This document is a set of 100% Bid Documents (architectural drawings and specifications) for the Building 111 Facade Repair project at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The project involves façade repair work on Drops (sections) 1, 3, 21, 23, 25, and 26 located on Floors 9 and 11 of the building. The documents include location maps, vicinity maps, and elevation drawings (North, South, and West) depicting the project scope and repair areas.
Critical to the project scope is the identification and abatement of asbestos-containing materials (ACM) found during surveys performed in December 2023 and June-July 2025 by ARC Environmental. Asbestos-containing caulk has been confirmed along vertical joints between pre-cast window panels and brick masonry, and asbestos-containing flashing tar has been identified on metal copper flashing. The contractor is responsible for coordinating with other trades, ensuring worker safety, properly handling and disposing of ACM, and performing daily recaulking/sealing of abated areas to maintain building envelope integrity. All abated areas must receive passing visual clearance inspection approval from an industrial hygienist before recaulking or concealment. The contractor must also assess and sample any newly discovered suspect ACM prior to disturbance. Work specifications are detailed in Section 02 82 11, and references are provided to the Limited Asbestos-Containing Materials Survey (June 28, 2024) and Supplemental Asbestos-Containing Materials Survey (August 28, 2025) reports.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S02 - 695-22-121_100pc Bid Final_Specification.pdf | ||
| S02 - 695-22-121_100pc Bid Final_Drawings Part1.pdf | ||
| S02 - 36C25226B0039 PRE-SOL 695-22-121 9.23.2026.pdf | ||
| 36C25226B0039.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseDESIGNER OF RECORD STAMPCONSULTANT
7 8 9 10321 4 5 6
NORTH
VICINITY MAP
PROJECT TEAM DRAWING SHEET INDEX
600 E. Michigan Avenue, Suite B Kalamazoo, MI 49007 P: 269.927.0144 www.bodwegroup.com
1635 Prince Street Alexandria, VA 22314 P: 202.617.8485 www.alliance.us.com
NORTH
LOCATION MAP
VA MILWAUKEE CAMPUS
Au to de sk
D oc s:
//2
VA
M ilw au ke e Bl dg
F ac ad e W or k/
V
A M ilw au ke e
Bl dg
F ac ad e
W or k-
AR
C H
_R
.rv t
3/
/2
:2 0:
P
M
CLEMENT J. ZABLOCKI VA MEDICAL CENTER
ALLIANCE | SEVEN GENERATIONS A+E JV
600 E. MICHIGAN AVENUE, Ste B
KALAMAZOO, MI 49007
PHONE: 269.927.0144
BODWEGROUP.COM
5000 W NATIONAL AVE
MILWAUKEE, WI, 53295
WISS, JANNEY, ELSTNER ASSOCIATES, INC.
330 PFINGSTEN ROAD
NORTHBROOK, IL 60062
847.272.7400
WJE.COM
HAZARDOUS MATERIAL SPECIALIST
ARC ENVIRONMENTAL
FAÇADE REPAIR CONSULTANT
1635 PRINCE STREET
ALEXANDRIA, VA 22314
PHONE: 202.617.8485
ALLIANCE.US.COM
CLEMENT J. ZABLOCKI VA MEDICAL CENTER
BUILDING 111 FACADE REPAIR
MILWAUKEE, WISCONSIN
MILWAUKEE, WISCONSIN
ARCHITECTURE/COST ESTIMATING:
TITLE SHEET BUILDING 111 FACADE REPAIR
5000 W NATIONAL AVE, MILWAUKEE,
WI, 53295
695-22-121
PROJECT DIRECTOR
MARCH 16, 2026 JD NL
100% BID DOCUMENTS
G001
1311 HAUBERT STREET
BALTIMORE, MD 21230
443.864.7464
ARCENVIRONMENTAL.COM
SHEET DESCRIPTION
GENERAL
G001 TITLE SHEET
G002 GENERAL INFO & SYMBOL LEGEND
G003 ROOF PLANS AND ISOMETRICS
G004 ROOF AND ELEVATOR ACCESS FLOORS 1 AND 3
G005 ROOF PLAN ACCESS INFORMATION FLOORS 9 AND 11
ARCHITECTURAL
