S02_631-19-003 Repair Foundation Cracks - Combined Specs V2.pdf

PDF 5 MB Posted

Attached to
Z1DZ--631-19-003 Repair Foundation Cracks
Solicitation number
36C24123B0014
Issued by

About this file

This is a solicitation for a construction project to repair foundation cracks at various buildings on the campus of the Edward P. Boland VA Medical Center in Leeds, Massachusetts. The solicitation number is 36C24123B0014 and involves work at buildings 1, 2, 3, 5, 8, 9, 11, 12, 13, 13S, 14, 15, 16, 22, 25, 45, and 60. The project includes repairing exterior cracks, interior cracks, hairline cracks, cracks through foundation walls, surface cracks, and concrete and parging deteriorations. Bidders must submit preconstruction documents and plans outlining project management teams that will oversee construction. The contract award is for general construction services and management of subcontractors to complete the foundation crack repairs according to drawings and specifications over a 270-day period of performance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FINAL BID DOCUMENTS

MASTER SPECIFICATION INDEX

For:

Repair Foundation Cracks Edward P. Boland VAMC

631-19-003 - Repair Foundation Cracks Final Bid Documents USDVA – Edward P. Boland VA Medical Center 05/31/2023

00 01 10 - 1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21 01 33 23 Shop Drawings, Product Data, and Samples 02-23 01 35 26 Safety Requirements 10-22 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 57 15 Temporary Construction Noise and Vibration Control 10-22 01 57 19 Temporary Environmental Controls 01-21 01 74 19 Construction Waste Management 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

