S02 - Attachment 22 - 280800 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.docx

DOCX document 21 KB Posted

Attached to
Install Garage Cameras at Lake Nona VAMC
Solicitation number
36C24823R0050
Issued by

About this file

This document provides specifications for commissioning electronic safety and security systems for the Install Garage Cameras at Lake Nona VAMC federal contract opportunity. The specifications require commissioning of electronic safety and security systems including inspection, pre-functional checklist completion by the contractor, contractor testing, and systems functional performance testing witnessed by the commissioning agent. The commissioning agent will prepare test procedures for approval. The contractor must provide labor, materials and equipment for testing, and sign test reports to verify completion. Training of VA operations and maintenance personnel is also required.

View the file

Other files

File Type Posted
S02 - Attachment 25 Physical Security Systems Technical Specifications 01-24-2023.pdf PDF
S02 - Attachment 26 - RFI Responses 36C24823R0050 RFIs for Install Parking Garage Cameras at Lake Nona.xlsx XLSX spreadsheet
S02 36C24823R0050 Install Garage Cameras at Lake Nona (Updated_1-24-23).pdf PDF
36C24823R0050 0002.pdf PDF
36C24823R0050 0001.pdf PDF
S02 - Attachment 05 - Specialized Experience Form (3 Pages).pdf PDF
S02 - Attachment 06 - 675-23-108 Parking Garage Drawings.pdf PDF
S02 - Attachment 08 - 013323 SHOP DRAWINGS-PRODUCT DATA-SAMPLES.docx DOCX document
36C24823R0050.pdf PDF
S02 - Attachment 25 Physical Security Systems Technical Specifications 12-20-2022.pdf PDF
S02 - Attachment 19 - 280500 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY.docx DOCX document
S02 - Attachment 14 - 079200 JOINT SEALANTS.docx DOCX document
S02 - Attachment 01 - Wage Determination Orlando.txt TXT text file
S02 - Attachment 24 - 28052833 CONDUITS AND BACKBOXES FOR ELECTRONIC SAFETY AND SECURITY.doc DOC document
S02 - Attachment 15 - 260511 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.docx DOCX document
S02 - Attachment 23 - 282300 Video Surveillance.doc DOC document
S02 - Attachment 09 - 013526 SAFETY REQUIREMENTS.docx DOCX document
S02 - Attachment 11 - 014500 QUALITY CONTROL.docx DOCX document
S02 - Attachment 20 - 280513 CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY.docx DOCX document
S02 - Attachment 10 - 014219 REFERENCE STANDARDS.docx DOCX document
S02 - Attachment 21 - 280526 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY.doc DOC document
S02 - Attachment 04 - EMR.docx DOCX document
S02 - Attachment 03 - Past Performance Questionnaire 36C24822R0050.pdf PDF
S02 - Attachment 18 - 260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS.docx DOCX document
S02 - Attachment 16 - 260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.docx DOCX document
S02 - Attachment 17 - 260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.docx DOCX document
S02 - Attachment 02 - Price Matrix.xlsx XLSX spreadsheet
S02 - Attachment 07 - 01 00 00 General Requirements (Orlando DB).docx DOCX document
S02 - Attachment 12 - 019100 GENERAL COMMISSIONING REQUIREMENTS.docx DOCX document
S02 - Attachment 13 - 078400 FIRESTOPPING.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11-1-16

SECTION 28 08 00

COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A.The requirements of this Section apply to all sections of Division 28.
B.This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY

A.This Section includes requirements for commissioning the Facility electronic safety and security systems, related subsystems and related equipment. This Section supplements the general requirements specified in Section 01 91 00 General Commissioning Requirements.
B.Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A.Commissioning of a system or systems specified in Division 28 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of Division 28, is required in cooperation with the VA and the Commissioning Agent.
B.The Facility exterior closure systems commissioning will include the systems listed in Section 01 91 00 General Commissioning Requirements:

1.6 SUBMITTALS

A.The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.
B.The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 Construction Inspections

A. Commissioning of Electronic Safety and Security systems will require inspection of individual elements of the electronic safety and security systems throughout the construction period. The Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 91 00 and the Commissioning plan to schedule electronic safety and security systems inspections as required to support the Commissioning Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning Agent may spot check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 28 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected Contractor tests at the sole discretion of the Commissioning Agent. Contractor tests shall be completed prior to scheduling Systems Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING

A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Resident Engineer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, for additional details.

3.5 TRAINING OF VA PERSONNEL

A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00. The instruction shall be scheduled in coordination with the VA Resident Engineer after submission and approval of formal training plans. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and Division 28 Sections for additional Contractor training requirements.

----- END -----