This is a solicitation for repair work at a Department of Veterans Affairs facility. The solicitation seeks bids for a project to repair roads, sidewalks, and parking areas at the Chalmers P. Wylie Columbus VA Ambulatory Care Center in Columbus, Ohio. The period of performance is 60 calendar days from notice to proceed. The project magnitude is between $100,000 and $250,000. Bids are due by April 14, 2023. The work must be performed in accordance with the drawings and specifications provided. The project is reserved for a service-disabled veteran owned small business. All bidders must be verified in VETBIZ and registered in SAM by the due date and time of award to be eligible.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S02. Drawings.pdf | ||
| S02. Wage Determination.pdf | ||
| S02. 36C25023R0126.pdf | ||
| S02. RFI Form.docx | DOCX document | |
| S02. Bid Opening Instructions.docx | DOCX document | |
| S02. Safety.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR ROADS, SIDEWALKS, AND
PARKING AREAS
Project # 757-21-201 For the
Columbus VA - Chalmers P. Wylie Outpatient Clinic 420 North James Road Columbus, OH 43219
PROJECT MANUAL
BID DOCUMENTS
February 22, 2023
Veterans Health Administration
PROJECT CONTACTS:
COR I OWNER: Columbus VA Chalmers P. Wylie Outpatient Clinic Attn: Jennifer Miller 420 North James Road Columbus, OH 43219 Phone: 614-388-7332 Email: Jennifer.Miller197e76@va.gov
ARCHITECT, CIVIL
ENGINEER:
Columbus VA Chalmers P. Wylie Outpatient Clinic Attn: Jennifer Miller 420 North James Road Columbus, OH 43219 Phone: 614-388-7332 Email: Jennifer.Miller197e76@va.gov
ISSUE DATE: February 22, 2023 mailto:Jennifer.Miller197e76@va.gov mailto:Jennifer.Miller197e76@va.gov
VA Project No. 757-21-201 Repair Roads, Sidewalks, and Parking Areas Bid Documents: 01-31-23
Department of Veterans Affairs Columbus VA Healthcare System Columbus, OH
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 02-23
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 03-20 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 09-19 01 45 00 Quality Control 03-19 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 07-19
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Cover Assemblies 02-16
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 17 23 Pavement Markings 08-16
32 17 23.33 Pavement Markings Materials - Thermoplastic 08-16
Repair Roads, Sidewalks, and Parking Areas Bid Documents: 01-31-2023
Department of Veterans Affairs Columbus VA Healthcare System
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 33 - UTILITIES
33 40 00 Storm Sewer Utilities 12-17
Repair Roads and Sidewalks
Department of Veterans Affairs Columbus VA Healthcare System
00 01 15 - 1
SECTION 00 01 15
Bid Documents: 01/31/23 05-01-20
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
GENERAL
G-001 COVER SHEET
CIVIL
CS-100 DEMOLITION AND REPAIR OF SIDEWALKS SITE LOCATION MAP
CS-101 DEMOLITION AND REPAIR OF SIDEWALK SITES B, C, D
CS-102 DEMOLITION AND REPAIR OF SIDEWALK SITES E, F, G, H
CS-103 DEMOLITION AND REPAIR OF SIDEWALK SITES J, K, L, M
CS-104 DEMOLITION AND REPAIR OF SIDEWALK SITES N, O, P, Q
CS-105 DEMOLITION AND REPAIR OF SIDEWALK SITE O
CS-106 NEW SIDEWALK WEST SIDE R, S
CS-107 DEMOLITION AND REPAIR STORM CATCH BASINS
CS-108 SITE PARKING
CS-109 PAVEMENT MARKING DETAILS
- - - END - - -
Department of Veterans Columbus VA Healthcare Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and Parking Areas Bid Documents: 02-22-2023
01 00 00 -1
SECTION 01 00 00
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -2
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 Safety Requirements
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 RESTORATION
1.10 PHYSICAL DATA
1.11 PROFESSIONAL SURVEYING SERVICES
1.12 LAYOUT OF WORK
1.13 AS-BUILT DRAWINGS
1.14 WARRANTY MANAGEMENT
1.15 USE OF ROADWAYS
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.17 TEMPORARY TOILETS
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
1.19 NEW TELEPHONE EQUIPMENT
1.20 TESTS
1.21 INSTRUCTIONS
1.22 GOVERNMENT-FURNISHED PROPERTY
1.23 RELOCATED EQUIPMENT or ITEMS
1.24 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.25 CONSTRUCTION SIGN
1.26 SAFETY SIGN
1.27 PHOTOGRAPHIC DOCUMENTATION
1.28 FINAL ELEVATION Digital Images
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -3
1.29 HISTORIC PRESERVATION
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -4
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the reconfiguration of the perimeter roadway, extension of a medium voltage electrical system, expansion and renovation of the
Engineering Building, closure and renovation of Washington
Street, additional paving and striping as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.