03 01 00 Rehabilitation of Concrete 02-18 03 30 00 Cast-in-Place Concrete 01-21

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants 04-22

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI003 TITLE SHEET

GI004 DRAWING INDEX

GC103 PROJECT PHASING AND STAGING PLAN

STRUCTURAL

S-002 STRUCTURAL NOTES & LEGEND

S-003 STRUCTURAL NOTES & LEGEND

S-203 STRUCTURAL ELEVATION - BLDG 1 NORTH

S-204 STRUCTURAL ELEVATION - BLDG 1 NORTH EAST SIDE

S-205 STRUCTURAL ELEVATION - BLDG 1 NORTH WEST SIDE

S-206 STRUCTURAL ELEVATION - BLDG 1 EAST & WEST

S-207 STRUCTURAL ELEVATION - BLDG 1 WEST

S-208 STRUCTURAL ELEVATION - BLDG 1 EAST

S-209 STRUCTURAL ELEVATION - BLDG 1 EAST

S-210 STRUCTURAL ELEVATION - BLDG 1 WEST

S-211 STRUCTURAL ELEVATION - BLDG 1 SOUTH EAST SIDE

S-212 STRUCTURAL ELEVATION - BLDG 1 SOUTH WEST SIDE

S-213 STRUCTURAL ELEVATION - BLDG 1 EAST

S-214 STRUCTURAL ELEVATION - BLDG 1 WEST

S-117 STRUCTURAL REPAIR PLAN - BLDG 2 BASEMENT

S-215 STRUCTURAL ELEVATION - BLDG 2 SOUTH

S-216 STRUCTURAL ELEVATION - BLDG 2 NORTH

S-217 STRUCTURAL ELEVATION - BLDG 2 WEST

S-218 STRUCTURAL ELEVATION - BLDG 2 EAST

S-265 STRUCTURAL INTERIOR ELEVATION-BLDG 2 BASEMENT

S-118 STRUCTURAL REPAIR PLAN - BLDG 3 BASEMENT

S-219 STRUCTURAL ELEVATION - BLDG 3 EAST

S-220 STRUCTURAL ELEVATION - BLDG 3 WEST

S-221 STRUCTURAL ELEVATION - BLDG 3 SOUTH

S-222 STRUCTURAL ELEVATION - BLDG 3 NORTH

S-266 STRUCTURAL INTERIOR ELEVATION-BLDG 3 BASEMENT

S-229 STRUCTURAL ELEVATION - BLDG 5 EAST

S-230 STRUCTURAL ELEVATION - BLDG 5 NORTH

S-231 STRUCTURAL ELEVATION - BLDG 5 WEST

S-232 STRUCTURAL ELEVATION - BLDG 5 SOUTH

S-401 ENLARGED STRUCTURAL ELEVATION-BLDG 5

S-121 STRUCTURAL REPAIR PLAN - BLDG 8 BASEMENT

S-233 STRUCTURAL ELEVATION - BLDG 8 WEST & EAST

00 01 15 - 2

S-234 STRUCTURAL ELEVATION - BLDG 8 NORTH

S-235 STRUCTURAL ELEVATION - BLDG 8 SOUTH

S-271 STRUCTURAL INTERIOR ELEVATION-BLDG 8 BASEMENT

S-122 STRUCTURAL REPAIR PLAN - BLDG 9 BASEMENT

S-237 STRUCTURAL ELEVATION - BLDG 9 SOUTH

S-238 STRUCTURAL ELEVATION - BLDG 9 EAST & WEST

S-239 STRUCTURAL ELEVATION - BLDG 9 EAST

S-272 STRUCTURAL INTERIOR ELEVATION- BLDG 9 BASEMENT

S-123 STRUCTURAL REPAIR PLAN - BLDG 11 BASEMENT

S-240 STRUCTURAL ELEVATION - BLDG 11 EAST & NORTH

S-241 STRUCTURAL ELEVATION - BLDG 11 WEST & SOUTH

S-274 STRUCTURAL INTERIOR ELEVATION-BLDG 11 BASEMENT

S-124 STRUCTURAL REPAIR PLAN - BLDG 12 BASEMENT

S-242 STRUCTURAL ELEVATION - BLDG 12 EAST

S-243 STRUCTURAL ELEVATION - BLDG 12 WEST

S-244 STRUCTURAL ELEVATION - BLDG 12 NORTH & SOUTH

S-276 STRUCTURAL INTERIOR ELEVATION - BLDG 12 BASEMENT

S-245 STRUCTURAL ELEVATION - BLDG 13 NORTH & EAST

S-246 STRUCTURAL ELEVATION - BLDG 13 SOUTH & WEST

S-247 STRUCTURAL ELEVATION - BLDG 13S

S-248 STRUCTURAL ELEVATION - BLDG 14 WEST

S-249 STRUCTURAL ELEVATION - BLDG 14 SOUTH & NORTH

S-251 STRUCTURAL ELEVATION - BLDG 15-16 EAST

S-252 STRUCTURAL ELEVATION - BLDG 15-16 NORTH & SOUTH

S-253 STRUCTURAL ELEVATION - BLDG 15-16 WEST

S-129 STRUCTURAL REPAIR PLAN - BLDG 22 BASEMENT

S-254 STRUCTURAL ELEVATION - BLDG 22

S-282 STRUCTURAL INTERIOR ELEVATIONS-BLDG 22 BASEMENT

S-130 STRUCTURAL REPAIR PLAN - BLDG 25 BASEMENT

S-255 STRUCTURAL ELEVATION - BLDG 25 WEST & SOUTH

S-256 STRUCTURAL ELEVATION - BLDG 25 EAST & NORTH

S-283 STRUCTURAL INTERIOR ELEVATION BLDG-25 BASEMENT

S-257 STRUCTURAL ELEVATION - BLDG 45

S-258 STRUCTURAL ELEVATION - BLDG 60 NORTH & WEST

S-259 STRUCTURAL ELEVATION - BLDG 60 SOUTH & EAST

S-501 STRUCTURAL DETAILS

- - - END - - -

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements. Contractor to submit the following as required:

1. Interim Life Safety Measures.

2. Infection Control Risk Assessments.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, furnish labor and materials, and interior repair work for Central Western

Massachusetts Healthcare System – Repair Foundation Cracks as required by the drawings and specifications.

B. Before placement and installation of work subject to tests by testing laboratory retained by the COR, the Contractor shall notify the COR to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall not be less than fifteen (15) work days unless otherwise designed by the

COR.

