This document contains an infection control risk assessment matrix and related federal contract opportunity. The risk assessment matrix provides guidance on classifying construction project activities based on type and patient risk groups to determine required infection control precautions. It details four classes of precautions and activities before, during, and after construction for each class.
The federal contract opportunity is to provide site preparation for a nuclear medicine SPECT/CT at the Louis Stokes Cleveland VA Medical Center. The project scope includes renovating and reconfiguring adjacent spaces and new mechanical, electrical, and plumbing systems. The magnitude is between $500,000 to $1,000,000. The NAICS code is 236220 and business size standard is $39.5 million. The solicitation number is 36C25021B0032_1. The performance period is at the VA medical center. A site visit will be conducted on May 20, 2021. Requests for information are due by May 20, 2021. The project is 100% set aside for a verified service-disabled veteran-owned small business registered in SAM.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S02. Safety.docx | DOCX document | |
| S02. Site Visit Information.pdf | ||
| S02. Bid Opening Instructions.pdf | ||
| S02. VAMC Health Requirements.pdf | ||
| S02. BID ISSUE SUBMISSION - DRAWINGS.pdf | ||
| S02. Calculation of Self-Performed and Sub-Contracted Work.docx | DOCX document | |
| S02. RFI Form.pdf | ||
| S02. Solicitation 36C25021B0032_1.pdf | ||
| S02. BID ISSUE SUBMISSION - SPECIFICATIONS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ICRA Matrix of Precautions for Construction and Renovation
Step One: Using the following table, identify the Type (A-D) of Construction Project Activity.
Type Construction Project Activity
Type A
Inspection and Non-Invasive Activities.
Include, but are not limited to:
Removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet.
Painting (but not sanding).
Wall covering, electrical trim work, minor plumbing, and activities that do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.
Type B
Small scale, short duration activities that create minimal dust.
Include, but are not limited to:
Installation of telephone and computer cabling.
Access to chase spaces.
Cutting of walls or ceiling where dust migration can be controlled.
Type C
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies.
Includes, but is not limited to:
Sanding of walls for painting or wall covering.
Removal of floor coverings, ceiling tiles, and casework.
New wall construction.
Minor duct work or electrical work above ceilings.
Major cabling activities.
Any activity that cannot be completed within a single work shift.
Type D
Major demolition and construction projects.
Includes, but is not limited to:
Activities that require consecutive work shifts.
Requires heavy demolition or removal of a complete cabling system.
New construction.
STEP 1: _________________________________________________________________
Step Two: Using the following table, identify the Patient Risk Groups that will be affected.
Low Risk
Medium Risk High Risk Highest Risk
▪ Office areas
▪ Cardiology
▪ Echocardiography
▪ Endoscopy
▪ Nuclear Medicine
▪ Physical Therapy
▪ Radiology/MRI
▪ Respiratory Therapy
▪ Outpatient Clinics
▪ Emergency Room
▪ Labor & Delivery
▪ Clinical Laboratories
▪ Pediatrics
▪ Pharmacy
▪ Post Anesthesia Care Unit
▪ Surgical Units
▪ Any area caring for immuno-compromised patients
▪ Burn Unit
▪ Cardiac Cath Lab
▪ Supply, Processing, and Distribution
▪ All inpatient medical or surgical units
▪ Medical Unit
▪ Negative pressure isolation rooms
▪ Outpatient chemotherapy areas
▪ Operating Rooms
Step 2: _________________________________________________________________
Step Three: Match the…
Patient Risk Group (Low, Medium, High, Highest) with the planned Construction Project Type (A, B, C, D) on the following matrix, to find the Class of Precautions (I, II, III or IV) or level of infection control activities required.
(Class I-IV or Color-Coded Precautions are delineated on the following table.)
