S02 Attach 2 USP Room FINAL SET 35 Pages.pdf
PDF 8 MB Posted
- Solicitation number
- 36C24826R0113
About this file
These are Bid Documents for a federal construction project for the U.S. Department of Veterans Affairs to upgrade the Pharmacy IV Mixing Room at the Lee County VA Clinic in Cape Coral, Florida (Project 516-22-112). The scope includes demolition and renovation work to create USP 797/800 compliant pharmacy spaces (IV Buffer, Ante Room, and Chemo Buffer rooms) with specialized HVAC, plumbing, electrical, and structural systems.
The architectural, mechanical, plumbing, structural, and electrical drawings establish requirements for new construction including: installation of a new air handling unit (AHU-1-4A) with HEPA filtration, biosafety cabinets, reheat coils, and ductwork to maintain required pressure differentials and air changes per hour; new hot water and chilled water piping connections with control valves; structural steel support frames and ductwork hangers; new electrical circuits, lighting fixtures, data receptacles, and HVAC control panels; and selective demolition of existing equipment and systems. The drawings specify product standards including DLC-qualified LED lighting fixtures, stainless steel ductwork, Johnson Controls-compatible DDC controls, and equipment from manufacturers such as Trane (AHU), Labconco (biosafety cabinet), and Greenheck (fans and louvers). Documentation includes detailed schedules, specifications, and design notes addressing infection control measures, temporary barrier construction, fire-rated assemblies, coordination requirements between trades, and compliance with IBC, NFPA, VA design manuals, and accessibility codes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHEET INDEX
GI001
SHEET
NO. DRAWING TITLE
GENERAL
GI002
ARCHITECTURAL
SHEET
NO.
COVER SHEET
NOTES, ABBREVIATIONS AND LEGENDS
UPGRADE PHARMACY IV MIXING
ROOM USP 797/800
PROJECT NUMBER: 516-22-112
BID DOCUMENTS
LEE COUNTY VA CLINIC
2489 DIPLOMAT PARKWAY EAST
CAPE CORAL, FL 33909
PARTIAL FIRST FLOOR PLANS AND ELEVATIONSAE101
MECHANICAL
MECHANICAL LEGEND, ABBREVIATIONS, AND NOTESM001
PARTIAL FIRST FLOOR AND ENLARGED HVAC DEMOLITION PLANMD101
MD102
ELECTRICAL
ELECTRICAL GENERAL NOTES AND ABBREVIATIONSE-001
ELECTRICAL DEMOLITION PLANED101
LOCATION MAP
NOT TO SCALE
AREA MAP
NOT TO SCALE
TRUE
NORTH
TRUE
NORTH
PLAN
NORTH
PLAN
NORTH
PROJECT LOCATION PROJECT LOCATION
ELECTRICAL LEGENDE-002
PARTIAL FIRST FLOOR AND ENLARGED PIPING DEMOLITION PLAN
M101 PARTIAL FIRST FLOOR AND ENLARGED HVAC NEW WORK PLAN
EP101 ELECTRICAL NEW WORK PLAN
PARTIAL FIRST FLOOR REFLECTED CEILING PLANS - DEMOLITIONAD111
PARTIAL FIRST FLOOR AND ENLARGED PLANS - DEMOLITIONAD101
PARTIAL SECOND FLOOR PLAN AND THIRD FLOOR PLAN - LOW PENTHOUSEAE102
PARTIAL FIRST FLOOR REFLECTED CEILING PLANS AE111
STRUCTURAL
STRUCTURAL NOTESS001
DEMOLITION AND FRAMING PLANSS101
STEEL DETAILSS501
MECHANICAL NOTESM002
M102 PARTIAL FIRST FLOOR AND ENLARGED PIPING NEW WORK PLAN
M501 HVAC DETAILS
M502 MECHANICAL PIPING DETAILS
M503 MECHANICAL PIPING AND EQUIPMENT DETAILS
M601 MECHANICAL SCHEDULES
M800 VA STATION GENERAL CONTROL NOTES AND LEGEND
M801 CONTROL SCHEMATIC, SEQUENCE OF CONTROL, AND CONTROL POINT - MECHANICAL
PLUMBING
PLUMBING ABBREVIATIONS, SCHEDULE AND NOTESP001
1ST FLOOR PHARMACY PLAN - PLUMBINGP101
PARTIAL FIRST FLOOR AND THIRD FLOOR LIFE SAFETY PLANSLS101
PARTIAL SECOND FLOOR AND ENLARGED PLANS - DEMOLITIONAD102
ROOM FINISH, DOOR AND FRAME SCHEDULES AND DETAILSAE601
GI003 PARTIAL FIRST FLOOR AND SECOND FLOOR ICRA PLANS
E-621 ELECTRICAL SCHEDULES
FRAMING DETAILSAE501
E-501 ELECTRICAL DETAILS
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
DATE:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
BID DOCUMENTS
590 MEANS ST NW
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and
Facilities Management
Drawn
SV SJ/KB
516-22-112
12-23-2025REVISIONS:
A
B
C
D
E
F
UPGRADE PHARMACY IV MIXING ROOM
USP 797/800
CAPE CORAL, FLORIDA
COVER SHEET
GI001
ARCHITECTURAL ABBREVIATIONSARCHITECTURAL LEGEND
GENERAL ARCHITECTURAL NOTES
GENERAL PROJECT NOTES
A
GA4
A301
A201
A401
ROOM
NAME
+ 0'-6"
F.E.C.
AIR CONDITIONING
ACOUSTICAL CEILING TILE
ABOVE FINISH FLOOR
ALUMINUM
BATT INSULATION
BOTTOM OF
CEMENTITIOUS BACKER BOARD
CEMENTITIOUS CRYSTALLINE WATERPROOFING
COLD-FORMED METAL FRAMING
CORNER GUARD
CENTERLINE
CONCRETE MASONRY UNIT
CASED OPENING
COMMUNICATION
CONCRETE
SEALED CONCRETE
CONTINUOUS
CONTRACTING OFFICER'S REPRESENTATIVE
CERAMIC TILE
CERAMIC TILE BASE
CARPET
DIAMETER
EXPANSION JOINT
ELECTRICAL
EPOXY FLOORING
EXPOSED STRUCTURE
ET CETERA
EXISTING
EXPOSED
FACTORY FINISH
FLOOR DRAIN
FIRE EXTINGUISHER CABINET
FIRE HOSE CABINET
FINISHED FLOOR
FINISH
FLOOR
FACE OF
FIELD VERIFY
FABRIC WALLCOVERING
GAGE
GRANITE
GYPSUM (WALL) BOARD
HANDICAPPED
HOLLOW METAL
HANDRAIL
HEATING VENTILATION AND AIR-CONDITIONING
MATERIAL
MAXIMUM
MECHANICAL
MANUFACTURER
MINIMUM
MASONRY OPENING
METAL
NOT IN CONTRACT
NOT TO SCALE
ON CENTER
OPPOSITE HAND
PLASTER
PLASTIC LAMINATE
PORCELAIN TILE
PAIR
PAINT
QUARRY TILE
RESILIENT BASE
REFRIGERATOR
REQUIRED
RESINOUS FLOORING
RESINOUS EPOXY WALL-CEILING
ROUGH OPENING
RUBBER FLOORING
RECESSED PAPER HOLDER
SEALED HIGH BUILD GLAZED COATING
SOLID CORE WOOD
SIMILAR
SPECIAL FACED
STAINLESS STEEL
STEEL
SUBSTRATE
SHEET VINYL
SOLID VINYL TILE
TELEPHONE
TOP OF
TYPICAL
UNLESS NOTED OTHERWISE
VINYL COMPOSITION TILE
VINYL WALL COVERING
WALL COVERING
WALL PROTECTION
WOOD
WELDED SEAM SHEET FLOORING
AC
AT
AFF
AL
BATT
BO
CBB
CCW
CFMF
CG
C
CMU
CO
COMM
CONC
SCONC
CONT
COR
CT
CTB
CP
DIA
EJ
ELEC
EPY
ES
ETC
EXIST
EXP
FAC FIN
FD
FEC
FHC
FF
FIN
FLR
FO
FV
FWC
GA
GRA
GYP BD/GWB
HC
HM
HR
HVAC
MATL
MAX
MECH
MFR
MIN
MO
MTL
NIC
NTS
OC
OH
PLS
PL
PT
PR
P
QT
RB
REF
REQ'D
RES
RES-W
RO
RF
RPH
SC
SCW
SIM
SP
SS
STL
SUBS
SV
SVT
TELE
TO
TYP
UNO
VCT
VWC
WC
WP
WD
WSF
L
FIRE EXTINGUISHER CABINET
ROOM NAME AND NUMBER
DOOR NUMBER
KEY NOTE
WINDOW TYPE
PARTITION TYPE
DETAIL CALLOUT
DETAIL NUMBER
SHEET WHERE DETAIL IS DRAWN
SECTION CALLOUT
VERTICAL ELEVATION
COLUMN CENTERLINE DESIGNATION
DEMOLITION KEY NOTE
DETAIL NUMBER
SHEET WHERE DETAIL IS DRAWN
INTERIOR ELEVATION CALLOUT
DETAIL NUMBER
SHEET WHERE DETAIL IS DRAWN
CARD READERCR
HIGH-PRESSURE LAMINATEHPL
LUXURY VINYL TILELVT
EDGE OF DECKEOD
DOWNSPOUTDS
CONTROL JOINTCJ
DRINKING FOUNTAINDF
FIRE RETARDANT TREATEDFRT
EXTERIOR INSULATION FINISHING SYSTEMEIFS
WATER RESISTANTWR
J1
SECTION CUT
HEAD/JAMB/SILL DETAIL NUMBER EQUALEQ
CARPET TILECPT
REFLECTED CEILING PLANRCP
SOLID SURFACE MATERIALSSM
X1045 EQUIPMENT JSN NUMBER
ALUMINUM COMPOSITE METAL PANELSACMP
A. DIMENSIONS, UNLESS OTHERWISE INDICATED, ARE TO:
• FACE OF EXISTING WALL SURFACE
• FACE OF MASONRY
• FACE OF WALL STUDS
• TOP OF SLAB
• TOP OF MASONRY
• ALIGN WALLS WITH EXISTING WHERE NOT OTHERWISE INDICATED.
B. COORDINATE WITH ALL DISCIPLINE DRAWINGS FOR ADDITIONAL REQUIREMENTS.
COORDINATE OPENINGS IN SLABS, ROOF, AND WALLS. WHERE HOLES IN EXISTING WALLS
AND SLABS ARE CREATED FOR PENETRATIONS, COORDINATE SIZE AND LOCATION. PATCH
HOLES CAUSED BY THE REMOVAL OF EQUIPMENT, PIPING, CONDUIT, DUCT, GRILLES, ETC.
WITH MATERIALS MATCHING EXISTING SLAB OR WALL IN STRUCTURE, MATERIAL,
THICKNESS, ALIGNMENT, GRADES, AND QUALITY.
C. COORDINATE AND PROVIDE GALVANIZED METAL BACKER PLATE OR SOLID FIRE
RETARDANT TREATED WOOD BLOCKING FOR WALL-MOUNTED ITEMS. COORDINATE
LOCATIONS WITH COR FOR GOVERNMENT PROVIDED/CONTRACTOR INSTALLED
EQUIPMENT.