C. All employees of the general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

01 00 00 -2

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION (BASE BID): The General Contractor will be responsible for all facets of construction management and construction work and the management of subcontractors to facilitate a construction project to Repair Foundation Crack

Deficiencies in accordance with Construction Drawings and

Specification as well as other contractual documents.

1. This project will repair foundation deficiencies (exterior cracks, interior cracks, hairline/superficial cracks, cracks going through foundation wall, surface cracks, chips), concrete and parging coat deteriorations. The project building locations for this work include Buildings 1, 2, 3, 5, 8, 9, 11, 12, 13, 13S, 14, 15, 16, 22, 25, 45, and 60.

MANAGEMENT TEAM

A. All of the people listed below need to attend all construction meetings.

B. Provide preconstruction submittal with delegation and identification letter for each of the persons below including any resumes or certifications demonstrating to the below requirements.

C. Project Manager

1. Minimum 10 years construction experience with at least 5 years management experience with projects similar in size and scope.

2. Be able to dedicate a minimum of 50% of time to this project.

3. The Project Manager shall be a separate qualified individual from the Prime Contractor’s Superintendent, MEP Coordinator, Safety Manager and CQC System Manager having duties only as the Project Manager.

01 00 00 -3

D. Superintendent

1. Provide project superintendent with a minimum of ten [10] years of experience in construction with at least five [5] of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of OSHA and have experience in the areas of hazard identification and safety compliance in addition to safety training requirements indicated elsewhere in the project documents. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The project superintendent shall be dedicated to this project only and not assigned on other contracts.

2. The Superintendent shall be a separate qualified individual from the Prime Contractor’s MEP Coordinator and CQC System

Manager, and the Safety Manager.

3. The General Contractor must provide adequate supervision for all locations (worksites / buildings) of work whenever work is being performed. This supervision must come from the General

Contractor and must be a competent person. This project will potentially have work in multiple locations concurrently and the General Contractor is expected to provide required additional supervision.

E. CQC System Manager

1. CQC System Manager (must meet all requirement in 01 45 00 specification) is responsible for overall management of CQC and has the authority to act in all CQC matters for the

Contractor. The CQC System manager is on the site at all times during construction and is employed by the General Contractor.

F. Safety Manager

01 00 00 -4

1. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and must meet requirements in 01 35 26 specification and be capable (through training, experience, and qualifications) of ensuring that the requirements of 29 CFR 1926.16 and other appropriate Federal, State and local requirements are met for the project.

2. The SSHO shall be a separated qualified individual from the

Prime Contractor’s CQC System Manager, but maybe assigned as an additional duty to the Superintendent.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without an appropriate VA issued PIV badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. All General Contractor’s employees and their sub-contractors shall always have their issued PIV badge on their person and visible while on VA property. Contractors are to be familiar with the VA multi-step PIV badging process. The PIV badging process may require a minimum of two visits to a VA facility to be fingerprinted, sponsored, register for a background check, and to receive a badge. Two (2) forms of identification will be required. This approval process may take more then 3+

01 00 00 -5 days to complete. It is the expectation of this project that each and every contractor be badged regardless of task or location. If working on site for one day only, the contractor’s employee is only required to register with the VA

Police Department at building 25. A temporary badge will be provided.

3. No photography of VA premises is allowed without written permission of the COR. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the

Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.

2. The VA will provide the General Contractor a defined number of keys as required to gain access to certain sensitive rooms.

The General Contractor is responsible for the control of these keys. If at any time, a General Contractor’s key is lost, the

General Contractor will be responsible for replacing ALL cores associated with the lost key at $45.00 per core. These keys are a controlled item, and their locations are inspectable by the VA at any time at a minimum, weekly. Unused keys are to be kept in a lockbox in a secure location approved by the COR and campus security.

01 00 00 -6

3. The General Contractor will be responsible for the costs associated with the replacement of the cores and any damages suffered by the Government.

D. Document Control:

1. Before starting any work, the General Contractor/Sub

Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the COR upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of the COR.