A200 EXTERIOR ELEVATIONS - 3 AND 1 (NORTH)
A201 EXTERIOR ELEVATIONS - 21 (SOUTH)
A202 EXTERIOR ELEVATIONS - 23 (SOUTH)
A203 EXTERIOR ELEVATIONS - 25 (SOUTH)
A204 EXTERIOR ELEVATIONS - 26 (WEST)
A300 ENLARGED ELEVATIONS
A301 WALL SECTIONS AND DETAILS
A302 REPAIR DETAILS
A303 REPAIR DETAILS
HAZARDOUS MATERIAL
HA200 HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 3 AND 1 (NORTH)
HA201 HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 21 (SOUTH)
HA202 HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 23 (SOUTH)
HA203 HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 25 (SOUTH)
HA204 HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 26 (WEST)
PROJECT LOCATION
100% BID DOCUMENTS
BUILDING 111
Revisions: Date:
VHAMIWGeorgK Rectangle
GENERAL HAZARDOUS
MATERIAL NOTES APPLICABLE
TO THE PROJECT AREA
1. AN ASBESTOS-CONTAINING MATERIALS (ACMS) SURVEY
WAS PERFORMED IN DECEMBER 2023 BY ARC
ENVIRONMENTAL AND IDENTIFIED MATERIALS ON THE
EXTERIOR FAÇADE. A SUPPLEMENTAL ASBESTOS SURVEY WAS
PERFORMED IN JUNE-JULY 2025 TO FURTHER DELINEATE
SUSPECT ACMS OBSERVED AT ACCESSIBLE PORTIONS OF
DROPS 1, 3, 21, 23, 25, & 26 WHICH ARE INCLUDED IN THE
PROJECT SCOPE. ASBESTOS-CONTAINING CAULK IS
CONFIRMED TO BE PRESENT ALONG THE VERTICAL JOINTS
BETWEEN PRE-CAST WINDOW PANELS AND BRICK MASONRY
AND ASBESTOS-CONTAINING FLASHING TAR HAS BEEN
IDENTIFIED ON METAL COPPER FLASHING. BOTH OF THESE
REQUIRE ABATEMENT TO FACILITATE THE FAÇADE REPAIRS. THE
CONTRACTOR SHALL REFER TO THE ASSOCIATED 'LIMITED
ASBESTOS-CONTAINING MATERIALS SURVEY - REPAIR
BUILDING 111 CONCRETE FAÇADE STUDY'' REPORT DATED
JUNE 28, 2024, AND 'SUPPLEMENTAL ASBESTOS-CONTAINING
MATERIALS SURVEY - BUILDING 111 CONCRETE FAÇADE
PROJECT' DATED AUGUST 28, 2025, FOR DETAILS RELATED TO
THE ASSESSMENTS AND ASSOCIATED ANALYTICAL DATA. THE
PROVIDED DRAWINGS AND SPECIFICATIONS DETAILING THE
SCOPE OF WORK FOR REMEDIATION AND ABATEMENT ARE
BASED ON THE COMPLETED SURVEYS AND THE PROJECT
SCOPE OF WORK.
2. ASBESTOS-CONTAINING MATERIALS HAVE BEEN IDENTIFIED
WITHIN THE PROJECT AREA. CONTRACTOR SHALL
COORDINATE WITH OTHER TRADES AS REQUIRED TO ENSURE
WORKER SAFETY, PHASING, AND PROPER HANDING,
REMOVAL, AND DISPOSAL OF ACMS. REFER TO
SPECIFICATION SECTION 02 82 11. IT IS ANTICIPATED THAT
ABATEMENT OF EXTERIOR CAULK WILL BE COMPLETED IN A
MANNER THAT MAINTAINS THE MATERIAL IN NON-FRIABLE
CONDITION. BRICK WORK IMPACTED BY ACM CAULK IS
SCOPED FOR REPLACEMENT; THEREFORE, IF MINIMAL
DAMAGE TO THE BRICK IS PERMITTED IF REQUIRED TO
PROPERLY ABATE THE IDENTIFIED ASBESTOS-CONTAINING
CAULK.
3. THE CONTRACTOR IS RESPONSIBLE FOR DAILY RE-
CAULKING/SEALING AREAS WHERE ASBESTOS-CONTAINING
CAULK IS ABATED TO ENSURE THAT THE INTEGRITY OF THE
BUILDING ENVELOPE IS MAINTAINED DURING CONSTRUCTION
ACTIVITIES. THE APPLIED CAULK/SEALANT SHALL BE APPROVED
THROUGH THE PRE-CONSTRUCTION SUBMITTAL PROCESS
PRIOR TO USE. ABATED AREAS SHALL NOT BE RE-
CAULKED/SEALED OR OTHERWISE CONCEALED UNTIL A
PASSING VISUAL CLEARANCE INSPECTION IS OBTAINED FOR
EACH AFFECTED WORK AREA AND APPROVED BY THE
INDUSTRIAL HYGIENIST.
4. IF IMPACTED, THE CONTRACTOR IS RESPONSIBLE FOR
ASSESSING AND SAMPLING ADDITIONAL SUSPECT ASBESTOS-
CONTAINING MATERIALS WITHIN THE PROJECT AREA PRIOR
TO DISTURBANCE OF THE MATERIAL(S) IF NEWLY DISCOVERED,
SUSPECT ACMS ARE IDENTIFIED DURING THE COURSE OF
CONSTRUCTION.