D. `PROVIDE' IS DEFINED AS PROVIDING MATERIALS, DELIVERY, STORAGE, HANDLING,
INSTALLATION, ADJUSTMENT, AND CLEANING FOR THE ITEM INDICATED.
E. SEAL PIPE PENETRATIONS THROUGH SLABS, MASONRY, SMOKE PARTITIONS, SMOKE
BARRIERS, AND FIRE BARRIERS WITH THE APPROPRIATE FIRESTOP TO MAINTAIN THE
RATING OF THE WALL OR SLAB. SUBMIT CUT SHEETS AND SPECIFICATIONS TO THE COR
FOR APPROVAL PRIOR TO INSTALLATION. PROVIDE UL LISTED ASSEMBLIES.
F. SKIM COAT ALL DAMAGED EXISTING WALL SURFACES THAT REQUIRE PAINTING.
G. REMOVED MATERIALS WHICH ARE INDICATED TO BE TURNED OVER TO THE COR SHALL BE
DELIVERED BY THE CONTRACTOR TO A LOCATION INDICATED BY THE COR.
H. REMOVE COMPLETELY ALL MATERIALS AS INDICATED ON THE DRAWINGS AND AS
REQUIRED FOR NEW CONSTRUCTION. EDGES AND FACES OF REMOVED AREAS SHALL BE
REPAIRED TO ACCEPT NEAT INSTALLATION OF CONSTRUCTION OR FINISHES. WHERE
EXISTING MATERIALS ARE TO BE REPLACED (WALLS, INSULATION, FLOORING, ETC.)
EXISTING MATERIALS, ADHESIVES, ETC., SHALL BE REMOVED AND EXPOSED SURFACES
SHALL BE PREPARED AS INDICATED OR SPECIFIED PRIOR TO INSTALLATION OF
MATERIALS.
I. PREVENT DAMAGE TO MATERIALS AND FINISHES TO REMAIN. REPAIR DAMAGES FROM
CONSTRUCTION ACTIVITIES TO EXISTING ITEMS TO REMAIN, AT NO ADDITIONAL COST
WHERE SUCH EXPOSED MATERIALS OR FINISHES TO REMAIN ARE DAMAGED.
J. SEAL ALL PLATES, COVERS, DEVICES; AND GENERAL FLOOR, WALL AND CEILING
PENETRATIONS IN ALL SPACES, TYPICAL.
A. THE CONTRACTOR SHALL BE PREPARED TO STOP ANY WORK AND CLEAN UP THE WORK AREA
AS DIRECTED IN MEDICAL SITUATIONS REQUIRING SUCH ACTION.
B. THE CONTRACTOR SHALL NOT ORDER OR INSTALL ANY MATERIALS OR EQUIPMENT UNTIL
SUBMITTALS FOR SUCH HAVE BEEN APPROVED.
C. ALL TOOLS AND MATERIALS USED IN THIS PROJECT SHALL BE PROPERLY SECURED AT ALL
TIMES BY THE CONTRACTOR TO REDUCE THE POSSIBILITY OF ANY OF THESE TOOLS BEING A
HAZARD TO PATIENTS, VISITORS AND STAFF.
D. THE CONTRACTOR WILL BE RESPONSIBLE FOR ACQUIRING I.D. BADGES FOR EACH MEMBER OF
HIS WORK FORCE. VALID FORMS OF I.D. ARE REQUIRED TO RECEIVE BADGES. COORDINATE
WITH COR.
E. THE CONTRACTOR, AT HIS EXPENSE, WILL BE RESPONSIBLE FOR TRAINING EACH MEMBER OF
HIS WORK FORCE ON VA POLICIES FOR ON-SITE WORK BEFORE ANY MEMBER WILL BE
ALLOWED TO PERFORM WORK ON VA PREMISES.
F. ABSOLUTELY NO VA TOOLS, MATERIALS OR EQUIPMENT WILL BE LOANED OR GIVEN BY THE VA
TO ANY MEMBER OF THE CONTRACTOR'S WORK FORCE AT ANY TIME.
G. ANY SMOKE DETECTORS HAVING ANY POTENTIAL FOR EXPOSURE TO CONSTRUCTION SMOKE,
DUST AND DEBRIS SHALL BE SUITABLY PROTECTED TO PREVENT ACCIDENTAL ALARM DURING
CONSTRUCTION. ALL SUCH ACTION MUST BE FIRST COORDINATED AN CLEARED WITH THE COR
AND THE VA SAFETY OFFICER. ALL FUNCTIONAL FIRE ALARM DEVICES SHALL BE ACTIVE
WHENEVER THE CONTRACTOR'S FORCES ARE NOT PRESENT IN THE WORK AREA.
H. THE CONTRACTOR MUST PROVIDE WRITTEN FIRE SAFETY CHECKLIST AT THE END OF EVERY
WORK DAY TO THE COR CERTIFYING THAT ALL WORK AREAS HAVE BEEN SURVEYED AND
FOUND TO BE SECURE, SAFE AND FREE OF ANY FLAMMABLE LIQUIDS.
I. CONTRACTOR SHALL COORDINATE ONLY WITH THE COR AND CONTRACTING OFFICER.
J. SEE SPECIFICATIONS SECTIONS 01 00 00 AND 01 35 26 FOR INTERIM LIFE SAFETY MEASURES.
K. ALL FINISH COLORS TO BE SELECTED BY COR/ VA INTERIOR DESIGNER WHERE NOT
OTHERWISE INDICATED. CONTRACTOR SHALL SUBMIT COLORS FROM THE MANUFACTURER'S
FULL RANGE OF COLORS.
L. PROVIDE 24"X24" ACCESS PANELS IN HARD CEILINGS WHERE DUCTS AND DAMPERS OR OTHER
PIPES REQUIRE ACCESS AS REQUIRED. COORDINATE EXACT LOCATIONS WITH THE COR.
M. THE CONTRACTOR SHALL NOT OPERATE ANY EXISTING VA EQUIPMENT WITHOUT
AUTHORIZATION FROM VAMC ENGINEERING SERVICE UNLESS AN EMERGENCY SITUATION
OCCURS.
N. CONTRACTOR SHALL MAINTAIN ALL FIRE-RATED ASSEMBLIES WITHIN THE PROJECT AREA
DURING PERFORMANCE OF THE WORK.
O. CONTRACTOR SHALL PROVIDE AND MAINTAIN ALL REQUIRED EXIT LIGHTING AND SIGNAGE
REQUIRED FOR EGRESS WITHIN AND ADJACENT TO THE PROJECT AREA DURING
PERFORMANCE OF THE WORK.
P. INDICATED EXISTING CONDITIONS ARE BASED UPON LIMITED FIELD INVESTIGATION THAT DID
NOT INCLUDE DESTRUCTIVE INVESTIGATION OR TESTING. CONTRACTOR SHALL VERIFY ALL
EXISTING CONDITIONS INCLUDING DIMENSIONS OF THE EXISTING CONSTRUCTION PRIOR TO
COMMENCING WITH THE WORK. IF DISCREPANCIES ARE DISCOVERED, THE CONTRACTOR
SHALL NOTIFY THE COR FOR INTERPRETATION AND DIRECTION PRIOR TO PROCEEDING WITH
THE WORK.
A ACCESSORY TYPE
MOUNTING HEIGHTS
ACCESSIBILITY REQUIREMENTS
FRONT APPROACHES
HINGE-SIDE APPROACHES
LATCH-SIDE APPROACHES
USE EITHER
OPTION 1 OR
OPTION 2
ALL DOOR ASSEMBLIES SHALL BE CONSTRUCTED TO MEET THE
INDICATED MINIMUM CLEARANCES AS APPLICABLE.
1'-0" IF DOOR HAS BOTH
A CLOSER AND A
LATCH
5' -0
1'-6"
3' -6
4'-6"
4' -0
O P
TI
O
N
5' -0
OPTION 1
3'-0"
O P
TI
O
N
4' -6
OPTION 2
3'-6"
2'-0"
4' -0
2'-0"
3' -6
4' -0
4' -6
W / C
LO
S
E R
4' -0
W / C
LO
S
E R
W /C
LO
S
E R
A N
D L
A
TC
H
ALL WORK SHALL COMPLY WITH FEDERAL ABA,
LOCAL, AND STATE ACCESSIBILITY CODES AND
REQUIREMENTS.
DOOR LOCATIONS
TYPICAL DETAILS
TYP DOOR LOCATION
SEE DOOR SCHEDULE
4"
TYP
TYPICAL SIGNAGE MOUTING HEIGHTS
A A
5' -0
4' -9
EQ EQ
PROVIDE BLOCKING AT ALL WALL MOUNTED EQUIPMENT AND ACCESSORIES
3' -4
3' -8
CL
CL
FEC GARMENT
HOOK
TYPICAL SCRUB SINK
PAPER
TOWEL
DISPENSER
3' -5
3' -6
SOAP
DISPENSER
2' -1
0"
1'-6"
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
DATE:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
BID DOCUMENTS
590 MEANS ST NW
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and
Facilities Management
Drawn
SV SJ/KB
516-22-112
12-23-2025REVISIONS:
A
B
C
D
E
F
UPGRADE PHARMACY IV MIXING ROOM
USP 797/800
CAPE CORAL, FLORIDA
NOTES, ABBREVIATIONS AND LEGENDS
GI002
3 4 5 6 7
H
K
M
N
Q
2 8
ELECTRICAL
1B-189
DATA
1B-190
SIGNAL
1B-191
CLEAN CARTS
1B-188
MED. SUP.
1B-163
LOCKERS
1B-162
RECYCLE
1B-185
EMS CHIEF
1B-180
TRASH
COLLECTION
1B-182
INF WASTE
1B-184
MAIL / WORK
ROOM
1B-179
SUPPLY ADMIN.
1B-155
ISSUE AREA
1B-154
CHIEF SPD
1B-153
MED. GAS
1B-160
FLAMM.
1B-159
GENERAL
STORAGE
1B-156
STERILE STORAGE
1B-157
EQ. STORAGE
1B-158
CHIEF
1B-140
CHIEF
1B-176
ASSIST.
1B-177
OFFICE ASSIST.
1B-178
CORRIDOR
C1-21
TLT
1B-173
TLT
1B-174
DATA PROCESS.
1B-172
SECURE DISP.
1B-170
SECURE DISP
1B-171
RAD. CHECK-IN
1B-137
STAFF PHYSIC.
1B-138
STAFF PHYSIC.
1B-139
CORRIDOR
C1-17
PHARMD
1B-168
OFFICE
1B-167
WAITING AREA
FEC
FEC
FECFEC
FEC
CHEMO BUFFER
1B-166
ANTE ROOM
1B-165
IV BUFFER
1B-164
CORRIDOR
C1-24
CORRIDOR
C1-25
CORRIDOR
C1-23
CORRIDOR
C1-22
ELEVATOR ELEVATOR
#ICRA BARRIER PLAN KEY NOTES:
PRIOR TO COMMENCING THE WORK, CONTRACTOR TO INSTALL
INFECTION CONTROL BARRIERS AND ENTRANCES. WORK SHALL BE
PERFORMED ON WEEKENDS AS DIRECTED BY THE COR. PROVIDE
KEYPAD LOCKSET AT ICRA BARRIER ENTRANCE DOORS.