C. Offices of Guidon Design, Inc., as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by the contractor, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -5
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction of Parts I, II, III, and IV with regards to alterations, roads, walks, grading, drainage, utilities, fences, gates, building expansion and renovation and all necessary removal of existing structures and construction and certain other items.
BID ALTERNATE A: WEST CAMPUS SIDEWALK
BID ALTERNATE A CONSISTS OF ALL WORK IN THE BASE BID EXCEPT DO NOT
CONSTRUCT THE WEST SIDEWALK AS SHOWN ON SHEETS: CS104C, CG104C,
CJ104C, AND CS501 (CONCRETE SIDEWALK DETAIL) SEE SHEETS CS104C,
CG104C, CJ104C AND CS501(CONCRETE SIDEWALK DETAIL).
BID ALTERNATE B: NORTH PARKING LOT STRIPING
BID ALTERNATE B CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE A,
AND DO NOT REMOVE AND REPLACE PAVEMENT MARKINGS IN THE NORTH PARKING
LOT. SEE SHEETS CD104A AND CS104A.
BID ALTERNATE C: SITE LIGHTING
BID ALTERNATE C CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE B,
AND DO NOT CONSTRUCT SITE LIGHTING IMPROVEMENTS AS SHOWN ON SHEET
ES104B. SEE SHEET ES104B
BID ALTERNATE D: TRAILER UTILITIES
BID ALTERNATE D CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE C
AND DO NOT CONSTRUCT ELECTRICAL POWER FOR MOBILE TRAILERS. SEE SHEETS
EE020, ES104A.
BID ALTERNATE E: ENGINEERING BUILDING INTERIOR IMPROVEMENTS
BID ALTERNATE E CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE D
AND DO NOT PERFORM WORK ON ENGINEERING BUILDING INTERIOR. SEE SHEETS
SI002, SB103, SF103, SB501, AE001, AE002, AE003M AE101, AD103, AE103A,
AE103B, AE113, AE203, AE303, AE503, AE603, AI103, EL103, EP103, FP103,
FP103A, FP103B, HH003, HD103, HH103, HH113, HH503, HH603, PP03, PD103,
PP103, PP603, PP903, TT003, TT013, TT103.
BID ALTERNATE F: ENGINEERING BUILDING ADDITION
BID ALTERNATE F CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE E
AND DO NOT CONSTRUCT ENGINEERING BUILDING ADDITION. SEE SHEETS CD103.
