 00 General Requirements
· 01 33 23 Shop Drawings, Product Data, and Samples
· 01 35 26 Safety Requirements
· 01 42 19 Reference Standards
· 01 45 00 Quality Control
· 01 45 29 Testing Laboratory Services
· 01 45 35 Special Inspections
· 01 57 19 Temporary Environmental Controls
· 01 74 19 Construction Waste Management
· 01 81 13 Sustainable Construction Requirements
· 01 91 00 General Commissioning Requirements
· 02 41 00 Demolition
· 02 82 11 Traditional Asbestos Abatement
· 07 84 00 Firestopping
· 23 05 10 Common Work Results for Boiler Plant and Steam Generation
· 23 05 11 Common Work Results for HVAC
· 23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
· 23 07 11 HVAC and Boiler Plant Insulation
· 23 08 00 Commissioning of HVAC Systems
· 23 21 11 Boiler Plant Piping Systems
· 23 50 11 Boiler Plant Mechanical Equipment
· 25 10 10 Advanced Utility Metering System
· 32 90 00 Planting
· 33 08 00 Commissioning of Site Utility Systems
· 33 63 00 Steam Energy Distribution
The contract further requires the vendor to plan for, establish and implement procedures and scheduling practices to minimize, to the greatest extent possible, the impact to the work performed at the medical center.
GENERAL SPECIFICATIONS
1. Standards: Contractor shall meet all Federal/ VA, state, and local standards, codes, and requirements. All design and installation shall be per master specifications and design manuals, and design guides found on the VA Technical Information Library.
2. Parking: Parking is rigidly controlled throughout the Medical Center. Parking of vehicles in other than the specified areas will result in said vehicles being towed at the owner’s expense off the Medical Center grounds.
3. Staging Areas: Onsite staging areas, including storage and dumpster locations, will not be provided, or allowed for this contract.
4. Safety: The contractor shall be responsible for developing their own safety plan for all site work, including asbestos awareness training and procedures when encountering hazardous materials (i.e. asbestos, lead, etc.). Contractor shall notify VA of any concerns to suspect hazardous or regulated materials.
5. Scheduling of Work: Upon receipt of the contract award, the Contractor must contact the CO and his/her COR to schedule the work.
6. Work Completion: All work under this contract shall be completed within 365 days following the award of the contract and the issuance by the VA of the “Notice to Proceed” letter. Completion of the contract includes inspection of all installed project features by the VA COR or designated alternate representative to ensure compliance with all VA requirements.
7. Material & Workmanship Quality: All materials and workmanship shall comply with all applicable codes and standards. All work shall be done in a first-class manner according to the best trade practices and to the satisfaction of the COR.
Records Management:
Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.
Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.
Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.
Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.
The Government Agency owns the rights to all data/records produced as part of this contract.
The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.
Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].
No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.
Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.
End of SOW
pg. 2
File details come from the government source that posted it. Updated .