ASBESTOS LOCATION LEGEND
ASBESTOS-CONTAINING MASONRY CAULK
ASBESTOS-CONTAINING FLASHING TAR
Project Number:
Building Number:
Drawing Number:
Project Title:
Location:
Issue Date: Checked: Drawn:
Drawing Title:
Approved: Project Director
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase:DESIGNER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Sprinkler:
600 E. Michigan Avenue, Suite B Kalamazoo, MI 49007 P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310 Alexandria, VA 22314 P: 202.617.8485 www.alliance.us.com
HAZARDOUS MATERIALS LOCATION PLAN
ELEVATIONS 3 AND 1 (NORTH)
BUILDING 111 FACADE REPAIR
5000 W NATIONAL AVE, MILWAUKEE, WI, 53295
695-22-121
MARCH 16, 2026 SK DL
100% BID DOCUMENTS
HA200
KEY PLAN
N
Revisions: Date:
(975.67)
LEVEL 01
ELEV. 83'-8"
LEVEL 02
ELEV. 97'-5 3/8"
LEVEL 03
ELEV. 111'-2 3/4"
LEVEL 04
ELEV. 122'-9 3/8"
LEVEL 05
ELEV. 134'-4"
LEVEL 06
ELEV. 145'-10 5/8"
LEVEL 07
ELEV. 157'-5 1/4"
LEVEL 08
ELEV. 168'-11 7/8"
LEVEL 09
ELEV. 180'-6 1/2"
LEVEL 10
ELEV. 192'-1 1/8"
P.H. FL. & TOP OF ROOF SLAB
ELEV. 203'-7 3/4"
AA CC FF GG HH JJ KK NNLL MM
3A3 3B3
3B4
3B5
3B6
3B7
3B8
3B9
3B10
3A4
3A5
3A6
3A7
3A8
3A9
3A10
1D3
1D4
1D5
1D6
1D7
1D8
1D9
1D10
1C3
1C4
1C5
1C6
1C7
1C8
1C9
1C10
1B3
1B4
1B5
1B6
1B7
1B8
1B9
1B10
1A3
1A4
1A5
1A6
1A7
1A8
1A9
1A10
ELEVATION 3 (NORTH) ELEVATION 1 (NORTH)
LOWER BUILDING ROOF
ELEV. 112'-0 3/4"
EJ EJ EJEJEJ
GLASS STRUCTURE
N O
T
IN
S C
O
PE
NOT IN SCOPE.
PROTECT DURING THE WORK.
ASBESTOS
CONTAINING
MASONRY
CAULK
LINE OF SOLARIUM
23 2122
GLASS STRUCTURE
NOT IN SCOPE
NOT IN SCOPE.
PROTECT DURING THE WORK.
ASBESTOS
CONTAINING
MASONRY
CAULK
SCALE: 1/8" = 1'-0"2 ELEVATIONS - 3 AND 1 (NORTH)
SCALE: 1/8" = 1'-0"1 ELEVATION - 2 (WEST)
ASBESTOS LOCATION LEGEND
ASBESTOS-CONTAINING MASONRY CAULK
ASBESTOS-CONTAINING FLASHING TAR
GENERAL HAZARDOUS
MATERIAL NOTES APPLICABLE
TO THE PROJECT AREA
1. AN ASBESTOS-CONTAINING MATERIALS (ACMS) SURVEY
WAS PERFORMED IN DECEMBER 2023 BY ARC
ENVIRONMENTAL AND IDENTIFIED MATERIALS ON THE
EXTERIOR FAÇADE. A SUPPLEMENTAL ASBESTOS SURVEY WAS
PERFORMED IN JUNE-JULY 2025 TO FURTHER DELINEATE
SUSPECT ACMS OBSERVED AT ACCESSIBLE PORTIONS OF
DROPS 1, 3, 21, 23, 25, & 26 WHICH ARE INCLUDED IN THE
PROJECT SCOPE. ASBESTOS-CONTAINING CAULK IS
CONFIRMED TO BE PRESENT ALONG THE VERTICAL JOINTS
BETWEEN PRE-CAST WINDOW PANELS AND BRICK MASONRY
AND ASBESTOS-CONTAINING FLASHING TAR HAS BEEN
IDENTIFIED ON METAL COPPER FLASHING. BOTH OF THESE
REQUIRE ABATEMENT TO FACILITATE THE FAÇADE REPAIRS. THE
CONTRACTOR SHALL REFER TO THE ASSOCIATED 'LIMITED
ASBESTOS-CONTAINING MATERIALS SURVEY - REPAIR
BUILDING 111 CONCRETE FAÇADE STUDY'' REPORT DATED
JUNE 28, 2024, AND 'SUPPLEMENTAL ASBESTOS-CONTAINING
MATERIALS SURVEY - BUILDING 111 CONCRETE FAÇADE
PROJECT' DATED AUGUST 28, 2025, FOR DETAILS RELATED TO
THE ASSESSMENTS AND ASSOCIATED ANALYTICAL DATA. THE
PROVIDED DRAWINGS AND SPECIFICATIONS DETAILING THE
SCOPE OF WORK FOR REMEDIATION AND ABATEMENT ARE
BASED ON THE COMPLETED SURVEYS AND THE PROJECT
SCOPE OF WORK.
2. ASBESTOS-CONTAINING MATERIALS HAVE BEEN IDENTIFIED
WITHIN THE PROJECT AREA. CONTRACTOR SHALL
COORDINATE WITH OTHER TRADES AS REQUIRED TO ENSURE
WORKER SAFETY, PHASING, AND PROPER HANDING,
REMOVAL, AND DISPOSAL OF ACMS. REFER TO
SPECIFICATION SECTION 02 82 11. IT IS ANTICIPATED THAT
ABATEMENT OF EXTERIOR CAULK WILL BE COMPLETED IN A
MANNER THAT MAINTAINS THE MATERIAL IN NON-FRIABLE
CONDITION. BRICK WORK IMPACTED BY ACM CAULK IS
SCOPED FOR REPLACEMENT; THEREFORE, IF MINIMAL
DAMAGE TO THE BRICK IS PERMITTED IF REQUIRED TO
PROPERLY ABATE THE IDENTIFIED ASBESTOS-CONTAINING
CAULK.