CS103, CG103, CU103, CJ103 SI001, SI002, SB103, SF103, SB501, AE001,
AE002, AE003M AE101, AD103, AE103A, AE103B, AE113, AE203, AE303,
AE503, AE603, AI103, EL103, EP103, FP103, FP103A, FP103B, HH003,
HD103, HH103, HH113, HH503, HH603, PP03, PD103, PP103, PP603, PP903,
TT003, TT013, TT103, EE020.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -6
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at
Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the
Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -7 project including toolboxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See
Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting
Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of
Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the
VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -8
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted
24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the
Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -9 temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workers are subject to rules of the Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -10
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
All such actions shall be coordinated with the COR or Utility
Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day
7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the
Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor, as follows:
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -11
PART I: PERIMETER ROAD:
WORK ON PERIMETER ROAD SHALL BE THE FIRST PHASE OF THE OVERALL PROJECT. ANY CLOSURES OF PERIMETER ROAD SHALL BE COORDINATED WITH THE COR. PART I AND II CAN BE CONSTRUCTED CONCURRENTLY. COORDINATE WITH THE COR. ALL WORK IN PHASE I MUST BE COMPLETE BEFORE
BEGINNING WORK ON PHASE III AND IV.
NOTES:
CONTRACTOR SHALL PHASE THE WORK FOR THE VA PERIMETER ROAD IMPROVEMENTS TO MAINTAIN SECURITY FOR THE VA AND ACCESS TO THE DSCC PROPERTY AT ALL TIMES. CONSTRUCTION IMPACTING
GOLF COURSE MUST COORDINATED IN ADVANCE WITH DM-FCW
PART 1A: CONSTRUCT NEW ROADWAY, SECURITY AND GOLF FENCE FOR DSCC AND CONSTRUCT NEW
PERIMETER ROADWAY.
1. CONTRACTOR SHALL INSTALL NEW ITEMS ON THE DSCC CAMPUS WHICH INCLUDE REMOVAL OF EXISTING TREES AS NECESSARY FOR THE NEW UTILITY ROAD, AND REPLACEMENT OF SECURITY
AND GOLF COURSE FENCE.
a. TREE REMOVAL MUST OCCUR BETWEEN OCTOBER 1ST AND MARCH 31ST.
b. THE NUMBER OF TREES GREATER 2.5" DIAMETER DEMOLISHED MUST BE REPLACED
ALONG THE EAST OF THE NEW DRIVE (DSCC SIDE}.
2. FOLLOWING INSTALLATION OF SECURITY FENCE CONTRACTOR SHALL DEMOLISH EXISTING
SECURITY FENCING TO ALLOW FOR CONSTRUCTION OF NEW VA PERIMETER ROAD DURING THIS
PHASE.
3. INSTALL NEW FIRE HYDRANTS BEFORE REMOVING EXISTING HYDRANT.
PART 1B: DEMOLISH EXISTING DSCC ROAD FENCES, AND VA PARKING AS NECESSARY TO CONSTRUCT
NEW ACCESS ROADS, PARKING LOTS, AND UTILITIES.
1. DEMOLISH EXISTING ITEMS AS NECESSARY TO RECONFIGURE PARKING LOTS AND ROADWAYS
AROUND THE ENGINEERING BUILDING.
2. CONTRACTOR TO MAINTAIN ACCESS FOR EMERGENCY VEHICLES AND DELIVERIES ALONG
WASHINGTON STREET AT ALL TIMES.
3. PEDESTRIAN ACCESS TO ENGINEERING BUILDING SHALL BE MAINTAINED FOR VA EMPLOYEES.
PART II - SECONDARY ELECTRICAL FEED:
THIS PHASE CONSISTS OF INSTALLATION OF THE SECONDARY ELECTRICAL FEED TO THE VA CAMPUS AND WILL INCLUDE INSTALLATION OF ALL POLES, POWER LINES, AND CONNECTIONS. PHASES I AND II MAY
BE CONSTRUCTED CONCURRENTLY.
1. TREE REMOVAL MUST OCCUR BETWEEN OCTOBER 1ST AND MARCH 31ST.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -12
2. THE NUMBER OF TREES GREATER THAN 2.5" DIAMETER DEMOLISHED MUST BE REPLACED
ALONG THE EAST OF THE NEW DRIVE (DSCC SIDE}.