ICRA BARRIER PLAN LEGEND
INFECTION CONTROL BARRIER
AND ENTRANCE DOOR
ICRA BARRIER PLAN GENERAL NOTES:
A. COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL BARRIER WALL CONSTRUCTION
AND INFECTION CONTROL MEASURES WITH COR AND PATIENT SAFETY/INFECTION CONTROL
REPRESENTATIVE. TEMPORARY IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS
ARE APPROXIMATE. CONTRACTOR SHALL PROVIDE MEASURED DRAWINGS TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA PROTOCOLS AND
SCHEDULE IS APPROVED.
B. EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED DURING NORMAL
BUSINESS HOURS. ANY INTERRUPTIONS MUST BE REQUESTED AHEAD OF TIME AND
APPROVED. SEE SPECIFICATION 013526 AND MEMO 001S-08-18 FOR PROCEDURES AND HOURS
OF OPERATION.
C. PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES: A 24"X36" STICKY WALK OFF MAT
AND HAND SANITIZER AT EACH TEMPORARY DOOR LOCATION. MAT SHALL BE REPLACED OR
CLEANED AS NECESSARY.
D. PROVIDE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH TEMPORARY ICRA
ENTRANCE DOOR.
E. PROVIDE ICRA BARRIERS AND ENTRANCE DOORS AS REQUIRED AND INDICATED ON FLOOR
PLANS. COORDINATE LOCATIONS WITH COR. BASIS OF DESIGN: STARC SYSTEMS. CONTACT:
MAX DANSKY; OFFICE : 207-844-2789; CELL: 978-502-9689; EMAIL:
MDANSKY@STARCSYSTEMS.COM.
F. CONTRACTOR SHALL MAINTAIN 4'-0" CLEAR WIDTH IN THE CORRIDOR FROM THE ICRA BARRIER
FOR CIRCULATION THROUGHOUT THE CONSTRUCTION.
G. PLANS PROVIDED ARE FOR GUIDANCE, CONTRACTOR TO PROVIDE SUBMITTAL PACKAGE
SHOWING ACTUAL LAYOUT AND CONSTRUCTION OF BARRIERS FOR REVIEW AND APPROVAL OF
COR.
LIMITS OF CONSTRUCTION
UNLESS NOTED OTHERWISE
3 4
M
P
N
Q
FROZEN SECT.
2B-169
CONTROL/COMM
2B-170
OR (ENDO)
2B-171
OR (ENDO)
2B-172
OR
2B-159
OR
2B-160
ANES.
2B-162
CORRIDOR
C2-29
CORRIDOR
C2-28
HAC
2B-112
2B-114
2B-115
2B-116
2B-117
SURGICAL
STORAGE
2B-175
MALE LOCKER
2B-176
FEMALE LOCKER
2B-178SURGICAL
STORAGE
2B-161 ANES. OFFICE
2B-163
CHASE
PROJECT
AREAS
KEY PLAN
NTS
TRUE
NORTH
PLAN
NORTH
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
DATE:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
BID DOCUMENTS
590 MEANS ST NW
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and
Facilities Management
Drawn
SV SJ/KB
516-22-112
12-23-2025REVISIONS:
A
B
C
D
E
F
UPGRADE PHARMACY IV MIXING ROOM
USP 797/800
CAPE CORAL, FLORIDA
PARTIAL FIRST FLOOR AND SECOND FLOOR
ICRA PLANS
GI003
1/8" = 1'-0"GI003
1 PARTIAL FIRST FLOOR ICRA PLAN
1/8" = 1'-0"GI003
2 PARTIAL SECOND FLOOR ICRA PLAN
0' 4' 8' 16' 24'
SCALE: 1/8" = 1' - 0"
DESIGN CODES:
1.01 2021 INTERNATIONAL BUILDING CODE (IBC) AS MODIFIED BY:
A. ANSI/ASCE 7-16, MINIMUM DESIGN LOADS FOR BUILDINGS AND OTHER STRUCTURES
B. VA SEISMIC DESIGN REQUIREMENTS H-18-8, 2024 EDITION
C. VA STRUCTURAL DESIGN MANUAL, JULY 1, 2023
D. VA PHYSICAL SECURITY RESIDENCY DESIGN MANUAL 2024 EDITION
1.02 AMERICAN CONCRETE INSTITUTE (ACI)
A. ACI 318-19 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE
1.03 AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
A. ANSI/AISC 360-16, SPECIFICATION FOR STRUCTURAL STEEL BUILDINGS
DESIGN LOADS:
1.01 DESIGN LOADS ARE AS FOLLOWS:
A. DEAD LOADS:
1. WALL:
a. SUPERIMPOSED: SELF WEIGHT OF MATERIALS
B. COLLATERAL LOADS: N/A
C. LIVE LOADS: N/A
D. SNOW LOADS:
1. GROUND SNOW LOADS PG = 0 PSF
2. IMPORTANCE FACTOR Is = 1.2
3. UNIFORM DESIGN SNOW LOAD (Pf) = 0 PSF
E. WIND LOADS:
1. ULTIMATE DESIGN WIND SPEED V, ULT = 154 MPH
2. NOMINAL DESIGN WIND SPEED V, ASD = 120 MPH
3. RISK CATEGORY = IV
4. WIND EXPOSURE = C
5. LATERAL SYSTEM = SAME AS FOR EARTHQUAKE LOADS
6. INTERNAL PRESSURE COEFFICIENT = ±0.18 (ENCLOSED)
DESIGN WIND PRESSURES: PLUS AND MINUS SIGNS SIGNIFY PRESSURE ACTING TOWARD AND AWAY
FROM EXTERIOR SURFACE RESPECTIVELY.
LOCATION ZONE
EFFECTIVE
WIND AREA (SF)
ULTIMATE DESIGN WIND
PRESSURE
(PSF)
ROOF
WALLS
5 5 a = 31'-7" h = 83'-6" a a h a a
-76.5,+16
2a
-66.6,+16
-62.3,+16
-120.2,+16
-106.2,+16
-100.2,+16
-52.3,+52.3
-49.6,+48.2
-47.5,+45.1
-95.9,+52.3
-84.9,+48.2
-76.5,+45.1
-120.2,+16
-106.2,+16
-100.2,+16
F. EARTHQUAKE LOADS:
1. RISK CATEGORY = IV
2. SEISMIC IMPORTANCE FACTOR Ie = 1.5
3. VA SEISMIC REQUIREMENTS H-18-8, 2023 EDITION
a. Ss = 0.055
b. S1= 0.024
4. SITE CLASS = D
5. SPECTRAL RESPONSE COEFFICIENTS (FOR SITE CLASS D)
a. Ss = 0.049 G
b. S1 = 0.035 G
6. SEISMIC DESIGN CATEGORY = A
1.02 DEFLECTION CRITERIA: REFER TO TABLE 1604.3 IN THE IBC FOR DEFLECTION LIMITS
GENERAL STRUCTURAL NOTES:
1.01 ELEVATIONS AS SHOWN ON THE STRUCTURAL DRAWINGS ARE RELATIVE TO FINISHED GROUND
FLOOR LEVEL ELEVATION = 0'-0". COORDINATE WITH EXISTING.
1.02 WHERE A DETAIL, TYPICAL DETAIL, SECTION, TYPICAL SECTION OR NOTE IS SHOWN FOR ONE CONDITION, IT SHALL APPLY FOR ALL SIMILAR OR LIKE CONDITIONS UNLESS OTHERWISE NOTED.
1.03 THE STRUCTURAL DESIGN OF THE BUILDING IS BASED ON THE FULL INTERACTION OF ALL ITS
COMPONENT PARTS, WITH NO PROVISION MADE FOR CONDITIONS OCCURRING DURING
CONSTRUCTION. THEREFORE, CONTRACTOR SHALL PROVIDE ADEQUATE BRACING AND
TEMPORARY SHORING DURING CONSTRUCTION IN ACCORDANCE WITH APPLICABLE STANDARDS.
1.04 CONTRACTOR IS RESPONSIBLE FOR ALL JOB SITE SAFETY INCLUDING THE SAFE RIGGING, LIFTING
AND SETTING OF MATERIALS AND EQUIPMENT IN ACCORDANCE WITH APPLICABLE STANDARDS.
1.05 FURNISH AND INSTALL ALL NECESSARY ATTACHMENTS, ANCHORAGES AND ACCESSORIES TO PROVIDE A COMPLETE STRUCTURALLY SOUND BUILDING WITH A CONTINUOUS LOAD PATH. BRING
ANY DISCONTINUITIES TO THE ATTENTION OF THE GOVERNMENT IMMEDIATELY.
1.06 FIELD VERIFY EXISTING CONDITIONS PRIOR TO COMMENCEMENT OF FABRICATION OR
CONSTRUCTION. BRING ANY DISCREPANCIES ALONG WITH DETAILED FIELD SKETCHES OF AS-
BUILT CONDITIONS TO THE ATTENTION OF THE GOVERNMENT IMMEDIATELY.
1.07 COORDINATE AND VERIFY ALL DIMENSIONS AND DETAILS WITH THE CIVIL, ARCHITECTURAL, MECHANICAL, ELECTRICAL, PLUMBING, FIRE PROTECTION, SHOP, AND SUBMITTAL DRAWINGS.
NOTIFY THE GOVERNMENT IMMEDIATELY OF ANY DISCREPANCIES.
1.08 WHERE A CONFLICT BETWEEN THE SPECIFICATION AND THE DRAWINGS OCCURS FOLLOW THE
REQUIREMENTS SHOWN ON THE DRAWINGS.
1.09 THIS PROJECT INVOLVES WORK INCLUDED IN BID ALTERNATES, AS DESCRIBED IN SPECIFICATION SECTION 01 00 00, "BID ITEMS". REFER TO SPECIFICATIONS FOR DESCRIPTIONS OF ALL BID
ALTERNATES, WHICH MAY ELIMINATE OR REPLACE WORK INCLUDED IN THE BASE BID. THESE
DRAWINGS MAY ALSO INCLUDE ADDITIONAL NOTES WHERE REQUIRED TO ADEQUATELY IDENTIFY
BID ALTERNATES.
SHOP DRAWINGS
1.01 STRUCTURAL DRAWINGS INDICATE TYPICAL AND CERTAIN SPECIFIC CONDITIONS ONLY. SHOP
DRAWINGS SHALL DETAIL ALL CONDITIONS IN ACCORDANCE WITH SPECIFIED STANDARDS AND
THE SPECIFIC REQUIREMENTS OF THIS PROJECT AS INDICATED ON THE DRAWINGS AND
SPECIFICATIONS.
1.02 CONTRACTOR SHALL PROVIDE A MINIMUM OF ONE HARD COPY AND LEGIBLE PDF FOR EACH
STRUCTURAL COMPONENT FOR REVIEW PRIOR TO FABRICATION. DRAWINGS EXCEEDING C-SIZE
(17X22) SHALL BE 1/2 SIZE.