5. All paper waste or electronic media such as CD’s shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify the COR and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

01 00 00 -7

Security, access, and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Motor Vehicles belonging to any contractor must be registered at the Police HQ in Bldg 25 and attain a parking pass for employee lots. This includes personally owned and company vehicles. These passes must be visibly displayed at all times while parked on VAMC campus. Contractor parking will be limited to Lots N and P and by written permission of the COR at any other employee lot. There will be absolutely no parking in patient parking spaces or ADA spaces (unless the contractor has an applicable decal/tag).

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The General Contractor will provide a Logistics Plan to include proposed laydown areas, delivery routes, container / equipment staging, temporary toilets, dumpsters, expected ingress and egress if applicable, location of construction fencing for work area and laydown area, parking, etc. The COR must approve the

Logistics Plan prior to the General Contractor executing.

B. All containers / pallets must be marked with the contract/task order number and 8 digit project number. Dumpster locations

(not the individual dumpsters) will also be marked if used over five (5) business days.

1. VA Warehouse will not and cannot accept any contractor deliveries and will turn away any such deliveries.

01 00 00 -8

C. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

D. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the COR, the buildings and utilities may be abandoned and need not be removed.

E. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the COR.

When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

F. Working space and space available for storing materials shall be as shown on the drawings or as determined by the COR.

G. Workers are subject to rules of the Medical Center applicable to their conduct.

H. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of

01 00 00 -9 construction materials, debris, standing construction equipment and vehicles at all times.

I. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by

Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to

Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

J. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

All such actions shall be coordinated with the COR or Utility

Company involved.

K. Phasing:

01 00 00 -10

1. The Medical Center must maintain its operation 24 hours a day

7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to the COR and Contractor, as follows:

a. Each building shall be considered a phase.

b. Building 1 may be split into multiple phases.

3. When the Contractor’s work interferes with hospital functions, such as when work produces excessive noise, odors, dust, utility service interruptions, or other interferences with normal hospital operations that cannot be contained within the area of work, the Contractor shall schedule said work at other than normal hours and as directed by the COR.

4. Review the Construction Notes on the drawings for each building. All on-site work (including cleanup) shall take place during the specified times, unless otherwise approved by the COR:

01 00 00 -11

5. Operational Hours: 7am-6pm Monday through Friday. Building(s) will be occupied during performance of work.

6. Off-Hours: 6pm-7am Monday- Friday and anytime Saturday and

Sunday. Activities impacting normal operations, scheduling conflicts or noisy work shall be scheduled off-hours.

a. Building 1 noisy work will be scheduled off-hours, during the times of 6am-8am and 5pm–7pm Monday – Friday only.

7. Holidays excepted unless other times are arranged in advance and approved in writing by the Project COR.

8. Work for project phase shall not commence until all material required to complete that phase are on site and ready for incorporation into the project.

9. This project includes 60 calendar days of administrative time to complete preconstruction submissions and other preparation prior to the start of the period of performance and additional

60 calendar days of closeout, i.e., site restoration, inspection, final clean, etc. for a total of 120 calendar days. Work shall commence upon receipt of a Notice to Proceed

(NTP) from the government and shall be completed within 270 calendar days (i.e. Period of Performance) after receipt of

NTP.

L. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to

Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate

01 00 00 -12 patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

M. Construction Fence: Submit proposed construction fence on the Logistic Plan. All work and laydown areas are required to be fenced, and gates to be lockable. Before construction operations begin, Contractor shall provide a chain link construction fence, eight feet minimum height, around each construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Ensure the Fire

Department has access to the Fire Department Connection (FDC) at each building at all times. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR. Provide the entire construction fence with an approved fabric privacy screening full height with wind cutouts.

Opacity/shade percentage 85% lock-stitch strength 50 lbs. per ft consisting of a knitted high density polyethylene filament. Color and design to be approved by COR.

N. When a building construction site is turned over to the Contractor, the Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C

(40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department if and when deemed necessary by the COR.

01 00 00 -13

O. Utilities Services: Maintain existing utility services for the Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc.

of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.

Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the

Medical Center Director’s prior knowledge and written approval.

2. Minor interruptions of any system must be requested, in writing, six (6) work days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Medical

Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 10 calendar days prior to the desired time and shall be performed as directed by the COR.

01 00 00 -14

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes, vents, and the like, and their hangers or supports, shall be completely removed back to their source.

1. Those which are indicated to be abandoned but cannot be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from in an approved method and as accepted by the COR.

2. Abandoned raceways that cannot be fully removed shall have the cables removed in all of those abandoned raceways and duct banks. Where removal of conduit and duct banks is not feasible and if approved by COR, cut abandoned raceway at horizontal level (before turn up) and cap (do not use tape – use an approved existing style conduit type cap) and paint cap red.

Indicate location on record documents.

3. The intent is that those systems listed above that are so embedded in existing concrete walls or floors that they cannot fully be removed without compromising the structure can be capped. These shall be fully investigated by the contractor and reviewed and accepted by the COR.

4. The lines shall not be capped in any finished or unfinished areas, but shall be removed and sealed, capped or plugged in only in masonry, CMU, concrete walls, concrete ceilings or concrete floors where they penetrate those materials or if accepted by the COR within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

01 00 00 -15

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Review Fire Alarm System and Panels: General Contractor is required to review and document the conditions of the existing

Fire Alarm System and Panels prior to beginning work. Determine existing state and sign-off that any troubles or other errors that occur are not an existing condition.

O. Noise and Vibration – See Specification 01 57 15 and Pre-

Construction Risk Assessment (PCRA).

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the COR. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout the affected areas of the building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, shades, etc., required by drawings to be either reused or relocated, or both.

01 00 00 -16

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled

"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

01 00 00 -17

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT

01 00 00 -18 required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

01 00 00 -19

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant

Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials;

and

5. Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work

01 00 00 -20 without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems

(including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS"

(FAR 52.236-2).

1.11 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.

01 00 00 -21

The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR.

The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark

(through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, 01 00 00 -22 floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.

F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.

01 00 00 -23

G. The contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of article "professional surveying services".

1.12 AS-BUILT DOCUMENTATION

A. The contractor shall maintain a full size set of Redline drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

A copy of this set must be provided monthly with application for payment.

B. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of pre-final punch list. Provide record drawings as follows:

C. Red-lined, hand-marked drawings are to be provided, with one paper copy and a scanned PDF version of the hand-marked drawings provided on CD or DVD 15 workdays prior to Pre-final punch list.

The pre-final punch list will not be scheduled until complete red-lines are received and approved.

D. AutoCAD as-built drawings to be submitted in the most current version of AutoCAD.

E. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.

F. Record Specifications: The Contractor shall maintain a copy of the Project Specifications, including addenda and modifications issued, for Project Record Documents. The Contractor shall mark the Specifications to indicate the actual installation where the installation varies substantially from that indicated in the

01 00 00 -24

Contract Specifications and modifications issued. (Note related

Project Record Drawing information where applicable). The

Contractor shall pay particular attention to substitutions, selection of product options, and information on concealed installations that would be difficult to identify or measure and record later. Upon completion of the mark ups, the Contractor shall submit record Specifications to the COR. As with master relines, Contractor shall maintain record specifications for COR review and inspection at any time.

G. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall contain a written sequence of test procedure with written test results annotated at each step along with the expected outcome or setpoint. The results shall include all readings, including but not limited to data on device (make, model and performance characteristics), normal pressures, switch ranges, trip points

H. Submit manufacturer’s literature and data updated to include submittal review comments and any equipment substitutions.

I. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or

DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation shall be included in the operation and maintenance manual. The operations and maintenance manual shall include

01 00 00 -25 troubleshooting techniques and procedures for emergency situations. Notes on all special systems or devices shall be included. A List of recommended spare parts (manufacturer, model number, and quantity) shall be furnished. Information explaining any special knowledge or tools the owner will be required to employ shall be inserted into the As-Built documentation.