CONSTRUCTION IMPACTING GOLF COURSE OR TRAFFIC MUST BE COORDINATED IN ADVANCE WITH dm-
FCI
PART III - ENGINEERING BUILDING EXPANSION:
PHASE IIIA:
DEMOLISH EXTERIOR SIDEWALK AND PARKING LOT AS NECESSARY TO CONSTRUCT THE NEW BUILDING ADDITION. REMOVE EXISTING EXTERIOR MECHANICAL EQUIPMENT. PROVIDE FILTERS FOR AIR INTAKE AND EXHAUST VENTS FOR EXISTING INTERIOR AIR HANDLER. CONSTRUCT BUILDING SHELL AND ROOF TO INSTALL NEW ROOFTOP MECHANICAL EQUIPMENT. CONTRACTOR TO PRIORITIZE INSTALLATION OF NEW ROOFTOP UNITS TO MINIMIZE THE TIME THE VA WILL DEPEND ON TEMPORARY HEATING AND COOLING EQUIPMENT. THE FOLLOWING MEASURES WILL NEED TO BE TAKEN TO MAINTAIN HEATING AND COOLING CAPABILITIES IN THE EXISTING BUILDING UNTIL THE NEW EQUIPMENT IS INSTALLED AND
OPERATIONAL.
ADMINISTRATIVE SIDE:
COOLER MONTHS: THE EXISTING AIR HANDLING UNIT IN THE EXISTING MECHANICAL ROOM WILL
REMAIN INSTALLED AND OPERATIONAL UNTIL THE NEW ROOFTOP UNITS ON THE ADDITION ARE
INSTALLED AND OPERATIONAL. DUE TO THE CONSTRUCTION DUST AND DEBRIS, THE OUTSIDE AIR INTAKE FOR THIS UNIT WILL REQUIRE FILTRATION AND SHUTTING OFF ALTOGETHER, AT LEAST TEMPORARILY, TO AVOID DISTRIBUTING DUST WITHIN THE OFFICE SPACES. THE EXTERIOR CONDENSING UNIT WILL NEED TO BE REMOVED IMMEDIATELY BUT THAT IS FOR COOLING ONLY. THE EXISTING OFFICE AREA IS SERVED BY VAV BOXES WITH ELECTRIC REHEAT, WHICH ALL WILL REMAIN. THEREFORE, THE
HEATING FOR THE OFFICES WILL OPERATE UNTIL THE NEW ROOFTOP UNITS ARE INSTALLED.
WARMER MONTHS: THE EXISTING AIR HANDLING UNIT IN THE EXISTING MECHANICAL ROOM WILL REMAIN OPERATIONAL TO CIRCULATE AIR THROUGHOUT THE BUILDING FOR VENTILATION. THIS UNIT WILL NO LONGER HAVE THE CAPABILITY TO PROVIDE COOLING DUE TO THE REMOVAL OF THE EXTERIOR CONDENSING UNIT, HOWEVER IT WILL BE USED TO DISTRIBUTE THE TEMPORARILY CONDITIONED AIR IN THE EXISTING SPACES. THE COOLING WILL BE PROVIDED BY TEMPORARY PORTABLE AC UNITS THAT WILL BE INSTALLED INSIDE THE EXISTING SPACE AND EXHAUSTED TO THE EXTERIOR. COOLING OF THIS SPACE WILL REQUIRE TWO 5-TON PORTABLE AC UNITS LOCATED AT EACH END OF THE OPEN OFFICE
AREA. THE PORTABLE AC UNITS WILL REQUIRE A FLEX DUCT EXTENDED TO THE EXTERIOR TO
DISCHARGE THE WARM AIR.
