S02 36C10F25R0006 Final.pdf

PDF 822 KB Posted

Attached to
Jefferson Barracks National Cemetery, Sylvan Springs, Phase 1 Development Federal contract opportunity
Solicitation number
36C10F25R0006
Issued by
Department of Veterans Affairs Office of Construction and Facilities Management

About this file

This document is a Request for Proposal (RFP) for the Jefferson Barracks National Cemetery Phase 1 Development project located in Saint Louis, Missouri. The Department of Veterans Affairs (VA) is seeking a Service-Disabled Veteran-Owned Small Business (SDVOSB) contractor to expand the 33.6-acre cemetery, which will increase burial capacity for approximately 208,000 veterans within a 75-mile service area. The project includes constructing 36,511 gravesites (18,533 pre-placed crypt full casket gravesites, 2,124 traditional casket gravesites, 10,854 in-ground cremation sites, and 5,000 columbarium niches), along with infrastructure improvements.

The solicitation (Solicitation Number 36C10F25R0006) is a Firm-Fixed-Price contract with a total performance period of 912 calendar days. The estimated project cost ranges between $50 million and $100 million, with an early turnover (ETO) phase required within 252 calendar days. The contract is set aside for SDVOSBs using a tiered evaluation approach, with the North American Industry Classification System (NAICS) code 237990 and a size standard of $45 million. Proposals are due by September 29, 2025, at 3:00 PM ET, and will be evaluated using a best value tradeoff process, with technical factors weighted more significantly than price.

View the file

Other files for this federal contract opportunity

Other files attached to Jefferson Barracks National Cemetery, Sylvan Springs, Phase 1 Development, newest first.
File Type Posted
S06 36C10F25R0006 0007.pdf PDF
S06 36C10F25R0006 0006.pdf PDF
VA 854-042 - JBNC Phase 1 - RFI Master List.xlsx XLSX spreadsheet
VA 852-042 - JBNC Phase 1 - Design Narrative.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 30-46.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 60-70.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 102-130.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 131-135.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 165-195.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 227-232.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 233-239.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 276-294.pdf PDF
VA 852-042 - JBNC Phase 1 - Specifications Vol. 2 2.0.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 15-29.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 94-101.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 196-215.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 216-220.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 221-226.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 266-275.pdf PDF
S06 36C10F25R0006 0005.pdf PDF
VA 852-042 - JBNC Phase 1 - Specifications Vol. 1 2.0.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 1-14.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 82-93.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 136-148.pdf PDF
VA 854-042 - JBNC Phase 1 Drawings 2.0 240-244.pdf PDF
S06 36C10F25R0006 0004.pdf PDF
S02 36C10F25R0006 0003.pdf PDF
S06 36C10F25R0006 0002.pdf PDF
S06 36C10F25R0006 0001.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 2.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 6.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 16.pdf PDF
S02 ATTACH VAAR 852.219-75 CERTIFICATE OF COMPLIANCE.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 3.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 8.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 11.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 14.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 17.pdf PDF
S02 ATTACH Wage Determination St.Louis, MO - Heavy and Highway.pdf PDF
S02 ATTACH Wage Determination St.Louis, MO - Building.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 1.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 5.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 7.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 9.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 10.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 12.pdf PDF
S02 ATTACH VA 852-042 - JBNC SS Phase 1 Drawings - Part 13.pdf PDF
S02 ATTACH Pre-Proposal Inquiry Form 36C10F25R0006.docx DOCX document
S02 ATTACH VA 852-042 - JBNC Phase 1 - Specifications Vol 1.pdf PDF
S02 ATTACH VA 852-042 - JBNC Phase 1 - Specifications Vol 2.pdf PDF
Show all 50

Jefferson Barracks National Cemetery, Sylvan Springs, Phase 1 Development has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C10F25R0006

X

TBD TBD

852-042

36C10F

Department of Veterans Affairs Office of Construction and Facilities Management (003C4B) 425 I Street NW Washington DC 20001

Department of Veterans Affairs Office of Construction and Facilities Management (003C4B) 425 I Street NW Washington DC 20001

Joshua Gibson; Joshua.Gibson2@va.gov RFIs are by e-mail only

Jefferson Barracks National Cemetery | Phase 1 Development | Project Number 852-042

The Department of Veterans Affairs (VA), Office of Construction and Facilities Management (CFM) anticipates awarding a Firm-Fixed-Price contract resulting from this solicitation for Phase 1 Development project located in Saint Louis, Missouri, 63125. The Contractor shall provide all labor, Materials, equipment and supervision for the construction as shown on the Statement of Work, plans, drawings and specifications (see attachments for details).

In accordance with 38 U.S.C. 8127 (Public Law 109-461), this procurement is set-aside for SDVOSBs utilizing a tiered evaluation approach, including other than small businesses, to minimize delays in the re-solicitation process.