1.03 PHOTOCOPY REPRODUCTIONS OF THE CONTRACT DOCUMENTS WILL BE REJECTED AND
CONTRACTOR WILL BE RESPONSIBLE FOR ANY ASSOCIATED DELAYS. STRUCTURAL DRAWINGS
INDICATE TYPICAL AND CERTAIN SPECIFIC CONDITIONS ONLY. SHOP DRAWINGS SHALL DETAIL ALL CONDITIONS IN ACCORDANCE WITH SPECIFIED STANDARDS AND THE SPECIFIC REQUIREMENTS OF
THIS PROJECT AS INDICATED ON THE DRAWINGS. THE PURPOSE OF SHOP DRAWINGS IS TO
VERIFY THAT THE CONTRACTOR HAS INTERPRETED THE INTENT OF THE CONSTRUCTION
DOCUMENTS CORRECTLY, DETAIL ALL CONDITIONS, INDEPENDENTLY CHECK, CONFIRM AND
COORDINATE ALL DIMENSIONS AND DETAILS, TAKE FIELD MEASUREMENTS, VERIFY FIELD
CONDITIONS, FUNCTIONALITY AND CONTRACTIBILITY AS WELL AS COORDINATE WITH OTHER
TRADES AND ACTUAL PRODUCTS PURCHASED. THE CONTRACT DRAWINGS ARE NOT INTENDED
FOR THIS PURPOSE AND TRANSLATION OF ELECTRONIC MEDIA MAY NOT BE ACCURATE. THE USE
OF PHOTOCOPY REPRODUCTIONS DEFEATS THE PURPOSE OF SHOP DRAWINGS AND DOING SO I
ENTIRELY AT THE CONTRACTORS OWN RISK.
1.04 SUBMITTALS FOR VENDOR DESIGN COMPONENTS, INCLUDING BUT NOT LIMITED TO LIGHT GAUGE
STEEL FRAMING, WINDOWS, AND DOORS, SHALL BE ACCOMPANIED BY DRAWINGS AND
CALCULATIONS SEALED BY A STRUCTURAL ENGINEER REGISTERED IN THE STATE OF THE
PROJECT. IN ADDITION, THESE SHOP DRAWINGS AND CALCULATIONS SHALL BE PREPARED UNDER
THE DIRECT SUPERVISION OF THE STRUCTURAL ENGINEER SEALING THIS WORK.
1.05 REVIEW OF SUBMITTALS INCLUDING SHOP DRAWINGS DOES NOT RELIEVE THE CONTRACTOR OF
THE SOLE RESPONSIBILITY FOR ERRORS AND OMISSIONS ASSOCIATED WITH THE PREPARATION
OF THOSE SUBMITTALS.
1.06 SUBMITTALS SHALL BE REVIEWED BY THE CONTRACTOR, PRIOR TO SUBMISSION FOR ENGINEER'S
REVIEW, FOR CONFORMANCE WITH THE CONSTRUCTION DOCUMENTS AND AS-BUILT CONDITIONS.
ANY DEVIATIONS FROM THE CONSTRUCTION DOCUMENTS SHALL BE CLEARLY NOTED ALONG WITH
REASONS FOR THE DEVIATION.
1.07 THE STRUCTURAL ENGINEER HAS BUDGET FOR ONE COORDINATED SUBMITTAL REVIEW. THE
CONTRACTOR SHALL REIMBURSE THE STRUCTURAL ENGINEER FOR MULTIPLE REVIEWS
REQUIRED DUE TO INCOMPLETE SUBMITTALS.
1.08 ALLOW A MINIMUM OF TWO CALENDAR WEEKS (14 DAYS), THREE CALENDAR WEEKS (21 DAYS) AT
CHRISTMAS AND NEW YEARS FROM RECEIPT OF SUBMITTALS AT THE ENGINEERS OFFICE FOR
REVIEW. ALLOW TIME IN THE CONSTRUCTION SCHEDULE FOR SHIPPING AND PROCESSING TIME IN
ADDITION TO SUCH REVIEWS.
EXISTING CONDITIONS:
1.01 AS WITH ANY WORK AFFECTING EXISTING CONSTRUCTION, UNFORESEEN CONDITIONS ARE
UNAVOIDABLE WITHOUT DEMOLISHING OTHERWISE SERVICEABLE CONSTRUCTION, DISRUPTING
OCCUPIED OPERATIONS AND INCURRING SIGNIFICANT COST FOR CLOSE UP EXAMINATION AND
NON-DESTRUCTIVE TESTING DURING THE DESIGN STAGE.
1.02 WITH THE PASSAGE OF TIME SINCE THE CREATION OF AS-BUILT DRAWINGS AND/OR THE
DESIGNERS SURVEY, BOTH CONCEALED AND VISIBLE CONDITIONS MAY HAVE CHANGED DUE TO
ALTERATIONS, ADDITIONS, RENOVATIONS AND DETERIORATION.
1.03 PRIOR TO THE COMMENCEMENT OF ANY WORK IN PREPARATION OF CONSTRUCTION RELATED
ACTIVITIES, INCLUDING BUT NOT LIMITED TO SHOP DRAWING PREPARATION, ALL BURIED,
EMBEDDED, AND CONCEALED ITEMS LIKELY TO BE ENCOUNTERED DURING CONSTRUCTION SHALL
BE LOCATED AND MARKED ON THE SURFACE. THIS WORK SHALL BE ACCOMPLISHED BY
DESTRUCTIVE AND/OR NON-DESTRUCTIVE MEANS WITHOUT IMPAIRING THE STRUCTURAL
INTEGRITY OF THE ASSOCIATED MEMBERS. SHORING AS REQUIRED SHALL BE DESIGNED BY A
PROFESSIONAL STRUCTURAL ENGINEER, LICENSED IN THE STATE OF THE PROJECT, AND
FURNISHED AND INSTALLED AT NO ADDITIONAL COST.
1.04 EXISTING CONDITIONS THAT INTERFERE OR OTHERWISE AFFECT THE DESIGN, CONSTRUCTION
OR SERVICEABILITY OF THE WORK SHALL BE BROUGHT TO THE ATTENTION OF THE
GOVERNMENT, INCLUDING PLAN AND SECTION SKETCHES, IMMEDIATELY FOR RESOLUTION.
THE CONTRACTOR SHALL ALLOW TWO CALENDAR WEEKS IN THE SCHEDULE FOR DESIGN
RESOLUTION THE INTERFERENCE AFTER ALL INFORMATION ABOUT THE INTERFERENCE,
INCLUDING SIZE, LOCATION AND FUNCTION OF THE EMBEDMENT, HAS BEEN RECEIVED BY THE
GOVERNMENT.
1.05 BURIED ITEMS OF CONCERN INCLUDE THOSE THAT MAY INTERFERE WITH PROPOSED
CONSTRUCTION AND THOSE WITHIN 12 INCHES BELOW A SLAB ON GRADE AND 4 FT BELOW
AND WITHIN THE FOOTING BEARING ZONE (DEFINED AS THE AREA BENEATH 1V:2H LINES
EXTENDING DOWNWARD AND OUTWARD FROM THE BOTTOM FOOTING EDGES). UNLESS
OTHERWISE NOTED, PIPES SHALL NOT BE ALLOWED TO RUN UNDER A FOUNDATION. WHERE
SPECIFICALLY ALLOWED AND UNLESS OTHERWISE DETAILED, A PIPE RUNNING BELOW A
FOUNDATION SHALL BE SLEEVED WITHIN A GALVANIZED PIPE 3 INCHES LARGER IN DIAMETER
WHICH EXTENDS 12 INCHES BEYOND THE INFLUENCE LINES. PIPES EXTENDING THROUGH A
FOUNDATION SHALL BE CONTAINED WITHIN A GALVANIZED PIPE SLEEVE 3 INCHES LARGER IN
DIAMETER. THE ENDS OF THE PIPE SLEEVES SHALL BE SEALED WITH A EXPANDING
COMPRESSIBLE FOAM OR MODULAR ELASTOMER SEALING SYSTEM TO PREVENT THE ENTRY
OF SILT INTO THE ANNULAR SPACE.
STRUCTURAL STEEL NOTES:
1.01 PART 1 GENERAL
A. GENERAL REQUIREMENTS
1. DESIGN, FABRICATION AND ERECTION OF STRUCTURAL STEEL SHALL BE IN
ACCORDANCE WITH THE MANUAL OF STEEL CONSTRUCTION, BY THE AMERICAN
INSTITUTE OF STEEL CONSTRUCTION, INC.
2. THE STRUCTURAL STEEL LATERAL LOAD-RESISTING SYSTEM INCLUDING BUT NOT
LIMITED TO BRACED FRAMES SHALL BE DESIGNED AND DETAILED IN ACCORDANCE WITH
AISC "SPECIFICATION FOR STRUCTURAL STEEL BUILDINGS".
B. SUBMITTALS
1. SHOP DRAWINGS: ERECTION AND FABRICATION DRAWINGS. SHOP DRAWINGS SHALL NOT
CONTAIN REPRODUCTIONS OF THE CONTRACT DRAWINGS. MEMBER SUBSTITUTION AND
DEVIATIONS FROM THE CONTRACT DRAWINGS SHALL BE CLEARLY IDENTIFIED WITH AN
EXPLANATION FOR THE PROPOSED DEVIATION.
2. CALCULATIONS: PRIOR TO PREPARATION OF FABRICATION DRAWINGS, ALL
CONNECTIONS SHALL BE DESIGNED AND DOCUMENTED WITH CALCULATIONS SEALED BY
THE CONTRACTORS PROFESSIONAL ENGINEER REGISTERED IN THE STATE OF THE
PROJECT.
C. QUALITY ASSURANCE
1. CONNECTION DESIGN SHALL BE PERFORMED UNDER THE DIRECT SUPERVISION OF A
PROFESSIONAL ENGINEER LICENSED IN THE STATE OF THE PROJECT.
2. AISC CERTIFICATION:
a. FABRICATOR SHALL BE AISC QUALITY CERTIFIED FOR THE FOLLOWING CATEGORY:
1) STD - STANDARD FOR STEEL BUILDING STRUCTURES
b. ERECTOR SHALL BE AISC QUALITY CERTIFIED FOR THE FOLLOWING CATEGORY:
1) CSE = CERTIFIED STEEL ERECTOR - FOR SIMPLE LOW RISE AND LIGHT INDUSTRIAL
STEEL STRUCTURES
D. DELIVERY, STORAGE AND HANDLING
1. PROTECT STEEL MEMBER FROM CORROSION, DEFORMATION, AND OTHER TYPES OF
DAMAGE. STORE ITEMS IN AN ENCLOSED AREA FREE FROM CONTACT WITH SOIL AND
WEATHER. REMOVE AND REPLACE DAMAGED ITEMS WITH NEW ITEMS.
1.02 PRODUCTS
A. MATERIALS:
1. ALL WIDE FLANGE W'S & WT'S SHALL BE IN CONFORMANCE WITH ASTM A 992, LATEST
ADOPTED EDITION, GRADE 50, UNO.
2. ALL OTHER SHAPES, PLATES AND BARS SHALL BE IN CONFORMANCE WITH ASTM A 36,
LATEST ADOPTED EDITION, UNO.
3. ALL SQUARE, RECTANGULAR AND ROUND TUBING SHALL BE IN CONFORMANCE WITH
ASTM A 500, LATEST ADOPTED EDITION, GRADE B.