SHOP SIDE:
COOLER AND WARMER MONTHS: ALL HEATING AND COOLING CAPABILITIES WILL BE REMOVED ONCE THE EXTERIOR UNIT FOR THIS SPACE IS REMOVED. MOBILE TEMPORARY UNITS WILL BE REQUIRED TO HEAT AND COOL THE SHOP SIDE OF THE EXISTING BUILDING. THESE UNITS CAN BE DELIVERED TO THE SITE AND DUCTED INTO THE EXISTING DUCTWORK FROM THE EXTERIOR OF THE BUILDING OR DUCTED DIRECTLY INTO THE SPACE DEPENDING ON THE PROGRESS OF THE ADDITION. THE CONTRACTOR WILL
NEED TO PROVIDE ACCESS AND CLEARANCE FOR THE TEMPORARY DUCTWORK THROUGH THE
CONSTRUCTION SITE UNTIL THE NEW ADDITION SHELL AND ROOF ARE CONSTRUCTED AND THE NEW
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -13
SHOP HVAC EQUIPMENT IS INSTALLED AND OPERATIONAL ON THE ROOF. THE LOCATIONS FOR THE
TEMPORARY EQUIPMENT WILL BE COORDINATED AND APPROVED BY THE VA.
ONCE THE NEW ROOFTOP EQUIPMENT IS INSTALLED AND OPERATIONAL, THE TEMPORARY DUCTWORK AND UNIT FOR THE TEMPORARY COOLING AND HEATING WILL BE REMOVED. THE EXISTING INTERIOR AIR HANDLING UNIT IS TO BE DEMOLISHED AND REMOVED PRIOR TO INTERIOR FINISH WORK. INTERIOR FINISH WORK TO TAKE PLACE AFTER THE BUILDING ADDITION IS ENCLOSED AND THE NEW ROOFTOP
EQUIPMENT IS OPERATIONAL AND TIED INTO THE EXISTING BUILDING DUCTWORK.
PHASE IIIB:
DEMOLISH WALLS ON THE INTERIOR OF THE EXISTING ADMINISTRATION AREA. CONSTRUCT NEW WALLS TO CREATE NEW OFFICES. FLOORING AND CEILING MODIFICATIONS WITHIN THE EXISTING
BUILDING WILL TAKE PLACE IN THIS PHASE.
PHASE IIIC:
REPLACE EXISTING CARPET IN THE REMAINDER OF THE EXISTING ADMINISTRATION BUILDING. REFER TO FINISH SCHEDULE FOR CARPET SELECTION. ALL WORK TO OCCUR AFTER HOURS BETWEEN 5:00 PM AND
6:00 AM AND ON WEEKENDS.
GENERAL: DATA ROOM 106 SPLIT SYSTEM AC UNIT TO REMAIN OPERATIONAL DURING CONSTRUCTION TO PREVENT DAMAGE TO OVERHEATED IT EQUIPMENT. SPLIT SYSTEM OUTDOOR CONDENSING UNIT TO BE RAISED ABOVE GRADE, MOUNTED TO EXTERIOR WALL AND PROTECTED AGAINST DAMAGE DURING ADDITION CONSTRUCTION. EXISTING SPLIT AC SYSTEM TO BE REPLACED BY NEW SPLIT SYSTEM, WITH ROOF-MOUNTED CONDENSING UNIT, ONCE ADDITION ROOF CONSTRUCTION IS COMPLETE. DURING CHANGEOVER TO NEW UNIT, IT IS UP TO THE CONTRACTOR TO PROVIDE TEMPORARY COOLING OF
DATA ROOM DEPENDING ON THE DURATION THE ROOM IS WITHOUT COOLING.
GENERAL: EXISTING DOMESTIC AND FIRE WATER SERVICE LINE NEEDS TO BE RELOCATED TO THE EAST, OUTSIDE OF THE NEW ADDITION FOOTPRINT. NEW WATER LINE TO BE INSTALLED AND CONNECTED INTO SITE WATER SYSTEM PRIOR TO REMOVING OR ABANDONING EXISTING LINE. CONNECTION OF
EXISTING WATER LINE TO NEW WATER LINE TO BE COMPLETED WITH LIMITED DOWNTIME SO
BUILDING CAN REMAIN OPERATIONAL AS MUCH AS POSSIBLE. ANY WATER SHUTOFFS AND DOWNTIME
WILL BE COORDINATED AND APPROVED BY THE VA.
