This is a Base Offer Price Breakdown form template for a construction project under federal contract solicitation 36C24826R0113. The form is designed for offerors to submit detailed pricing for the upgrade of an IV Mixing Room for USP 800 Compliance at the Lee County VA Clinic in Cape Coral, Florida. The pricing structure follows the CSI (Construction Specifications Institute) divisions, requiring offerors to break down costs into Labor and Material categories across 24 construction divisions, including General Requirements, Concrete, Masonry, Metals, HVAC, Electrical, Plumbing, Fire Suppression, and Earthwork, among others. Each division subtotal is calculated automatically by summing labor and material costs.
The form requires offerors to input Overhead percentage, Profit percentage, and Bond percentage, which are calculated sequentially against the Division Subtotals and cumulative costs. The final Total Base Offer Cost is derived from all divisions plus overhead, profit, and bond calculations. Offerors are instructed to provide detailed price breakdowns avoiding lump sum entries. This solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) entities issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8. The site visit is scheduled for May 21, 2026, with Requests for Information due May 26, 2026, and proposals due June 12, 2026, at 10:00 AM EST.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Offer Base Offer Cost Breakdown
Project Number:
Edward L Roy: VA assigned project #
| Date: | |
| Project Title |
| Edward L Roy: VA assigned Project Title | Project Location | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | $ - 0 | $ - 0 |
| Division 2 | Existing Conditions | - 0 | - 0 | - 0 |
| Division 3 | Concrete | - 0 | - 0 | - 0 |
| Division 4 | Masonry | - 0 | - 0 | - 0 |
| Division 5 | Metals | - 0 | - 0 | - 0 |
| Division 6 | Wood and Plastic | - 0 | - 0 | - 0 |
| Division 7 | Thermal & Moisture Protect | - 0 | - 0 | - 0 |
| Division 8 | Doors and Windows | - 0 | - 0 | - 0 |
| Division 9 | Finishes | - 0 | - 0 | - 0 |
| Division 10 | Specialties | - 0 | - 0 | - 0 |
| Division 11 | Equipment | - 0 | - 0 | - 0 |
| Division 12 | Furnishings | - 0 | - 0 | - 0 |
| Division 13 | Special Construction | - 0 | - 0 | - 0 |
| Division 14 | Conveying Equipment | - 0 | - 0 | - 0 |
| Division 21 | Fire Suppression | - 0 | - 0 | - 0 |
| Division 22 | Plumbing | - 0 | - 0 | - 0 |
| Division 23 | HVAC | - 0 | - 0 | - 0 |
| Division 26 | Electrical | - 0 | - 0 | - 0 |
| Division 27 | Communications | - 0 | - 0 | - 0 |
| Division 28 | Electronic Safety & Security | - 0 | - 0 | - 0 |
| Division 31 | Earthwork | - 0 | - 0 | - 0 |
| Division 32 | Exterior Improvements | - 0 | - 0 | - 0 |
| Division 33 | Utilities | - 0 | - 0 | - 0 |
| Division 34 | Transportation Subtotal | - 0 | - 0 | - 0 |
| Division Subtotals : | $ - 0 | $ - 0 | $ - 0 |
Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| - 0 | |||
| Profit % | 0.00% | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | - 0 | ||
| Bond % | 0.00% |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| - 0 | ||
| Overhead/Profit Subtotals : | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0
Offerors shall provide additional price breakdown to avoiding lump sum, etc. This price offer breakdown is the overall base offer price for Government price analysis
File details come from the government source that posted it. Updated .