This document outlines a federal contract opportunity for electrical services at a Veterans Affairs Medical Center. The Department of Veterans Affairs is seeking to provide a new electrical service for a 500-ton trailer mounted chiller at the Wilkes-Barre VAMC in Pennsylvania. The scope of work includes all construction services such as project management, labor, materials, testing, and reports to meet applicable Federal, State and Local codes as well as VA Master Specifications. The magnitude of the project is estimated between $250,000 to $500,000 with a period of performance of approximately 180 calendar days from the issuance of the Notice to Proceed. This is a 100% service-disabled veteran small business set aside where the SDVOSB must be registered on SAM.gov and VetBiz.gov. The NAICS code is 238210 and the small business size standard is $16.5 million. A pre-proposal conference will be held within two weeks of solicitation issuance. The solicitation will be posted on August 16, 2021 on betasam.gov. Questions should be directed to the specified contracting officer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Existing Exterior 3000 Amp - 480V Boiler Plant Switchboard. Provide a new 1200Amp Eaton MDS-612 drawout circuit breaker in existing space, trip set to 1000 amps

24"x24"x8" Nema 3R pullbox (typical)

P.B

P.B.

P.B.

P.B.

1200 Amp-480V-3Phase Non-fused Heavy Duty Nema 3R lockable disconnect switch mounted on unistrut against building wall at ground level. Terminate (3)-3" Aluminum rigid conduits with chiller feeders at disconnect switch.

Location of 500 ton chiller. Provide chiller feeders from 1200 Amp disconnect switch to chiller electrical power supply location and terminate. Feeders shall be run in liquid tight flexible metal conduit.

(3)-3" Aluminum rigid conduits with feeders shall run from boiler plant switchboard to 500 ton chiller location via rooftops.

Provide pipe support blocks under all rooftop conduits.

(3)-3" Aluminum rigid conduits with feeders shall be mounted to exterior building wall between first and second floors and drop to 1200 Amp disconnect switch.

(3)-3" Aluminum rigid conduits with feeders shall run from boiler plant switchboard to 1200 Amp disconnect switch at 500 ton chiller location. Conduits shall rise above existing boiler plant wall mounted wire way, run along exterior building wall and drop to roof level below.

Note:

Refer to paragraph 12.c in the Statement of Work for detailed information associated with numerical references on this pdf.

ELECTRICAL SERVICE FOR 500 TON

CHILLER - BUILDING 1 NORTH WING

NO SCALE

3 4

X

+920.66'

+880.00'

+894.64'

+894.64'

+894.31'