PART IV - ADDITIONAL CAMPUS WORK:
ALL WORK IN PHASE I MUST BE COMPLETED BEFORE WORK IN THIS PHASE CAN COMMENCE. THIS PHASE WILL INCLUDE ALL ITEMS IN THE LIST BELOW. CONTRACTOR TO MAINTAIN EMERGENCY VEHICLE
AND DELIVERY ACCESS ALONG WASHINGTON STREET AT ALL TIMES.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -14
1. RECONFIGURATION OF LOADING DOCK AREA AND ACCESS CONTROL
2. WASHINGTON STREET LANDSCAPED EVENT SPACE WITH FIRE ACCESS AND BOLLARDS
3. INSTALLATION OF CONCRETE PAD AND UTILITY CONNECTIONS FOR MOBILE MEDICAL
TRAILERS AND TEMPORARY TRAILERS (4 SPACES TOTAL}
4. INSTALLATION OF CONCRETE PAD AND UTILITY CONNECTIONS FOR VISN 10 SIMLAB
TRAILERS/TRUCKS (1 SPACE}
5. INSTALLATION OF CONCRETE PAD AND UTILITY CONNECTIONS FOR CARDBOARD
COMPACTOR
6. REFRESH NORTH PARKING LOT STRIPING
7. RELOCATE GREASE DUMPSTER
8. WEST LOT CONCRETE WALKWAY
9. STRIPING OF PARKING LOT
10. CONTRACTOR WILL NEED TO COORDINATE WORK WITH THE VA AND MAINTAIN
DELIVERY ACCESS AT ALL TIMES
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical
Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -15 bottom rails with tie wires spaced at maximum (15 inches). Bottom of fences shall extend to (one inch) above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of (40 degrees
F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company
(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -16
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11
REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical
Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -17
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting
Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -18
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled
"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
E. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -19 protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by
COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
a. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place.
If any limbs or branches of trees are broken during
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -20 contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting
Officer.
b. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
c. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL
CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage
Areas" for additional instructions concerning repair of damage to structures and site improvements.
d. Refer to FAR clause 52.236-7, "Permits and
Responsibilities," which is included in General Conditions.
A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the
(appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -21 furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the
Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1) Designating areas for equipment maintenance and repair;
2) Providing waste receptacles at convenient locations and provide regular collection of wastes;
3) Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4) Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5) Providing adequately maintained sanitary facilities.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -22 patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems
(including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS"
(FAR 52.236-2).
1.10 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by the surveyor and A/E design team.
(FAR 52.236-4)
2. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically in the Geotechnical Report.
3. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical Center and shall be considered part of the contract documents.
4. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -23 explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans
Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.11 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the
Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.12 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and benchmarks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.
The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the
Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through
Contractor's negligence before their removal is authorized, the
Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
(FAR 52.236-17)
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -24
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark
(through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -25
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
4. Lines of elevations of all swales and interment areas.
5. Lines and elevations of roads, streets and parking lots.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".
1.13 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.14 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of
Construction in at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -26
Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved.
Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
Columbus, OH
Affairs System
VA Project No. 757-21-201 Repair Roads Sidewalks and
01 00 00 -27
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
5. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
6. Starting point and duration of warranty period.
7. Summary of maintenance procedures required to continue the warranty in force.
8. Cross-reference to specific pertinent Operation and
Maintenance manuals.
9. Organizations, names and phone numbers of persons to call for warranty service.
10. Typical response time and repair time expected for various warranted equipment.
11. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
12. Procedure and status of…