4. ALL ROUND PIPE SHALL BE IN CONFORMANCE WITH ASTM A 53, LATEST ADOPTED
EDITION, GRADE B.
5. BOLTS SHALL COMPLY WITH ASTM A 325, TYPE 1 UNO.
6. BOLTS/NUT/WASHER ASSEMBLY SHALL COMPLY WITH TWIST-OFF-TYPE TENSION-
CONTROL BOLTS IN ACCORDANCE WITH ASTM F 1852 (SAME STRENGTH AS A 325) TYPE 1
LOAD INDICATOR BOLTS.
7. THREADED RODS SHALL COMPLY WITH ASTM A 36, LATEST ADOPTED EDITION, UNO.
8. ANCHOR RODS SHALL COMPLY WITH ASTM F 1554, LATEST ADOPTED EDITION, UNO.
a. GRADE 36
9. HARDENED STEEL WASHERS SHALL COMPLY WITH ASTM F 436.
10.HEAVY HEX NUTS SHALL COMPLY WITH ASTM A 563.
11.WEDGE ANCHORS, ACCEPTABLE PRODUCTS
a. KWIK BOLT3, HILTI INC.
b. WEDGE-ALL, SIMPSON STRONG-TIE COMPANY INC.
c. POWER-STUD, POWERS FASTENERS INC.
12.DEFORMED BAR ANCHORS:
a. WELDED REINFORCING STEEL SHALL CONFORM TO ASTM A 706 AND BE WELDED IN
ACCORDANCE WITH AWS D 1.4.
b. DEFORMED BAR SHALL BE WELDED TO STRUCTURAL STEEL. COUPLERS AVAILABLE
FOR #4 AND #5 REBAR SIZES SHALL BE STUD-ARC WELDED TO THE STEEL. LENTON
TAPER REBAR SHALL THEN BE INSTALLED IN THE FIELD IN ACCORDANCE WITH
MANUFACTURER'S INSTRUCTIONS.
13.GROUT FOR BASE PLATES (WHERE SHOWN OR REQUIRED) SHALL BE NON-SHRINK, NON-
METALLIC FACTORY PREMIXED GROUT HAVING A COMPRESSIVE STRENGTH OF 6800 PSI
(MIN.) AT 28 DAYS.
B. FABRICATION
1. ALL NATURAL AND FABRICATED CAMBER SHALL BE INSTALLED UPWARD.
2. THE MINIMUM THICKNESS OF GUSSET AND FIN PLATES SHALL BE 3/8".
3. ANCHOR RODS:
a. BOLT HEADS AND NUTS SHALL BE HEAVY HEX. ANCHOR RODS SHALL BE A MINIMUM OF
3/4" DIA.. EQUAL SIZE AND STRENGTH THREADED RODS WITH TACK WELDED NUTS
MAY BE USED IN LIEU OF HEADED BOLTS.
b. ANCHOR RODS SHALL BE EMBEDDED TO 3" ABOVE THE BOTTOM OF THE LOWEST
FOOTING UNO.
4. BOLTED CONNECTIONS:
a. ALL BOLTS SHALL BE CONSIDERED AS "BEARING" TYPE N, UNO.
b. THE MINIMUM NUMBER OF BOLTS IN STRUCTURAL STEEL CONNECTIONS SHALL BE AS
FOLLOWS:
1) A MINIMUM OF TWO BOLTS PER CONNECTION SHALL BE USED.
2) IN CONNECTIONS WHERE THE BEAM SHEAR, V, IS NOT NOTED ON THE DRAWINGS,
THE CONNECTION SHALL DEVELOP THE BEAM SHEAR BASED ON THE UNIFORM
LOAD TABLES IN THE AISC MANUAL, SEE DESIGN CODE NOTES.
5. CONNECTIONS THAT ARE PART OF A BRACED FRAME ARE SLIP CRITICAL AND SHALL
DEVELOP THE FULL STRENGTH OF THE CONNECTED MEMBERS, UNLESS FORCES ARE
INDICATED ON THE DRAWINGS.
C. FINISH (EXPOSED TO ELEMENTS)
1. SURFACE PREPARATION:
a. EPOXY FINISH SYSTEM:
1) NEW STEEL - SSPC-SP 6 COMMERCIAL BLAST CLEANING
2) WELDS - REMOVE SLAG, WIRE BRUSH AND SSPC-SP 1 SOLVENT CLEANING
2. PRIMER:
a. EPOXY FINISH SYSTEM:
1) APPLY (1) COAT OF INORGANIC ZINC RICH PRIMER IN ACCORDANCE WITH MASTER
PAINTERS INSTITUTE MP #19. (3 TO 4 MILS DFT)
3. FINISH COATING:
a. APPLY (1) INTERMEDIATE COAT OF EPOXY, HIGH BUILD, LOW GLOSS COAT IN
ACCORDANCE WITH MASTER PAINTERS INSTITUTE MP #108. (4 TO 6 MILS DFT)
b. APPLY (1) TOP COAT POLYURETHANE, TWO COMPONENT, PIGMENTED, GLOSS (MPI
GLOSS LEVEL 6) IN ACCORDANCE WITH MASTER PAINTERS INSTITUTE MP #72.
(2 TO 3 MILS DFT)
c. STANDARD COLORS AS SELECTED BY THE GOVERNMENT OR OTHERWISE SPECIFIED
STRUCTURAL STEEL NOTES: (CTD)
D. FINISH (ALL OTHER STEEL)
1. SURFACE PREPARATION:
a. UNLESS NOTED OTHERWISE, SHOP CLEAN THE SURFACE OF ALL STRUCTURAL STEEL IN
ACCORDANCE WITH THE REQUIREMENTS OF SSPC-SP2.
2. PRIMER:
a. UNLESS NOTED OTHERWISE SHOP PAINT WITH A MINIMUM OF 1.0 MILS OF THE RUST
INHIBITIVE PRIMER.
3. FINISH COATING
a. PAINT AS SPECIFIED
b. STANDARD COLORS AS SELECTED BY THE GOVERNMENT OR OTHERWISE SPECIFIED
1.03 PART 3 EXECUTION
A. EXAMINATION
1. PRIOR TO STRUCTURAL STEEL ERECTION, ERECTOR SHALL INSPECT EXISTING
CONSTRUCTION FOR CORRECT SIZE, LAYOUT AND ALIGNMENT. ANY INCONSISTENCIES
DEEMED DETRIMENTAL TO THE ERECTION OF STEEL SHALL BE REPORTED AND REPAIRED
PRIOR TO INSTALLATION.
B. INSTALLATION
1. BOLTED CONNECTIONS SHALL BE ASSEMBLED AND INSPECTED IN ACCORDANCE WITH
RCSC-2010, SPECIFICATION FOR STRUCTURAL JOINTS USING HIGH-STRENGTH BOLTS BY THE
RESEARCH COUNCIL ON STRUCTURAL CONNECTIONS.
a. PRE-TENSIONED JOINTS (UNO)
1) TWIST-OFF-TYPE TENSION-CONTROL BOLT PRE-TENSIONING
2. WELDED CONNECTIONS SHALL BE MADE WITH E70XX ELECTRODES IN ACCORDANCE WITH
AWS D1.1, STRUCTURAL WELDING CODE BY THE AMERICAN WELDING SOCIETY, AND SHALL
BE PERFORMED BY CERTIFIED WELDERS. WELDER CERTIFICATION SHALL BE AVAILABLE ON
SITE DURING TIMES OF INSPECTION.
3. GROUT:
a. GROUT SHALL BE INSTALLED IN ACCORDANCE WITH MANUFACTURER'S
RECOMMENDATIONS.
4. FINISH
a. SEE ARCHITECTURAL NOTES/SPECIFICATIONS.
b. BURIED STEEL
1) TWO COATS, 12 MILS MINIMUM PER COAT, SINGLE COMPONENT BITUMEN MASTIC
COATING. PREPARE SURFACE AS RECOMMENDED BY THE MANUFACTURER TO 6"
ABOVE GRADE UNO.
C. FIELD QUALITY CONTROL
1. TOLERANCES
a. FABRICATION TOLERANCES SHALL BE IN CONFORMANCE WITH THE CODE OF STANDARD
PRACTICE FOR STEEL BUILDINGS AND BRIDGES BY THE AMERICAN INSTITUTE OF STEEL
CONSTRUCTION, APRIL 14, 2010.
2. BOLTED CONNECTIONS
a. ALL BOLTS SHALL BE VISUALLY INSPECTED IN ACCORDANCE WITH THE "SPECIFICATION
FOR STRUCTURAL JOINTS USING HIGH-STRENGTH BOLTS", LATEST EDITION ADOPTED BY
THE BUILDING CODE IN AFFECT AT THE TIME OF PERMITTING.
3. WELDED CONNECTIONS:
a. ALL WELDS SHALL BE VISUALLY EXAMINED.
b. 15% OF ALL WELDS SHALL BE TESTED IN ACCORDANCE WITH THE FOLLOWING METHODS:
1) FULL AND PARTIAL PENETRATION WELDS SHALL BE TESTED ULTRASONICALLY IN
ACCORDANCE WITH ASTM E 164.
2) ALL OTHER WELDS SHALL BE TESTED BY THE LIQUID PENETRANT METHOD IN
ACCORDANCE WITH ASTM E 165 OR THE MAGNETIC PARTICLE METHOD IN
ACCORDANCE WITH ASTM E 709.
3) IN THE EVENT ANY OF THE TESTED WELDS FAIL TO MEET THE TESTING CRITERIA, ALL
WELDS MADE BY THE SAME WELDER SHALL BE TESTED.
D. REPAIR
1. PROTECTIVE COATINGS DAMAGED DURING THE TRANSPORTATION, ERECTION AND FIELD
WELDING PROCESSES SHALL BE REPAIRED IN THE FIELD TO MATCH THE SHOP APPLIED
COATING.
E. CLEANING AND PROTECTION
1. CLEAN AFTER INSTALLATION EXPOSED PREFINISHED ITEMS IN ACCORDANCE WITH
MANUFACTURER'S RECOMMENDATIONS.
PROTECT INSTALLED ITEMS FROM DAMAGE CAUSED BY SUBSEQUENT CONSTRUCTION.
POST-INSTALLED ANCHORS:
1.01 POST-INSTALLED ANCHORS SHALL ONLY BE USED WHERE SPECIFIED ON THE CONSTRUCTION
DOCUMENTS. THE CONTRACTOR SHALL OBTAIN APPROVAL FROM THE ENGINEER-OF-RECORD
PRIOR TO INSTALLING POST-INSTALLED ANCHORS IN PLACE OF MISSING OR MISPLACED CAST-
IN-PLACE ANCHORS. CARE SHALL BE TAKEN IN PLACING POST-INSTALLED ANCHORS TO AVOID
CONFLICTS WITH EXISTING REBAR. HOLES SHALL BE DRILLED AND CLEANED IN ACCORDANCE
WITH THE MANUFACTURER'S WRITTEN INSTRUCTIONS. SUBSTITUTION REQUESTS, FOR
PRODUCTS OTHER THAN THOSE SPECIFIED BELOW, SHALL BE SUBMITTED BY THE
CONTRACTOR TO THE ENGINEER-OF-RECORD ALONG WITH CALCULATIONS THAT ARE
PREPARED & SEALED BY A REGISTERED PROFESSIONAL ENGINEER. THE CALCULATIONS SHALL
DEMONSTRATE THAT THE SUBSTITUTED PRODUCT IS CAPABLE OF ACHIEVING THE PERTINENT
EQUIVALENT PERFORMANCE VALUES (MINIMUM) OF THE SPECIFIED PRODUCT USING THE
APPROPRIATE DESIGN PROCEDURE AND/OR STANDARD(S) AS REQUIRED BY THE BUILDING
CODE.