IC Matrix Class of Precautions: Construction Project by Patient Risk
Construction Project Type
Patient Risk Group TTYYPPEE AA TTYYPPEE BB TTYYPPEE CC TTYYPPEE DD
LLOOWW Risk Group II ((ggrreeeenn)) IIII ((yyeellllooww)) IIII ((yyeellllooww)) IIIIII//IIVV ((ppiinnkk))
MMEEDDIIUUMM Risk Group II ((ggrreeeenn)) IIII ((yyeellllooww)) IIIIII ((ppiinnkk)) IIVV ((rreedd))
HHIIGGHH Risk Group II ((ggrreeeenn)) IIII ((yyeellllooww)) IIIIII//IIVV ((ppiinnkk)) IIVV ((rreedd))
HHIIGGHHEESSTT Risk Group
IIII ((yyeellllooww)) IIIIII//IIVV ((ppiinnkk)) IIIIII//IIVV ((ppiinnkk)) IIVV ((rreedd))
Note: Infection Control approval is required for all construction or renovation activities.
Step 3: _________________________________________________________________
Description of Required Infection Control Precautions by Class
C L
A S
S During Construction Project Upon Completion of the Project
C L
A S
S I
1. Execute work by methods to minimize dust dispersal from minor flooring or surface disruptions.
2. Immediately replace a ceiling tile displaced for visual inspection.
Clean up any dust that may have been generated with HEPA filtered vacuum or damp mop.
C L
A S
S I
I
1. Provide active means to prevent airborne dust from dispersing into atmosphere with use of control cubes or other dust barriers.
2. Remove or isolate HVAC system in areas where work is being performed.
3. Water mist work surfaces to control dust while cutting.
4. Seal unused doors with duct tape.
5. Block off and seal air vents.
6. Place tacky mat at entrance and exit of work area and change frequently or when ineffective.
1. Wet mop and/or vacuum with HEPA-filtered vacuum before leaving work area and wipe work surfaces with disinfectant.
2. Contain construction waste before transport in tightly covered containers.
Tape may be used to ensure a tight cover.
3. Remove isolation of HVAC system in areas when work has been completed.
C L
A S
S During Construction Project Upon Completion of the Project
C L
A S
S
II
As above and:
1. Complete all critical barriers, i.e., sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method before construction begins.
2. Maintain negative air pressure (NPV) within the work site utilizing HEPA-equipped air filtration units.
3. NPV monitoring devices should be visible from outside the worksite and readings should be documented daily or more often as needed.
4. Contain construction waste before transport in tightly covered containers. Tape covering unless solid lid.
As above and:
1. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
2. Do not remove barriers from work area until completed project is thoroughly cleaned by Environmental Management Services Department and inspected by FMS, Safety and Infection Control.
C L
A S
S
V
As above and:
1. Seal holes, pipes, conduits, and punctures appropriately.
2. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site OR they can wear cloth or paper coveralls that are removed each time they leave the work site.
3. All personnel entering work site are required to wear shoe covers. Shoe covers must be changed each time the worker exits the work area.
As above
Step 4: Identify the areas surrounding the project area, assessing potential impact.
Unit Below Unit Above Lateral Lateral Behind Front
Risk Group Risk Group Risk Group Risk Group Risk Group Risk Group
Step 5: Identify specific site of activity, e.g., patient rooms, medication room, etc.
Step 6: Identify issues related to: ventilation, plumbing, and electrical, in terms of the occurrence of probable outages.
Step 7: Identify containment measures using prior assessment. What types of barriers such as solid wall barriers? Will HEPA filtration be required?
Note: Renovation/construction area shall be isolated from the occupied areas during construction and shall be negative with respect to surrounding areas.
Step 8: Consider potential risk of water damage. Is there a risk due to compromising structural integrity (e.g., wall, ceiling, roof)?
Step 9: Work hours: Can or will the work be done during non-patient-care hours?
Step 10: Do plans allow for adequate number of isolation/negative airflow rooms?
Step 11: Do the plans allow for the required number and type of hand washing sinks?
Step 12: Does the infection control staff agree with the minimum number of sinks for this project? (Verify against the American Institute of Architects Guidelines for types and area.)
Step 13: Does the infection control staff agree with the plans relative to clean and soiled utility rooms?
Step 14: Plan to discuss the following containment issues with the project team: traffic flow, housekeeping, and debris removal (how and when).
Appendix: The ICRA may be modified throughout the project. Revisions must be communicated to the Project Manager.