3. THE CONTRACTOR IS RESPONSIBLE FOR DAILY RE-
CAULKING/SEALING AREAS WHERE ASBESTOS-CONTAINING
CAULK IS ABATED TO ENSURE THAT THE INTEGRITY OF THE
BUILDING ENVELOPE IS MAINTAINED DURING CONSTRUCTION
ACTIVITIES. THE APPLIED CAULK/SEALANT SHALL BE APPROVED
THROUGH THE PRE-CONSTRUCTION SUBMITTAL PROCESS
PRIOR TO USE. ABATED AREAS SHALL NOT BE RE-
CAULKED/SEALED OR OTHERWISE CONCEALED UNTIL A
PASSING VISUAL CLEARANCE INSPECTION IS OBTAINED FOR
EACH AFFECTED WORK AREA AND APPROVED BY THE
INDUSTRIAL HYGIENIST.
4. IF IMPACTED, THE CONTRACTOR IS RESPONSIBLE FOR
ASSESSING AND SAMPLING ADDITIONAL SUSPECT ASBESTOS-
CONTAINING MATERIALS WITHIN THE PROJECT AREA PRIOR
TO DISTURBANCE OF THE MATERIAL(S) IF NEWLY DISCOVERED,
SUSPECT ACMS ARE IDENTIFIED DURING THE COURSE OF
CONSTRUCTION.
Project Number:
Building Number:
Drawing Number:
Project Title:
Location:
Issue Date: Checked: Drawn:
Drawing Title:
Approved: Project Director
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase:DESIGNER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Sprinkler:
600 E. Michigan Avenue, Suite B Kalamazoo, MI 49007 P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310 Alexandria, VA 22314 P: 202.617.8485 www.alliance.us.com
HAZARDOUS MATERIALS LOCATION PLAN
ELEVATIONS 21 (SOUTH)
BUILDING 111 FACADE REPAIR
5000 W NATIONAL AVE, MILWAUKEE, WI, 53295
695-22-121
MARCH 16, 2026 SK DL
100% BID DOCUMENTS
HA201
KEY PLAN
N 21
Revisions: Date:
(975.67)
LEVEL 01
ELEV. 83'-8"
LEVEL 02
ELEV. 97'-5 3/8"
A
LEVEL 03
ELEV. 111'-2 3/4"
LEVEL 04
ELEV. 122'-9 3/8"
LEVEL 05
ELEV. 134'-4"
LEVEL 06
ELEV. 145'-10 5/8"
LEVEL 07
ELEV. 157'-5 1/4"
LEVEL 08
ELEV. 168'-11 7/8"
LEVEL 09
ELEV. 180'-6 1/2"
LEVEL 10
ELEV. 192'-1 1/8"
P.H. FL. & TOP OF ROOF SLAB
ELEV. 203'-7 3/4"
BCEHK DJ
A
A
EJEJ EJ EJ
21C1
21A2 21B2
21A3 21B3
21A4 21B4
21A5 21B5
21A6 21B6
21A7 21B7
21A8 21B8
21A9 21B9
21A10 21B10
21D1
ASBESTOS
CONTAINING
MASONRY
CAULK
ELEVATION 21 ELEVATION 19
NOT IN SCOPE
EMERGENCY AMBULANCE ENTRY GARAGE AND SHED
SCALE: 1/8" = 1'-0"1 ELEVATION - 21 (SOUTH)
TO THE PROJECT AREA
1. AN ASBESTOS-CONTAINING MATERIALS (ACMS) SURVEY
WAS PERFORMED IN DECEMBER 2023 BY ARC
ENVIRONMENTAL AND IDENTIFIED MATERIALS ON THE
EXTERIOR FAÇADE. A SUPPLEMENTAL ASBESTOS SURVEY WAS
PERFORMED IN JUNE-JULY 2025 TO FURTHER DELINEATE
SUSPECT ACMS OBSERVED AT ACCESSIBLE PORTIONS OF
DROPS 1, 3, 21, 23, 25, & 26 WHICH ARE INCLUDED IN THE
PROJECT SCOPE. ASBESTOS-CONTAINING CAULK IS
CONFIRMED TO BE PRESENT ALONG THE VERTICAL JOINTS
BETWEEN PRE-CAST WINDOW PANELS AND BRICK MASONRY
AND ASBESTOS-CONTAINING FLASHING TAR HAS BEEN
IDENTIFIED ON METAL COPPER FLASHING. BOTH OF THESE
REQUIRE ABATEMENT TO FACILITATE THE FAÇADE REPAIRS. THE
CONTRACTOR SHALL REFER TO THE ASSOCIATED 'LIMITED
ASBESTOS-CONTAINING MATERIALS SURVEY - REPAIR
BUILDING 111 CONCRETE FAÇADE STUDY'' REPORT DATED
JUNE 28, 2024, AND 'SUPPLEMENTAL ASBESTOS-CONTAINING
MATERIALS SURVEY - BUILDING 111 CONCRETE FAÇADE
PROJECT' DATED AUGUST 28, 2025, FOR DETAILS RELATED TO
THE ASSESSMENTS AND ASSOCIATED ANALYTICAL DATA. THE
PROVIDED DRAWINGS AND SPECIFICATIONS DETAILING THE
SCOPE OF WORK FOR REMEDIATION AND ABATEMENT ARE
BASED ON THE COMPLETED SURVEYS AND THE PROJECT
SCOPE OF WORK.