1.02 CONCRETE ANCHORS
A. MECHANICAL ANCHORS FOR USE IN CRACKED AND UNCRACKED CONCRETE SHALL HAVE
BEEN TESTED AND QUALIFIED FOR USE IN ACCORDANCE WITH ACI 355.2 AND ICC-ES AC193.
PRE-APPROVED MECHANICAL ANCHOR MANUFACTURERS:
1. SIMPSON STRONG-TIE ANCHORING SYSTEMS
2. HILTI
3. POWERS
B. ADHESIVE ANCHORS FOR USE IN CRACKED AND UNCRACKED CONCRETE SHALL HAVE BEEN
TESTED AND QUALIFIED FOR USE IN ACCORDANCE WITH ICC-ES AC308. PRE-APPROVED
ADHESIVE ANCHOR MANUFACTURERS
1. SIMPSON STRONG-TIE ANCHORING SYSTEMS
2. HILTI
3. POWERS
STRUCTURAL DRAWING ABBREVIATIONS:
BOT BOTTOM
B/STL BOTTOM OF STEEL
C.J. CONSTRUCTION OR CONTROL JOINT
CJT CORNER JACK TRUSS
CMU CONCRETE MASONRY UNIT
CONN CONNECTION
DBA DEFORMED BAR ANCHOR
DIAG DIAGONAL
EA EACH
EF EACH FACE
EL ELEVATION
EMBED EMBEDMENT
EOD EDGE OF DECK
EOS EDGE OF SLAB
EW EACH WAY
EXF EXISTING FOOTING
FOB FACE OF BRICK
FF FAR FACE
FP FACE OF PANEL
FWC FOR WOOD CONSTRUCTION
FX FOOTING MARK NUMBER (SEE SCHEDULE)
GT GIRDER TRUSS
HORIZ HORIZONTAL
IFW INSIDE FACE OF WALL
JB JOIST BEARING
JT JACK TRUSS
LLH LONG LEG HORIZONTAL
LLO LONG LEG OUT
LLV LONG LEG VERTICAL
LSH LONG SIDE HORIZONTAL
LSV LONG SIDE VERTICAL
MAX. MAXIMUM
MIN. MINIMUM
NDS NATIONAL DESIGN STANDARD
NF NEAR FACE
OC ON CENTER
OFW OUTSIDE FACE OF WALL
PAF POWDER ACTUATED FASTENER
PC PRECAST
PDF POWDER DRIVEN FASTENER
PJF PREMOLDED JOINT FILLER
PLF POUNDS PER LINEAR FOOT
PTC POST TENSIONED CONCRETE
PTW PRESSURE TREATED WOOD
PXXX PIER MARK NUMBER (SEE SCHEDULE)
REF REFERENCE
REQ'D REQUIRED
RRS REBAR REINFORCING STEEL
SOG SLAB-ON-GROUND
STD STANDARD
T&B TOP AND BOTTOM
T/FTG TOP OF FOOTING
T/STL TOP OF STEEL
T/U TILT-UP
TYP TYPICAL
U.N.O. UNLESS NOTED OTHERWISE
VERT VERTICAL
WWR WELDED WIRE REINFORCEMENT
3380 Trickum Road
Woodstock, GA. 30188 770-517-5507 voice 770-517-5508 fax
Bldg. 500, Ste. 100 www.ieiusa.com
INCORPORATED
INNOVATIVE
ENGINEERING
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
DATE:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
590 MEANS ST NW
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and
Facilities Management
Drawn
REVISIONS:
A
B
C
D
E
F
STRUCTURAL NOTES
S001
BID DOCUMENT
UPGRADE PHARMACY IV MIXING ROOM
USP 797/800
CAPE CORAL, FLORIDA
12-23-2025 SLW DCA
516-22-112
S
P
N.2
REF
33' - 4"
R E
F
0"
EXISTING CMU
WALL
EXISTING
PRECAST
CONCRETE WALL
PANEL
S101
S501
INDICATES LOCATION OF WALL DEMOLOTION
HIDDEN EDGE OF EXISTING FOOTING
EDGE OF SLAB / FOOTING
PLAN
NORTH
TRUE
NORTH
1. REF. DENOTES FOR REFERENCE ONLY, CONTRACTOR
SHALL FIELD VERIFY
2. FIELD VERIFY EXISTING CONDITIONS AND DIMENSIONS
PRIOR TO SUBMISSION OF SHOP DRAWINGS
P
N.2
REF
33' - 4"
R E
F
0"
S501
S501
3'
4'
1"
1. REF. DENOTES FOR REFERENCE ONLY, CONTRACTOR SHALL FIELD
VERIFY
2. FIELD VERIFY EXISTING CONDITIONS AND DIMENSIONS PRIOR TO
SUBMISSION OF SHOP DRAWINGS
DENOTES EXISTING CONCRETE BEAM
DENOTES EXISTING CONCRETE BEAM
P
N.2
REF
33' - 4"
R E
F
0"
S501
S101
HIDDEN EDGE OF EXISTING FOOTING
EDGE OF SLAB / FOOTING
1. REF. DENOTES FOR REFERENCE ONLY, CONTRACTOR
SHALL FIELD VERIFY
2. FIELD VERIFY EXISTING CONDITIONS AND DIMENSIONS
PRIOR TO SUBMISSION OF SHOP DRAWINGS
FIRST FLOOR
0"
SECOND FLOOR
18' - 0"
S501TYP.
5'
4" 5'
4"
3'
1/ 2"
M
K
3 4
REF
36' - 4"
R E
F
S101
S501
COORDINATE WITH MECH.
Level 4 48' - 0"
M
6"9
S501
3380 Trickum Road
Woodstock, GA. 30188 770-517-5507 voice 770-517-5508 fax
Bldg. 500, Ste. 100 www.ieiusa.com
INCORPORATED
INNOVATIVE
ENGINEERING
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
DATE:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
590 MEANS ST NW
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and
Facilities Management
Drawn
REVISIONS:
A
B
C
D
E
F
DEMOLITION AND FRAMING PLANS
S101
BID DOCUMENT
UPGRADE PHARMACY IV MIXING ROOM
USP 797/800
CAPE CORAL, FLORIDA
12-23-2025 SLW DCA
516-22-112
3/16" = 1'-0"S101
1 PARTIAL FIRST FLOOR DEMOLITION PLAN
3/16" = 1'-0"S101
3 PARTIAL 2ND FLOOR FRAMING PLAN
DEMOLITION PLAN LEGENDDEMOLITION PLAN NOTES
2nd FLOOR FRAMING PLAN NOTES 2nd FLOOR FRAMING PLAN LEGEND
Scale: 3/16"=1'-0"
2' 4' 8' 12'1'
Scale: 3/16"=1'-0"
2' 4' 8' 12'1'
3/16" = 1'-0"S101
2 PARTIAL 1ST FLOOR FRAMING PLAN
1ST FLOOR FRAMING PLAN1ST FLOOR FRAMING PLAN NOTES
Scale: 3/16"=1'-0"
2' 4' 8' 12'1'
3/4" = 1'-0"S101
5 DUCT SUPPORT FRAMING ELEVATION
Scale: 3/4"=1'-0"
1' 2' 4' 8'
3/16" = 1'-0"S101
4 ROOF DUCT FRAMING PLAN
Scale: 3/16"=1'-0"
2' 4' 8' 12'1'
3/4" = 1'-0"S101
6 DUCT SUPPORT FRAMING ELEVATION
Scale: 3/4"=1'-0"
1' 2' 4' 8'
P N.2
REF
24' - 10" V
3' - 4" 5' - 4"
DEMO EXISTING CMU
COORDINATE WITH
MECHANICAL PRIOR TO
DEMOLITION
COORDINATE WITH
MECHANICAL PRIOR TO
DEMOLITION
EXISTING CMU
TO REMAIN
EXISTING DOOR
HSS BEAM
SEE, 2/S501
HSS POST, SEE PLAN
3/16
3 SIDES
3/16
3 SIDES
INTERSECTION
L4x4x1/4x0'-7 5/8"
L4x4x1/4x0'-7 5/8"
2" 2"
2" 2"
4"
L4x4x1/4x0'-4" LONG
3/16
3-SIDES
HSS POST,
SEE PLAN
EXIST CONCRETE
PRECAST PANEL
(1) 1/2"Ø HILTI HIT
HY-200 W/ HAS ROD
2 3/4" EMBED
1 1/2" 1 1/2"
6"
1 1/2"
1 1/2"
HSS, SEE
PLAN
1/4
TYP.
1/
2" 5"
1/
2"
E D
G E
O F
C O
N C
R E
TE
1/
2"
PL. 1/2"x1'-0"x8" W/ (4)1/2"Øx2 3/4" EMBED HILTI
KWIK BOLT TZ2 ANCHORS
EXIST. CONCRETE
PRECAST PANEL
P N.2
REF
24' - 10" V
3' - 4" 5' - 4"
R E
F
9'
1/
4"
S501
8'
1/
4" 3'
0"
4' - 1" 3' - 10"
NEW DUCT PENETRATION
INSTALL AFTER STEEL HAS BEEN
INSTALLED. DO NOT OVERCUT
PENETRATION AND PROVIDE
RADIUSED CORNERS
S501
TYP.
S501
S501
S501
HSS8x2x1/4
LSH
HSS8x2x1/4
LSH
HSS8x6x1/4, SEE PLAN
R E
F
1'
6"
REF
5' - 0"
REF
2' - 0"
M A
X
1'
0" 3'
3/ 4"
3'
3/
4" 2'
3/ 4"
2'
3/
8" 2'
3/ 8"
M A
X
1'
0"
EXIST CMU
BEYOND
EXIST CONCRETE
BEAM
EXIST PRECAST
PANEL
3'
0" 8'
1/ 4"
1'
0"
REF
1' - 3"
9 3/4"5"
REF
1' - 1"
3/4" dia THROUGH
BOLT IN SHORT
SLOTTED HOLES
L8x4x1/2 LLV EA
SIDE OF TUBE
(2) 1/2" dia x 2 1/2" EMBED
HILTI KWIK BOLT TZ2
ANCHORS IN EACH ANGLE
3" 2"
6 3/4" 9 1/4"
1 1/2"
HSS8x2x, SEE 2/S501
HSS8x2x, SEE 2/S501
L4x4x, SEE 5/S501
HSS8x6x, SEE PLAN
NOTES:
1. DO NOT DAMAGE EXISTING PANEL
REINFORCING DURING ANCHOR
INSTALLATION. LOCATE EXISTING
REINFORCING THROUGH NON-
DESTRUCTIVE MEANS PRIOR TO
SUBMISSION OF SHOP DRAWINGS
FOR REVIEW.