J. The installing contractor shall maintain as-built drawings of each completed phase for verification; and shall provide the complete set at the time of final systems certification testing.

Should the installing contractor engage the testing company to provide as built or any portion thereof, it shall not deem a conflict of interest or breach of the ‘third party testing company’ requirement.

1.13 COORDINATION

A. Coordinate work and products meeting the requirements associated with all applicable specification sections and plans to produce a system complete, functional, and ready for the purpose intended.

B. Pre-worksite Re-visit Requirements: Before starting work in a particular area, visit the worksite and carefully examine the areas to verify complexity, existing conditions and difficulties that will affect work including all work done under various specification sections and the VA. Commencement of work shall be construed as acceptance of the existing conditions and difficulties. No change to the contract price or schedule shall be allowed for work caused by unfamiliarity with the site conditions that are visible or readily construed by an experienced observer.

C. Coordinate the location of all work, equipment and components with all trades and equipment installers to prevent interferences and maintain proper use and access to all items and spaces. Refer to the “Coordination Drawing Checklist” for

01 00 00 -26 further details. General Contractor is responsible for coordinating all equipment and components being installed with the placement location and dimension requirements. Prior to job execution each trade shall submit “complete” coordinated shop drawings indicating all equipment and material layouts with locations from walls/columns, bottom/top elevations, vibration isolators, supports, dimensions, utility requirements and equipment submittal numbers. Each trade shall maintain a set of working drawings to document as-built information as the work progresses and submit to the COR monthly for review.

D. New work shall be installed and connected to existing work neatly and carefully. All work shall be coordinated with other trades to avoid conflicts and to obtain a neat competent installation that will afford maximum accessibility for easy and proper operation, maintenance, service, and headroom. All work shall be installed in a manner that permits easy accessibility and proper removal of system components requiring periodic service. Disturbed or damaged work shall be replaced or repaired to new conditions. Any items determined to be in non-compliance shall be corrected by the Contractor at no additional expense to the Government.

E. The drawings show or describe the general arrangement of equipment, articles, assemblies, appurtenances but do not show all required fittings, drains, air vents, supports and may not identify all required accessories, components, fittings, and offsets that are necessary to properly complete the installation for the purpose intended. The contract drawings are diagrammatic only intended to show general layout of conduit, ductwork, piping, equipment, terminals, specialties and not intended to show all required offsets, details, accessories and equipment to be connected. Provide all necessary fittings, offsets and pipe runs based on field measurements and reviewed coordination

01 00 00 -27 drawings. Coordinate with other trades for space available and relative location of equipment and accessories to be connected at all locations. The Contractor shall alter locations of items where necessary to avoid interference and clearance difficulties. Locations of components and equipment shall be adjusted to accommodate the work with interferences anticipated and encountered. The Contractor shall determine the exact routing and location of systems prior to fabrication and installation. Accurate field measurements and coordination drawings shall be prepared to establish the locations and characteristics of the various systems (new and existing to remain). It is the intent of the drawings/specifications that the Contractor provides all materials, labor and coordination necessary to complete the work described or implied by the contract documents at no additional cost/time to the

Government. The Contractor shall propose with submitted coordination drawings other dimensions with similar characteristics where necessary to avoid interferences and clearance difficulties. Should the contract documents not agree with themselves the greater quantity of superior work and materials shall be performed.

F. Coordinate all mechanical (eg, HVAC), electrical, plumbing (MEP) utility service, fire protection sprinkler system shutdowns and space access three (3) weeks in advance with the COR. Due to facility scheduling and access difficulties, some shutdowns and the performance of certain work will need to be performed during off-hours by the Contractor. Arrange phases and perform work to ensure utility services for other buildings and areas at all times as required.

G. Before placement and installation of work subject to tests, the

Contractor shall coordinate and notify the COR in sufficient time to enable testing personnel to be present at the site in time for

01 00 00 -28 proper testing and field inspection. Such prior notice shall be not less than two (2) weeks unless otherwise designated by the

COR.

1.14 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of

Construction in at least 30 days before the…