2. ASBESTOS-CONTAINING MATERIALS HAVE BEEN IDENTIFIED
WITHIN THE PROJECT AREA. CONTRACTOR SHALL
COORDINATE WITH OTHER TRADES AS REQUIRED TO ENSURE
WORKER SAFETY, PHASING, AND PROPER HANDING,
REMOVAL, AND DISPOSAL OF ACMS. REFER TO
SPECIFICATION SECTION 02 82 11. IT IS ANTICIPATED THAT
ABATEMENT OF EXTERIOR CAULK WILL BE COMPLETED IN A
MANNER THAT MAINTAINS THE MATERIAL IN NON-FRIABLE
CONDITION. BRICK WORK IMPACTED BY ACM CAULK IS
SCOPED FOR REPLACEMENT; THEREFORE, IF MINIMAL
DAMAGE TO THE BRICK IS PERMITTED IF REQUIRED TO
PROPERLY ABATE THE IDENTIFIED ASBESTOS-CONTAINING
CAULK.
3. THE CONTRACTOR IS RESPONSIBLE FOR DAILY RE-
CAULKING/SEALING AREAS WHERE ASBESTOS-CONTAINING
CAULK IS ABATED TO ENSURE THAT THE INTEGRITY OF THE
BUILDING ENVELOPE IS MAINTAINED DURING CONSTRUCTION
ACTIVITIES. THE APPLIED CAULK/SEALANT SHALL BE APPROVED
THROUGH THE PRE-CONSTRUCTION SUBMITTAL PROCESS
PRIOR TO USE. ABATED AREAS SHALL NOT BE RE-
CAULKED/SEALED OR OTHERWISE CONCEALED UNTIL A
PASSING VISUAL CLEARANCE INSPECTION IS OBTAINED FOR
EACH AFFECTED WORK AREA AND APPROVED BY THE
INDUSTRIAL HYGIENIST.
4. IF IMPACTED, THE CONTRACTOR IS RESPONSIBLE FOR
ASSESSING AND SAMPLING ADDITIONAL SUSPECT ASBESTOS-
CONTAINING MATERIALS WITHIN THE PROJECT AREA PRIOR
TO DISTURBANCE OF THE MATERIAL(S) IF NEWLY DISCOVERED,
SUSPECT ACMS ARE IDENTIFIED DURING THE COURSE OF
CONSTRUCTION.
ASBESTOS LOCATION LEGEND
ASBESTOS-CONTAINING MASONRY CAULK
ASBESTOS-CONTAINING FLASHING TAR
Project Number:
Building Number:
Drawing Number:
Project Title:
Location:
Issue Date: Checked: Drawn:
Drawing Title:
Approved: Project Director
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase:DESIGNER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Sprinkler:
600 E. Michigan Avenue, Suite B Kalamazoo, MI 49007 P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310 Alexandria, VA 22314 P: 202.617.8485 www.alliance.us.com
HAZARDOUS MATERIALS LOCATION PLAN
ELEVATIONS 23 (SOUTH)
BUILDING 111 FACADE REPAIR
5000 W NATIONAL AVE, MILWAUKEE, WI, 53295
695-22-121
MARCH 16, 2026 SK DL
100% BID DOCUMENTS
HA202
KEY PLAN
N
Revisions: Date:
(975.67)
LEVEL 01
ELEV. 83'-8"
LEVEL 02
ELEV. 97'-5 3/8"
LEVEL 03
ELEV. 111'-2 3/4"
LEVEL 04
ELEV. 122'-9 3/8"
LEVEL 05
ELEV. 134'-4"
LEVEL 06
ELEV. 145'-10 5/8"
LEVEL 07
ELEV. 157'-5 1/4"
LEVEL 08
ELEV. 168'-11 7/8"
LEVEL 09
ELEV. 180'-6 1/2"
LEVEL 10
ELEV. 192'-1 1/8"
P.H. FL. & TOP OF ROOF SLAB
ELEV. 203'-7 3/4"
KLN
MACHINE ROOM
ELEV. 217'-2 3/8"
TANK RM. FL./TOP OF P.H. ROOF
ELEV. 227'-2 3/8"
QSTUXZAA RV
T.O. ROOF SLAB
ELEV. 243'-5"
A
A
A
23A9 23B9 23C9 23D10 23E9 23F9 23G9 23H9 23I9 23J9 23K9 23L9 23M9
23N1023M1023L1023K1023J1023I1023H1023G1023E10 23F1023C10 23D1023A10 23B10
N O
T
IN
S C
O
PE
ASBESTOS
CONTAINING
MASONRY
CAULK
LINE OF SOLARIUM
109 10a
EJ
24K10
24K924J9
24J10
ASBESTOS
CONTAINING
MASONRY
CAULK
LEVEL 09
ELEV. 180'-6 1/2"
LEVEL 10
ELEV. 192'-1 1/8"