3/16
3-SIDES
L4x4x1/4x0'-4" LONG
HSS BEAM,
SEE 2/S501
3/16
3-SIDES
L4x4x1/4x0'-4" LONG
(1) 1/2"Ø HILTI HIT
HY-200 W/ HAS ROD
2 3/4" EMBED
EXIST CONCRETE
PRECAST PANEL
REF
8"
OPENING
T Y
P
6"
3/16
CJP TYP
1' - 2"
3"
1'
8"
2"
L3x3x1/4
EXIST PRECAST
PANEL
1' - 10"
S501
3/16
TYP
NOTES:
1. CONNECTIONS OF DUCT TO FRAME SHALL
BE BY THE CONTRACTOR.
2. DO NOT DAMAGE EXISTING PANEL
REINFORCING DURING ANCHOR
INSTALLATION. LOCATE EXISTING
REINFORCING THROUGH NON-DESTRUCTIVE
MEANS PRIOR TO SUBMISSION OF SHOP
DRAWINGS FOR REVIEW.
3. ALL EXPOSED STEEL SHALL BE HOT DIPPED
GALVANIZED.
3/16
TYP. EA END
EXIST PRECAST
PANEL OR NEW
CONCRETE WALL
L3x3x1/4
3/8" DIA. x 2" EMBED KWIK TZ2
ANCHOR AT 12" O.C.
2'
1/
2"
3/16
TYP
3"
1' - 2"
7"
S501
NOTES:
1. CONNECTIONS OF DUCT TO FRAME SHALL
BE BY THE CONTRACTOR.
2. DO NOT DAMAGE EXISTING PANEL
REINFORCING DURING ANCHOR
INSTALLATION. LOCATE EXISTING
REINFORCING THROUGH NON-DESTRUCTIVE
MEANS PRIOR TO SUBMISSION OF SHOP
DRAWINGS FOR REVIEW.
3. ALL EXPOSED STEEL SHALL BE HOT DIPPED
GALVANIZED.
L3x3x1/4
3/16
CJP TYP
3/16
TYP
CONCRETE WALL
2'
5"1'
4" 3/16
TYP. EA END
EXIST PRECAST
PANEL OR NEW
CONCRETE WALL
L3x3x1/4
3/8" DIA. x 2" EMBED KWIK TZ2
ANCHOR AT 12" O.C.
1'
1/
2"
3/16
TYP
3380 Trickum Road
Woodstock, GA. 30188 770-517-5507 voice 770-517-5508 fax
Bldg. 500, Ste. 100 www.ieiusa.com
INCORPORATED
INNOVATIVE
ENGINEERING
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
DATE:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
590 MEANS ST NW
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and
Facilities Management
Drawn
REVISIONS:
A
B
C
D
E
F
STEEL DETAILS
S501
BID DOCUMENT
UPGRADE PHARMACY IV MIXING ROOM
USP 797/800
CAPE CORAL, FLORIDA
12-23-2025 SLW DCA
516-22-112
1/2" = 1'-0"S501
1 DEMO ELEVATION ALONG GRID LINE 2
1 1/2" = 1'-0"S501
3 TYPICAL DETAIL- HSS CONNECTIONS
1 1/2" = 1'-0"S501
7 DETAIL AT POST CONNECTION TO PANEL
3" = 1'-0"S501
4 BASE PLATE AT MAN DOOR FRAME
1/2" = 1'-0"S501
2 FRAMING ELEVATION ALONG GRID LINE 2
3/4" = 1'-0"S501
6 SECTION
1 1/2" = 1'-0"S501
8 SECTION BEAM CONNECTION TO PANEL
3/4" = 1'-0"S501
5 ENLARGED DUCT SUPPORT FRAMING PLAN
1" = 1'-0"S501
10 SECTION
3/4" = 1'-0"S501
9 ENLARGED DUCT SUPPORT FRAMING PLAN
1" = 1'-0"S501
11 SECTION
STAIR 2
STAIR 3
STAIR 4
EW
EW
EW
EW
F H
V
FHV
AED
AED
AED
FACP
A
B
C
E
D
UP
UP
UP
UP
UP
R A
D
IO
L O
G Y
LAB
PHARMACY
SECURITY
URGENT CARE
OFFICE
1A-129
1A-131
EXAM
1A-133
EXAM
1A-132
1A-130
TLT
1A-106
MED. EQ.
1A-108
M.H.
1A-102
CLEAN
LINEN
1A-103
SOIL LINEN
1A-105
OBS.
1A-107
OBS.
1A-109
OBS.
1A-111
OBS.
1A-112
SOCIAL
WORK
SERVICE
1A-104
M.H.
HOLDING
1A-134
TRIAGE
1A-136
TLT
1A-100
TLT
1A-101
EXAM
1A-135
CHECK-IN/OUT
OBS.
1A-116
OBS.
1A-115
OBS. / ISO.
1A-114
MALE
LOCKER /
TOILET
1B-187
FEMALE
LKR / TLT
1B-186
EMS
STORAGE
1B-181
MED. GAS
1B-160
FLAMM.
1B-159
EQ.
STORAGE
1B-158
STORAGE
1B-184
STORAGE
1B-182
EMS CHIEF
1B-180
MAIL /
WORK
ROOM
1B-179
MRI
1B-151
OFFICE
1B-130
TLT
1B-128
SOIL
1B-127
MRI EQ.
1B-126
CT
1B-146
CT CONT.
1B-147
MR CONT.
1B-150
CHIEF
TECH.
1B-141
DATA
1B-118
SIGNAL
1B-117
LOUNGE
1B-116 STAFF TLT
1B-115
OFFICE
1B-112
OFFICE
1B-110
OFFICE
1B-109
TOILET
1B-111
STRESS
1B-120
INJ.
1B-123
MAMMO
1B-131
RAD.
CHECK-IN
1B-137
SECURE
DISP.
1B-171
268,240,276
WAITING
AREA
C1-15
LOCKERS
1B-162
BREAK
ROOM
1B-185
CLEAN
CARTS
1B-188
ELEC.
1B-189
DATA
1B-190
SIGNAL
1B-191
BADGE / ID
1B-199
EVIDENCE
1B-193
ARMORY
1B-194
OFFICE
1B-195 HOLD.
1B-196
OFFICE
1B-197
LOCKERS
1B-198
ISSUE
AREA
1B-154
CHIEF SPD
1B-153
GENERAL
STORAGE
1B-156
NURSES
STATION
C1-28
MEDICATION
1A-110
STORAGE
1A-113
TLT
1A-221
TLT
1A-220
ELEV.
S-1
ELEV.
S-2
CORR.
C1-11
CORR.
C1-30
CORR.
C1-27
CORR.
C1-31
CORR.
C1-31
SECURE
DISP.
STOR.
1B-170
SCRIPT.
REC.
1B-169 PHARMD
1B-168
OFFICE
1B-167
MED. SUP.
1B-163
PHARMACY
1B-212
OFFICE
ASSIST.
1B-178
ASSIST.
1B-177
CHIEF
1B-176
HAC
1B-175
TLT
1B-174
TLT
1B-173
DATA
PROCESS.
1B-172
CHIEF
1B-140
STAFF
PHYSIC.
1B-139
R/F
1B-133
NUC. MED.
1B-121
HOT LAB
1B-122
X-RAY
1B-136
HAC
1B-124
ELEC.
1B-125
VESTIBULE
1B-108
BULK
STOR.
1B-113
BREAK
1B-114
LAB
1B-106
TLT
1B-102
TLT
1B-104
TLT
1B-105
LAB
CHECK-IN
1B-100
LAB WORK
AREA
1B-103
SPECIMEN
COLLECTION
1B-101
TLT
1B-149
DRESSING
1B-148
DRESSING
1B-145
RADIOLOGY
1B-144
ELECT.
1B-142
SOILED
CARTS
1B-183
CORR.
C1-12
CORR.
C1-13
CORR.
C1-17
TECH
WORK
1B-135
CORR.
C1-19
CORR.
C1-20
CORR.
C1-21
CORR.
C1-22
CORR.
C1-23 CORR.
C1-24
CORR.
C1-25
SUPPLY
ADMIN.
1B-155
SECURITY
1B-192
C.E.P.
1B-200
MED. VAC.
& AIR
1B-204
BOILER
ROOM
1B-205
CHILLER
ROOM
1B-201
STAFF
PHYSIC.
1B-138
FIRE PUMP
1B-203
STERILE
STORAGE
1B-157
MICROBIOLOGY
1B-107
VESTIBULE
C1-26
CONTROL
ROOM
1B-206
VESTIBULE
1B-119TLT
1B-129
RAD /
X-RAY
1B-132
UCC
EXAM
EXAM
REF.
KVA.
CHASE
HOLDING
TOOL
ROOM
OPEN
CANOPY
1B-133A
OFFICE
1B-204A
NON FERRIS
WATER MIST
W ALL H O LE
w o/ PIP E
4 "x4"C - SM ALL
18"
H O LE
w / PIPEP 7/ E7
T
O P EN
C ON DU IT 3/ 4"- 4"
K 4- LAR G EK 3- LAR G E
K 2- LAR G EK 1- LAR G E
P 3/ E3 P 5/ E5 P 6/ E6 P 4/ E4 P 2/ E2 P 1/ E1 O 2 O 1N 2 N 1 M 1 M 2
J G F W 5W 4 W 3W 2
D - SM ALL
W 1
150- 250 SQ .
IN .
W ALL
H O LES
H O LE
w / PIPE
H O LE
w / PIPE
H O LE
w / PIPE
H O LE
w / PIPE
H O LE
w / PIPE
H O LE
w / PIPE
D U CT
P ER IMETER
D U CT
P ER IMETER
D U CT
P ER IMETER
D U CT
P ER IMETER
D U CT
P ER IMETER
D U CT
P ER IMETER
1/ 2"- 4" 12" 8"6"
0- 3/ 4" 1"- 2"
25"- 50" 1"
G AP25"- 50" 4"
G AP50"- 100" 1"
G AP
50"- 100" 4"
G AP100"- 200" 1"
G AP
100"- 200" 4"
G AP
FLOO R
P EN ETR ATIO N S
W ALL
H O LES
W ALL
H O LES
W ALL
H O LES
FLU TED
JO IN T
C AB LE
TR AY
W ALL H O LE
w o/ PIP E
EXTEN D
W ALLS
EXTEN D
W ALLS
EXTEN D
W ALLS
EXTEN D
W ALLS
EXTEN D
W ALLS
50- 75 SQ .
IN .75- 100 SQ .
IN .
100- 150 SQ .
IN .
P ER
FO O T
O PENING
SIZE
6 "x6"
CO DE
B - SM ALL
A- SM ALL* W ALL H O LE
w o/ PIP E
W ALL H O LE
w o/ PIP E
T YPE CO NDITIO N
2 "x2" 0"- 1"
1HR
C O NSTR U CTIO N2HR
C O NSTR U CTIO N
SM OK E
W ALLD ISSIM ILAR
M ATER IALS
AP PR OX
N UM BER
H O LE- M ULT.
P IPE/C ON D.
P 8/ E8
JBC O P EN JUN CTIO N BO X
C O VER
I I- B EAM
V C H ANN EL
D R YWALL
JO IN T
H W ALL/ SLAB
JO IN T
N .R .
