S02 - Attachment C - Salary Survey Data QASP.pdf
PDF 206 KB Posted
- Attached to
- R405--Total Compensation Analysis (VA-23-00011103) Federal contract opportunity
- Solicitation number
- 36C77624R0042
About this file
This document outlines performance standards and quality assurance plans for a salary survey data contract. The contractor must demonstrate understanding of requirements, meet technical needs and schedules, and possess qualified staff. Key performance metrics include quickly addressing issues and delivering quality products on schedule. The contractor's work will be inspected by the program manager and contracting officer's representative, with incentives for acceptance and penalties for repeated errors. This quality assurance surveillance plan defines performance expectations and oversight methods for the contract.
A separate federal solicitation seeks proposals for a single-award, firm-fixed-price contract to support the Department of Veterans Affairs' Workforce Management and Consulting division. Offerors will provide total compensation analysis using FAR parts 12 and 15 procedures. The Technology Acquisition Center in Austin, Texas will administer the contract on behalf of VA.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S05 - Total Compensation Analysis Questions and Answers.docx | DOCX document | |
| 36C77624R0042 A0001.docx | DOCX document | |
| S02 - Attachment B - Salary Survey Data PWS.pdf | ||
| S02 - Attachment A - Past Performance Questionnaire 02.docx | DOCX document | |
| 36C77624R0042.docx | DOCX document | |
| S02 - Attachment E - Wage Rates.txt | TXT text file | |
| S02 - Attachment D - Subcontracting Plan Template.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Salary Survey Data Quality Assurance Surveillance Plan (QASP)
The table below defines the performance standards and acceptable levels of performance associated with the deliverables in this effort.
Required Service/Task
Performance Standard
Acceptable Quality Level
Method of Surveillance
Incentive (Positive and/or
Negative) Technical Needs
Demonstrates understanding of requirements
Efficient and effective in meeting requirements
Meets technical needs and mission requirements
Offers quality services/ products
95% (See Note 1)
100% Inspection
The PM and COR shall review and accept deliverables.
Contractor shall re-accomplish products found to be unacceptable or not meeting the intent of the task and the work within five (5) business days.
Contractor shall receive payment once deliverable is accepted by the Government (See Note 2)
Project Milestones and Schedule
Quick response capability
Products completed, reviewed, delivered in timely manner
Notifies customer in advance of potential problems, recommends solutions
95% (See Note 1)
100% Inspection
The PM and COR shall review and accept deliverables.
Contractor shall re-accomplish products found to be unacceptable or not meeting the intent of the task and the work within five (5) business days.
Contractor shall receive payment once deliverable is accepted by the Government (See Note 2)
Staffing Currency of Expertise
Personnel possess necessary knowledge, skills, and abilities to perform tasks
95% (See Note 1)
100% Inspection
The PM and COR shall review and accept deliverables.
Contractor shall re-accomplish products found to be unacceptable or not
Required Service/Task
Performance Standard
Acceptable Quality Level
Method of Surveillance
Incentive (Positive and/or
Negative) meeting the intent of the task and the work within five (5) business days.
Contractor shall receive payment once deliverable is accepted by the Government (See Note 2)
Value Added Provided valuable service to Government
Services/ products delivered were of desired quality
Proactively meets government’s needs, including responding to changing requirements, systems, etc.
95% (See Note 1)
100% Inspection
The PM and COR shall review and accept deliverables.
Contractor shall re-accomplish products found to be unacceptable or not meeting the intent of the task and the work within five (5) business days.
Contractor shall receive payment once deliverable is accepted by the Government (See Note 2)
* Note 1: Significant errors or omissions are defined as deliverables not meeting the intent of the task and the work considered to be within scope of this order.
** Note 2: Continued repetitive errors may result in an unacceptable rating on performance report to be used as part of the evaluation criteria on future order competitions.
Types of Surveillance:
1. Random sampling: Appropriate for frequently recurring tasks. Evaluate randomly selected samples of the lot to determine the acceptability of the entire lot (random inspection guide, method of surveillance, lot size, sample size, performance requirement, sampling procedure, and inspection procedure).
2. One hundred percent inspection: Appropriate for tasks that occur infrequently. Inspect and evaluate performance each time task is performed.
3. Periodic surveillance: Evaluation of samples selected on other than a 100 percent or statistically random basis (such as monthly, quarterly, or semi-annually).
File details come from the government source that posted it. Updated .