P.H. FL. & TOP OF ROOF SLAB
ELEV. 203'-7 3/4"
10 910a
EJ22B1022A10
ASBESTOS
CONTAINING
MASONRY
CAULK
SCALE: 1/8" = 1'-0"3 ELEVATION - 23 (SOUTH)
SCALE: 1/8" = 1'-0"1 ELEVATION - 24 (EAST)
SCALE: 1/8" = 1'-0"2 ELEVATION - 22 (WEST)
ASBESTOS LOCATION LEGEND
ASBESTOS-CONTAINING MASONRY CAULK
ASBESTOS-CONTAINING FLASHING TAR
GENERAL HAZARDOUS
MATERIAL NOTES APPLICABLE
TO THE PROJECT AREA
1. AN ASBESTOS-CONTAINING MATERIALS (ACMS) SURVEY
WAS PERFORMED IN DECEMBER 2023 BY ARC
ENVIRONMENTAL AND IDENTIFIED MATERIALS ON THE
EXTERIOR FAÇADE. A SUPPLEMENTAL ASBESTOS SURVEY WAS
PERFORMED IN JUNE-JULY 2025 TO FURTHER DELINEATE
SUSPECT ACMS OBSERVED AT ACCESSIBLE PORTIONS OF
DROPS 1, 3, 21, 23, 25, & 26 WHICH ARE INCLUDED IN THE
PROJECT SCOPE. ASBESTOS-CONTAINING CAULK IS
CONFIRMED TO BE PRESENT ALONG THE VERTICAL JOINTS
BETWEEN PRE-CAST WINDOW PANELS AND BRICK MASONRY
AND ASBESTOS-CONTAINING FLASHING TAR HAS BEEN
IDENTIFIED ON METAL COPPER FLASHING. BOTH OF THESE
REQUIRE ABATEMENT TO FACILITATE THE FAÇADE REPAIRS. THE
CONTRACTOR SHALL REFER TO THE ASSOCIATED 'LIMITED
ASBESTOS-CONTAINING MATERIALS SURVEY - REPAIR
BUILDING 111 CONCRETE FAÇADE STUDY'' REPORT DATED
JUNE 28, 2024, AND 'SUPPLEMENTAL ASBESTOS-CONTAINING
MATERIALS SURVEY - BUILDING 111 CONCRETE FAÇADE
PROJECT' DATED AUGUST 28, 2025, FOR DETAILS RELATED TO
THE ASSESSMENTS AND ASSOCIATED ANALYTICAL DATA. THE
PROVIDED DRAWINGS AND SPECIFICATIONS DETAILING THE
SCOPE OF WORK FOR REMEDIATION AND ABATEMENT ARE
BASED ON THE COMPLETED SURVEYS AND THE PROJECT
SCOPE OF WORK.
2. ASBESTOS-CONTAINING MATERIALS HAVE BEEN IDENTIFIED
WITHIN THE PROJECT AREA. CONTRACTOR SHALL
COORDINATE WITH OTHER TRADES AS REQUIRED TO ENSURE
WORKER SAFETY, PHASING, AND PROPER HANDING,
REMOVAL, AND DISPOSAL OF ACMS. REFER TO
SPECIFICATION SECTION 02 82 11. IT IS ANTICIPATED THAT
ABATEMENT OF EXTERIOR CAULK WILL BE COMPLETED IN A
MANNER THAT MAINTAINS THE MATERIAL IN NON-FRIABLE
CONDITION. BRICK WORK IMPACTED BY ACM CAULK IS
SCOPED FOR REPLACEMENT; THEREFORE, IF MINIMAL
DAMAGE TO THE BRICK IS PERMITTED IF REQUIRED TO
PROPERLY ABATE THE IDENTIFIED ASBESTOS-CONTAINING
CAULK.
3. THE CONTRACTOR IS RESPONSIBLE FOR DAILY RE-
CAULKING/SEALING AREAS WHERE ASBESTOS-CONTAINING
CAULK IS ABATED TO ENSURE THAT THE INTEGRITY OF THE
BUILDING ENVELOPE IS MAINTAINED DURING CONSTRUCTION
ACTIVITIES. THE APPLIED CAULK/SEALANT SHALL BE APPROVED
THROUGH THE PRE-CONSTRUCTION SUBMITTAL PROCESS
PRIOR TO USE. ABATED AREAS SHALL NOT BE RE-
CAULKED/SEALED OR OTHERWISE CONCEALED UNTIL A
PASSING VISUAL CLEARANCE INSPECTION IS OBTAINED FOR
EACH AFFECTED WORK AREA AND APPROVED BY THE
INDUSTRIAL HYGIENIST.
4. IF IMPACTED, THE CONTRACTOR IS RESPONSIBLE FOR
ASSESSING AND SAMPLING ADDITIONAL SUSPECT ASBESTOS-
CONTAINING MATERIALS WITHIN THE PROJECT AREA PRIOR
TO DISTURBANCE OF THE MATERIAL(S) IF NEWLY DISCOVERED,
SUSPECT ACMS ARE IDENTIFIED DURING THE COURSE OF
CONSTRUCTION.