SEALAN T
CO DE * T YPE C O NDITIO N
CO DE * T YPE C O NDITIO N
CO DE * T YPE C O NDITIO N CO DE * T YPE C O NDITIO NCO DE * T YPE C O NDITIO N CO DE* T YPE C O NDITIO N
P EN ET RAT IO N D ES CR IPT IO NS
S YM BO L S L IST
P EN ET RA TI O N DE SC RI PT IO NS
S YM BO L S L IST
P EN ET RA TI O N DE SC RI PT IO NS
S YM BO L S L IST
P EN ET RA TI O N DE SC RI PT IO NSP EN ET RAT IO N D ES CR IPT IO NS
S YM BO L S L IST
P EN ET RAT IO N D ES CR IPT IO NS
ORIGINAL
SCAL ED
BY 0 .9
ORIGINAL
SCAL ED
BY 0 .9
2 HO UR FIRE B ARR IER
2 HO UR FIRE/ SM OK E ZON E B AR R IER
SM OK E ZON E B AR R IER1 HO UR FIRE BARR IER (HAZAR DO U S RO OM EN CLO SU RE)
N O N- RATED SM OK E ZON E P AR TITIO N
SM O KE RESISTIVE H AZAR DO U S R OO M EN CLO SU R E
H EALTH C AR E O CC UP AN CY CO RR ID OR S
SM O KE RESISTIVE H AZAR DO U S R OO M EN CLO SU R E
1 HO UR FIRE B AR R IER HAZAR DO US RO OM EN CLOSUR E
SP RIN KLER AN D FIR E ALARM ZO NE BO UN D AR Y
N O N- RATED SM OK E B AR RIER (C O MM UN ICATIN G SP ACE)
2 HO UR FIRE B ARR IER
2 HO UR FIRE/ SM OK E ZON E B AR R IER
SM OK E ZON E B AR R IER
1 HO UR FIRE BARR IER (HAZAR DO U S RO OM EN CLO SU RE)
N O N- RATED SM OK E ZON E P AR TITIO N
SM O KE RESISTIVE H AZAR DO U S R OO M EN CLO SU R E
H EALTH C AR E O CC UP AN CY CO RR ID OR S
SM O KE RESISTIVE H AZAR DO U S R OO M EN CLO SU R E
1 HO UR FIRE B AR R IER HAZAR DO US RO OM EN CLOSUR E
SP RIN KLER AN D FIR E ALARM ZO NE BO UN D AR Y
N O N- RATED SM OK E B AR RIER (C O MM UN ICATIN G SP ACE)
S YM B O LS LIST
S YM B O LS LIST P EN ET RAT IO N D ES CR IPT IO NS
P EN ETR ATIO N
N O TATIO N
N U MB ER P RIO R TO P EN ETR ATIO N C OD E (IN P AR ENTH ESES) IN D IC ATES
Q U AN TITIES/ LIN EAR FEET (LF) AT TH AT LO C ATIO N .
W ALL H OLE wo/ PIP E 4"x4" w /B AC KIN GC - SM ALL
18"P 7/ E7
* NU M BER PR IOR TO PEN ETR ATIO N C OD E IN D IC ATES Q U ANTITY AT TH AT LO CATIO N .
T O P EN C ON DU IT 3/ 4"- 4"
K 4- LAR G E
K 3- LAR G E
K 2- LAR G E
K 1- LAR G E
P 3/ E3
P 5/ E5 P 6/ E6
P 4/ E4
P 2/ E2 P 1/ E1 O 2 O 1 N 2 N 1 M 1M 2
J G
FW 5
W 4 W 3 W 2
D - SM ALLW 1
150- 250 SQ . IN .W ALL HO LES
H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E
D U CT PER IM ETER
D U CT PER IM ETER
D U CT PER IM ETER
D U CT PER IM ETER
D U CT PER IM ETERD U CT PER IM ETER
12" 8" 6"
50"- 100" 1" G AP
50"- 100" 4" G AP
100"- 200" 1" G AP
100"- 200" 4" G AP
FLO O R P EN ETR ATIO N S
W ALL HO LES
W ALL HO LES
W ALL HO LES
FLU TED JO IN T
C AB LE TR AY
W ALL H OLE wo/ PIP E
EXTEN D W ALLS
EXTEN D W ALLS
EXTEN D W ALLS
EXTEN D W ALLS
EXTEN D W ALLS
50- 75 SQ . IN .
75- 100 SQ . IN .
100- 150 SQ . IN .
P ER FOO T
1" x 4"
6"x6" w /B AC KIN G
B - SM ALL
A- SM ALL
W ALL H OLE wo/ PIP E W ALL H OLE wo/ PIP E
2"x2" w /B AC KIN G 0"- 1"
N O TATIO N
1H R CO NSTRU CTIO N
2H R CO NSTRU CTIO N
SM O KE WALL
D ISSIM ILAR M ATER IALS
P 8/ E8
JBC O P EN JUN C TION B O X CO VER
I
V C H ANN EL
D R YW ALL JO IN T
H O R IZO N TAL EXIT P ASSAG EW AY
EXIT
SU ITE DESIG N ATIO N S
SM O K E RESISTIVE H AZAR D O U S AR EA30 M IN SMO K E B AR R IER
1 HO U R FIR E B AR R IER
2 HO U R FIR E B AR R IER
AR EA OP EN TO C O RR IDO R - W ITH SM OK E D ETEC TIO N
AR EA O P EN TO C OR R ID OR - NO SM OK E D ETEC TIO N REQ UIRED
EXIT P ASSAG EW AY
H E E X
EP
LIN EN C HU TELC
TR ASH C HU TETC
H W ALL/ SLAB JO IN T N .R . SEALAN T
25"- 50" 1" G AP25"- 50" 4" G AP
2 1/ 2"- 4" 1"- 2" 0- 3/ 4""
N .R. N O N RATED
C .J. C ON TRO L JO IN TE.J. EXP AN SIO N JO IN T
W / WITH
W O/ W ITHO UTC MPD C OMPO UND
I- B EAM , C ON C . B EAM N .R . SEALAN T
N .R . SEALAN T
VAR IESH O LE- M ULTIP LE P IPE/ CO N DU IT
H O LE w/ P IP E
W ALL H O LE w o/P IP E 4"x4" w /B AC KIN GC - SM ALL
18"P 7/ E7
* N UM B ER P R IO R TO PEN ETR ATIO N C O D E IN DIC ATES Q U ANTITY AT TH AT LOC ATIO N .
T O P EN C ON DU IT 3/ 4"- 4"
K 4- LAR G E
K 3- LAR G E
K 2- LAR G E
K 1- LAR G E
P 3/ E3
P 5/ E5 P 6/ E6
P 4/ E4
P 2/ E2 P 1/ E1
O 2 O 1N 2 N 1
M 1 M 2
J G
F W 5 W 4 W 3 W 2
D - SM ALL
W 1
150- 250 SQ . IN .W ALL H O LES
H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E
D U C T P ERIM ETER
D U C T P ERIM ETERD U C T P ERIM ETER
D U C T P ERIM ETER
D U C T P ERIM ETER
D U C T P ERIM ETER
12" 8" 6"
50"- 100" 1" G AP
50"- 100" 4" G AP100"- 200" 1" G AP
100"- 200" 4" G AP
FLO O R P EN ETR ATIO N S
W ALL H O LES
W ALL H O LES
W ALL H O LES
FLU TED JO IN T
C AB LE TR AY
W ALL H O LE w o/P IP E
EXTEN D W ALLS
EXTEN D W ALLS
EXTEN D W ALLS
EXTEN D W ALLS
EXTEN D W ALLS
50- 75 SQ . IN .
75- 100 SQ . IN .
100- 150 SQ . IN .
P ER FOO T
1" x 4"
6"x6" w /B AC KIN G
B - SM ALL
A- SM ALL
W ALL H O LE w o/P IP E W ALL H O LE w o/P IP E
2"x2" w /B AC KIN G 0"- 1"
N O TATIO N
1H R C ON STR UC TIO N
2H R C ON STR UC TIO N
SM O K E W ALL
D ISSIM ILAR M ATER IALS
P 8/ E8
JB C O P EN JU NC TIO N B OX C O VER
I
V C H ANN EL
D R YW ALL JO IN T
H O R IZO N TAL EXIT P ASSAG EW AY
E XIT
SU ITE D ESIG N ATIO N S
SM O K E R ESISTIVE H AZAR D OU S AR EA
30 MIN SM O KE BAR RIER
1 H OU R FIRE BAR RIER
2 H OU R FIRE BAR RIER
AR EA OP EN TO C OR R ID O R - W ITH SM O KE DETEC TIO N
AR EA OP EN TO CO R RIDO R - NO SM OK E D ETECTION R EQU IRED
EXIT P ASSAG EW AY
H E E X
EP
LIN EN C HU TELC
TR ASH C HU TETC
H W ALL/ SLAB JO IN T N .R . SEALAN T
25"- 50" 1" G AP
25"- 50" 4" G AP
2 1/ 2"- 4" 1"- 2" 0- 3/ 4""
N .R. N ON R ATED
C .J. C O N TR O L JOIN TE.J. EXP AN SIO N JO IN T
W / WITH
W O / WITH OU TC MP D COM POU ND
I- B EAM , C ON C . B EAM
N .R . SEALAN TN .R . SEALAN T
VAR IESH O LE- M U LTIP LE PIP E/C O N DU IT
H O LE w/ P IP E
W ALL H O LE w o/P IP E 4"x4" w /B AC KIN GC - SM ALL D - SM ALL W ALL H O LE w o/P IP E 6"x6" w /B AC KIN G
B - SM ALL
A- SM ALL
W ALL H O LE w o/P IP E W ALL H O LE w o/P IP E
2"x2" w /B AC KIN G 0"- 1"
H O R IZO N TAL EXIT P ASSAG EW AY
E XIT
SU ITE D ESIG N ATIO N S
SM O K E R ESISTIVE H AZAR D OU S AR EA
30 MIN SM O KE BAR RIER
1 H OU R FIRE BAR RIER
2 H OU R FIRE BAR RIER
AR EA OP EN TO C OR R ID O R - W ITH SM O KE DETEC TIO N
AR EA OP EN TO CO R RIDO R - NO SM OK E D ETECTION R EQU IRED
EXIT P ASSAG EW AY
H E
E X
EP
LIN EN C HU TE
LC
TR ASH C HU TETC
18"P 7/ E7
K 4- LAR G E
K 3- LAR G E
K 2- LAR G EK 1- LAR G E
P 3/ E3
P 5/ E5 P 6/ E6
P 4/ E4
P 2/ E2P 1/ E1
O 2 O 1 N 2 N 1
M 1 M 2
J G
F W 5 W 4 W 3 W 2 W 1
150- 250 SQ . IN .W ALL H O LES
H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP E H O LE w/ P IP EH O LE w/ P IP E
D U C T P ERIM ETER
D U C T P ERIM ETER
D U C T P ERIM ETER
D U C T P ERIM ETER
D U C T P ERIM ETER
D U C T P ERIM ETER
12" 8" 6"
50"- 100" 1" G AP
50"- 100" 4" G AP
100"- 200" 1" G AP
100"- 200" 4" G AP
FLO O R P EN ETR…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .