This document outlines a federal contract opportunity for electrical services at a Veterans Affairs Medical Center. The Department of Veterans Affairs Medical Center in Wilkes-Barre, Pennsylvania is soliciting bids to provide a new electrical service for a 500-ton trailer-mounted chiller. The scope of work includes all construction services such as administration, supervision, project management, labor, materials, tools, equipment, testing and reports to install electrical conduits and feeders running from an existing boiler plant switchboard to the chiller location. The contract is set aside for service-disabled veteran small businesses and has an estimated value between $250,000 and $500,000. The period of performance is approximately 180 calendar days from the issuance of the notice to proceed. Interested parties should direct any questions to the specified contracting officer by the stated deadline while referencing the synopsis and project number in the subject line.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Existing Exterior 3000 Amp - 480V Boiler Plant Switchboard. Provide a new 1200Amp Eaton MDS-612 drawout circuit breaker in existing space, trip set to 1000 amps

24"x24"x8" Nema 3R pullbox (typical)

P.B

P.B.

P.B.

P.B.

1200 Amp-480V-3Phase Non-fused Heavy Duty Nema 3R lockable CAM Lock Connection Switch at ground level. Terminate (3)-3" Aluminum rigid conduits with chiller feeders at switch.

Location of 500 ton chiller.

(3)-3" Aluminum rigid conduits with feeders shall run from boiler plant switchboard to 500 ton chiller location via rooftops.

Provide pipe support blocks under all rooftop conduits.

(3)-3" Aluminum rigid conduits with feeders shall be mounted to exterior building wall between first and second floors and drop to 1200 Amp CAM Lock Connection Switch.

(3)-3" Aluminum rigid conduits with feeders shall run from boiler plant switchboard to 1200 Amp CAM Lock Connection Switch at 500 ton chiller location. Conduits shall rise above existing boiler plant wall mounted wire way, run along exterior building wall and drop to roof level below.

Note:

Refer to paragraph 12.c in the Statement of Work for detailed information associated with numerical references on this pdf.

ELECTRICAL SERVICE FOR 500 TON

CHILLER - BUILDING 1 NORTH WING

NO SCALE

X

+920.66'

+880.00'

+894.64'

+894.64'

+894.31'

Amendment 001 Revisions