Project Number:
Building Number:
Drawing Number:
Project Title:
Location:
Issue Date: Checked: Drawn:
Drawing Title:
Approved: Project Director
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase:DESIGNER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Sprinkler:
600 E. Michigan Avenue, Suite B Kalamazoo, MI 49007 P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310 Alexandria, VA 22314 P: 202.617.8485 www.alliance.us.com
HAZARDOUS MATERIALS LOCATION PLAN
ELEVATIONS 25 (SOUTH)
BUILDING 111 FACADE REPAIR
5000 W NATIONAL AVE, MILWAUKEE, WI, 53295
695-22-121
MARCH 16, 2026 SK DL
100% BID DOCUMENTS
HA203
KEY PLAN
N
Revisions: Date:
(975.67)
LEVEL 01
ELEV. 83'-8"
LEVEL 02
ELEV. 97'-5 3/8"
LEVEL 03
ELEV. 111'-2 3/4"
LEVEL 04
ELEV. 122'-9 3/8"
LEVEL 05
ELEV. 134'-4"
LEVEL 06
ELEV. 145'-10 5/8"
LEVEL 07
ELEV. 157'-5 1/4"
LEVEL 08
ELEV. 168'-11 7/8"
LEVEL 09
ELEV. 180'-6 1/2"
LEVEL 10
ELEV. 192'-1 1/8"
P.H. FL. & TOP OF ROOF SLAB
ELEV. 203'-7 3/4"
AACCFFGGHHJJKKLL
A
25C2
25C3
25C4
25C5
25C6
25C7
25C8
25C9
25C10
25D2
25D3
25D4
25D5
25D6
25D7
25D8
25D9
25D10
25C1 25D125A1 25B1 25E1 25F1
ELEVATION 25ELEVATION 27
EJEJEJEJ
NOT IN SCOPE
ASBESTOS
CONTAINING
MASONRY
CAULK
SCALE: 1/8" = 1'-0"1 ELEVATION - 25 (SOUTH)
TO THE PROJECT AREA
1. AN ASBESTOS-CONTAINING MATERIALS (ACMS) SURVEY
WAS PERFORMED IN DECEMBER 2023 BY ARC
ENVIRONMENTAL AND IDENTIFIED MATERIALS ON THE
EXTERIOR FAÇADE. A SUPPLEMENTAL ASBESTOS SURVEY WAS
PERFORMED IN JUNE-JULY 2025 TO FURTHER DELINEATE
SUSPECT ACMS OBSERVED AT ACCESSIBLE PORTIONS OF
DROPS 1, 3, 21, 23, 25, & 26 WHICH ARE INCLUDED IN THE
PROJECT SCOPE. ASBESTOS-CONTAINING CAULK IS
CONFIRMED TO BE PRESENT ALONG THE VERTICAL JOINTS
BETWEEN PRE-CAST WINDOW PANELS AND BRICK MASONRY
AND ASBESTOS-CONTAINING FLASHING TAR HAS BEEN
IDENTIFIED ON METAL COPPER FLASHING. BOTH OF THESE
REQUIRE ABATEMENT TO FACILITATE THE FAÇADE REPAIRS. THE
CONTRACTOR SHALL REFER TO THE ASSOCIATED 'LIMITED
ASBESTOS-CONTAINING MATERIALS SURVEY - REPAIR
BUILDING 111 CONCRETE FAÇADE STUDY'' REPORT DATED
JUNE 28, 2024, AND 'SUPPLEMENTAL ASBESTOS-CONTAINING
MATERIALS SURVEY - BUILDING 111 CONCRETE FAÇADE
PROJECT' DATED AUGUST 28, 2025, FOR DETAILS RELATED TO
THE ASSESSMENTS AND ASSOCIATED ANALYTICAL DATA. THE
PROVIDED DRAWINGS AND SPECIFICATIONS DETAILING THE
SCOPE OF WORK FOR REMEDIATION AND ABATEMENT ARE
BASED ON THE COMPLETED SURVEYS AND THE PROJECT
SCOPE OF WORK.
2. ASBESTOS-CONTAINING MATERIALS HAVE BEEN IDENTIFIED
WITHIN THE PROJECT AREA. CONTRACTOR SHALL
COORDINATE WITH OTHER TRADES AS REQUIRED TO ENSURE
WORKER SAFETY, PHASING, AND PROPER HANDING,
REMOVAL, AND DISPOSAL OF ACMS. REFER TO
SPECIFICATION SECTION 02 82 11. IT IS ANTICIPATED THAT
ABATEMENT OF EXTERIOR CAULK WILL BE COMPLETED IN A
MANNER THAT MAINTAINS THE MATERIAL IN NON-FRIABLE
CONDITION. BRICK WORK IMPACTED BY ACM CAULK IS
SCOPED FOR REPLACEMENT; THEREFORE, IF MINIMAL
DAMAGE TO THE BRICK IS PERMITTED IF REQUIRED TO
PROPERLY ABATE THE IDENTIFIED ASBESTOS-CONTAINING
CAULK.
3. THE CONTRACTOR IS RESPONSIBLE FOR DAILY RE-
CAULKING/SEALING AREAS WHERE ASBESTOS-CONTAINING
CAULK IS ABATED TO ENSURE THAT THE INTEGRITY OF THE
BUILDING ENVELOPE IS MAINTAINED DURING CONSTRUCTION
ACTIVITIES. THE APPLIED CAULK/SEALANT SHALL BE APPROVED
THROUGH THE PRE-CONSTRUCTION SUBMITTAL PROCESS
PRIOR TO USE. ABATED AREAS SHALL NOT BE RE-
CAULKED/SEALED OR OTHERWISE CONCEALED UNTIL A
PASSING VISUAL CLEARANCE INSPECTION IS OBTAINED FOR
EACH AFFECTED WORK AREA AND APPROVED BY THE
INDUSTRIAL HYGIENIST.
4. IF IMPACTED, THE CONTRACTOR IS RESPONSIBLE FOR
ASSESSING AND SAMPLING ADDITIONAL SUSPECT ASBESTOS-
CONTAINING MATERIALS WITHIN THE PROJECT AREA PRIOR
TO DISTURBANCE OF THE MATERIAL(S) IF NEWLY DISCOVERED,
SUSPECT ACMS ARE IDENTIFIED DURING THE COURSE OF
CONSTRUCTION.
ASBESTOS LOCATION LEGEND
ASBESTOS-CONTAINING MASONRY CAULK
ASBESTOS-CONTAINING FLASHING TAR
Project Number:
Building Number:
Drawing Number:
Project Title:
Location:
Issue Date: Checked: Drawn:
Drawing Title:
Approved: Project Director
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase:DESIGNER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Sprinkler:
600 E. Michigan Avenue, Suite B Kalamazoo, MI 49007 P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310 Alexandria, VA 22314 P: 202.617.8485 www.alliance.us.com
HAZARDOUS MATERIALS LOCATION PLAN
ELEVATIONS 26 (WEST)
BUILDING 111 FACADE REPAIR
5000 W NATIONAL AVE, MILWAUKEE, WI, 53295
695-22-121
MARCH 16, 2026 SK DL
100% BID DOCUMENTS
HA204
KEY PLAN
N
�26
Revisions: Date:
(975.67)
LEVEL 01
ELEV. 83'-8"
LEVEL 02
ELEV. 97'-5 3/8"
LEVEL 03
ELEV. 111'-2 3/4"
LEVEL 04
ELEV. 122'-9 3/8"
LEVEL 05
ELEV. 134'-4"
LEVEL 06
ELEV. 145'-10 5/8"
LEVEL 07
ELEV. 157'-5 1/4"
LEVEL 08
ELEV. 168'-11 7/8"
LEVEL 09
ELEV. 180'-6 1/2"
LEVEL 10
ELEV. 192'-1 1/8"
P.H. FL. & TOP OF ROOF SLAB
ELEV. 203'-7 3/4"
8 7 6 5 4 2 13
26F2
26F3
26F4
26F5
26F6
26F7
26F8
26F9
26F10
26E2
26E3
26E4
26E5
26E6
26E7
26E8
26E9
26E10
26B2
26B3
26B4
26B5
26B6
26B7
26B8
26B9
26B10
26A2
26A3
26A4
26A5
26A6
26A7
26A8
26A9
26A10
26C126B1 26D1 26E1 26F1
NOT IN SCOPENOT IN SCOPE
BASE BID
EMERGENCY EXIT
2ND FLOOR ROOF
ACCESS DOOR
JJKK
NOT IN SCOPE
ASBESTOS
CONTAINING
MASONRY
CAULK
ASBESTOS
CONTAINING
MASONRY
CAULK
EJ
SCALE: 1/8" = 1'-0"2 ELEVATION - 26 (WEST)
SCALE: 1/8" = 1'-0"1 ELEVATION - 27 (SOUTH)
| G001 - TITLE SHEET |
| G002 - GENERAL INFO & SYMBOL LEGEND |
| G003 - ROOF PLANS AND ISOMETRICS |
| G004 - ROOF AND ELEVATOR ACCESS FLOORS 1 AND 3 |
| G005 - ROOF PLAN ACCESS INFORMATION FLOORS 9 AND 11 |
| A200 - EXTERIOR ELEVATIONS - 3 AND 1 (NORTH) |
| A201 - EXTERIOR ELEVATIONS - 21 (SOUTH) |
| A202 - EXTERIOR ELEVATIONS - 23 (SOUTH) |
| A203 - EXTERIOR ELEVATIONS - 25 (SOUTH) |
| A204 - EXTERIOR ELEVATIONS - 26 (WEST) |
| A300 - ENLARGED ELEVATIONS |
| A301 - WALL SECTIONS AND DETAILS |
| A302 - REPAIR DETAILS |
| A303 - REPAIR DETAILS |
| HA200 - HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 3 AND 1 (NORTH) |
| HA201 - HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 21 (SOUTH) |
| HA202 - HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 23 (SOUTH) |
| HA203 - HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 25 (SOUTH) |
| HA204 - HAZARDOUS MATERIALS LOCATION PLAN ELEVATIONS 26 (WEST) |
File details come from the government source that posted it. Updated .