The North American Industry Classification System (NAICS) is 237990 (Other Heavy and Civil Engineering Construction) with the size standard of $45 Million.

VAAR Subpart 819.70, The VA Veterans First Contracting Program applies to this solicitation.

The magnitude of construction cost for this project is between $50,000,000 and $100,000,000.

Contractors are required to electronically submit proposals by email to the contracting officer by the due date and time.

Site Visit: See Page 31, 52.236-27 SITE VISIT (CONSTRUCTION)(FEB 1995) ALTERNATE I(FEB 1995) for Site Visit information.

The award will be made to the offeror whose proposal represents the “best value” to the Government utilizing the Best Value Tradeoff process in accordance with FAR 15.101-1.

10 912

X X 52.211-10

X 10

0 3:00 PM ET

9/29/2025

X mailto:Joshua.Gibson2@va.gov

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

CLIN 0001 – Base Bid – General Construction CLIN 0002 – Base Bid – Pre-Placed Crypts CLIN 0003 – Option #1 CLIN 0004 – Option #2 CLIN 0005 – Option #3 CLIN 0006 – Option #4

36C10F

Department of Veterans Affairs Office of Construction and Facilities Management (003C4B) 425 I Street NW

FMS-VA-2(101)

Financial Services Center PO Box 149971 Austin TX 78714-9971

Table of Contents

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR

REPAIR)– BACK

PRICE/COST SCHEDULE

PART I – GENERAL

STATEMENT OF WORK (SOW)

PART II – PROPOSAL INFORMATION

2.1 INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

2.2 INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.3 SOLICITATION NOTICE OF TIERED SET-ASIDE EVALUATIONS

2.4 OFFEROR SUBMISSION INSTRUCTIONS

2.4.1 Volume I – Technical Proposal

2.4.2 Volume II – Price Proposal

2.5 EVALUATION METHODOLOGY

2.6 EVALUATION FACTOR WEIGHTINGS

2.7 DEFINITIONS

PART III – PROVISIONS

3.1 52.216-1 TYPE OF CONTRACT (APR 1984)

3.2 52.217-5 EVALUATION OF OPTIONS (JUL 1990)

3.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF

THE WORK (MAY 2014)

3.4 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014) AND

ALTERNATE II (NOV 2023)

3.5 52.228-1 BID GUARANTEE (SEP 1996)

3.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)

3.7 52.233-2 SERVICE OF PROTEST (SEP 2006)

3.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

3.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

3.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT

2018)

3.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

3.12 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY

ACCESSIBILITY NOTICE (FEB 2023)

PART IV - REPRESENTATIONS AND CERTIFICATIONS

4.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN

2025)(DEVIATION FEB 2025)

4.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND

VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

4.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

REPRESENTATION AND DISCLOSURES (DEC 2023)

4.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

4.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—

CERTIFICATION (NOV 2021)

PART V - GENERAL CONDITIONS

5.1 SUPPLEMENTAL INSURANCE REQUIREMENTS

5.2 MANDATORY WRITTEN DISCLOSURES

5.3 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION

SYSTEMS (NOV 2021)

5.4 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

PROHIBITION (DEC 2023)

5.5 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR

1984) ALTERNATE I (APR 1984)

5.6 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)

5.7 52.217-7 OPTION FOR INCREASED QUANTITY—SEPARATELY PRICED LINE ITEM

(MAR 1989)

5.8 52.219-3 NOTICE OF HUBZONE SET-ASIDE OF SOLE-SOURCE AWARD (Oct 2022) . 49

5.9 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)

5.10 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)

5.11 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN

2025)

5.12 52.223-21 FOAMS (MAY 2024)

5.13 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE

AGREEMENTS (NOV 2023)

5.14 52.236-4 PHYSICAL DATA (APR 1984)

5.15 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

5.16 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)

5.17 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

5.18 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB

2023)

5.19 VAAR 852.219-70 VA SMALL BUSINESS SUBCONTRACTING PLAN MINIMUM

REQUIREMENTS (JAN 2023) (DEVIATION)

5.20 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-

DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)

5.21 VAAR 852.219-74 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED VETERAN-

OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)

5.22 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION)

5.23 VAAR 852.222-71 COMPLIANCE WITH EXECUTIVE ORDER 13899. (DEVIATION)

(APR 2025)

5.24 VAAR 852.223-70 INSTRUCTIONS TO OFFERORS-SUSTAINABLE ACQUISITION

PLAN (SEP 2019)

5.25 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)

5.26 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)

5.27 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND

VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)

5.28 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS

(INCLUDING NAS– CPM) (NOV 2018)

5.29 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)

5.30 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR

2019)

5.31 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019) .. 89

5.32 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

5.33 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

ALTERNATE I (APR 2019)

5.34 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION

(OCT 2020)

5.35 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP

2019)

5.36 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)

5.37 VAAR 852.246-71 REJECTED GOODS (OCT 2018)

5.38 SPECIAL CLAUSES

PART VI - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS

S02 ATTACH Pre-Proposal Inquiry Form 36C10F25R0006 S02 ATTACH Past Performance Questionnaire 36C10F25R0006 S02 ATTACH Wage Determination St. Louis, MO. – Heavy and Highway S02 ATTACH Wage Determination St. Louis, MO. – Building

S02 ATTACH VAAR 852.219-75 CERTIFICATE OF COMPLIANCE

S02 ATTACH VA 852-042 - JBNC Phase 1 - Specifications Vol 1 S02 ATTACH VA 852-042 - JBNC Phase 1 - Specifications Vol 2 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 1 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 2 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 3 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 4 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 5 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 6 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 7 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 8 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 9 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 10 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 11 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 12 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 13 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 14 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 15 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 16 S02 ATTACH VA 852-042 - JBNC Phase 1 Drawings - Part 17

PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT AMOUNT

1.00 JB

General Construction:

Jefferson Barracks National Cemetery, Phase 1 Development, Project No.: 852-042

Work of the Contract includes general conditions, general construction, alterations, roads, walks, grading, drainage, mechanical and electrical work, utility systems, water storage facilities, necessary removal of existing structures and construction, and certain other items and all other work necessary to construct the project.

The POP for Line Item 0001 is 912 calendar days after the contractor receives the NTP. The ETO shall be completed and accepted by NCA for operation within 252 calendar days from

NTP.

Pre-Placed Crypts: Furnish and deliver to the site.

The POP for Line Item 0002 is 912 calendar days after the contractor receives the NTP.

Option #1: Install Maintenance Storage Yard and associated site work, including but not limited to pavements, curbs, drainage, fencing and gates, signage, landscaping, and irrigation.

Once the option is exercised, all option work must be completed within the 912 calendar days period of performance. The Option CLINS may be exercised within 180 calendar days after issuance of the base contract award.

Option #2: Install maintenance material storage building, including but not limited to site work, pavements, curbing, concrete foundations, concrete walls, structural steel, and standing seam metal roofing.

Once the option is exercised, all option work must be completed within the 912 calendar days period of performance. The Option

Option #3: Install Satellite Maintenance Building and associated site work including but not limited to site work, utilities, concrete foundations, concrete slab, engineered metal building, HVAC system, concrete masonry walls, metal wall panels, standing seam metal roof, doors, windows, interior finishes, landscaping, irrigation, signage, and all other work necessary to construct the building.

Once the option is exercised, all option work must be completed within the 912 calendar days period of performance. The Option

Option #4: Demolish and Replace Committal Shelter #4 (in the main cemetery) along with associate site work, concrete foundations, concrete piers, curbs, paving, standing seam metal roof, landscaping, irrigation, site furniture, and signage.

Once the option is exercised, all option work must be completed within the 912 calendar days period of performance. The Option

GRAND TOTAL ________________

NOTE: The Government intends to award a single contract for CLIN 0001- CLIN 0002 at the time of award. Due to the availability of funding, CLIN 0003 through CLIN 0006 are Options. Options may be awarded if funding is available at the time of award. If funding is unavailable at the time of the base contract award, the Option CLINS may be exercised within 180 calendar days after

PART I – GENERAL

STATEMENT OF WORK (SOW)

JEFFERSON BARRACKS NATIONAL CEMETERY,

SYLVAN SPRINGS, PHASE 1 DEVELOPMENT

Background

The National Cemetery Administration (NCA) is one of three Administrations within the U.S Department of Veterans Affairs (VA) that provide for the delivery of services and benefits to Veterans. NCA is responsible for providing cemetery services to Veterans and other eligible persons pursuant to the provisions of the National Cemeteries Act of 1973 and other statutory authority and regulations (38 U.S.C. 2306, 38 U.S.C. Chapter 24, 38 CFR Parts 38-39). NCA’s responsibilities include the operation and maintenance of 156 national cemeteries and the construction of new national cemeteries.

The National Cemetery Administration (NCA) is contracting this 33.6-acre cemetery expansion project to increase the burial capacity of Jefferson Barracks National Cemetery (JBNC) to serve veterans in the St. Louis area. The proposed development will provide continued service to an estimated Fiscal Year (FY) 2024 veteran population of approximately 208,000 within a 75-mile service area.

Project Goal

The purpose of this Phase 1 Expansion and Development project for Jefferson Barracks National Cemetery is to enable the existing national cemetery to continue to provide for an additional 15-year inventory of the more efficient casketed, double-depth, pre-placed crypts before depletion of the current inventory and extend the full range of burial options until FY 2045, as well as provide several nominal cemetery operational and infrastructure improvements within the older cemetery grounds.

Contract Requirements:

The solicitation includes the following CLINs:

• CLIN 0001: General Construction

• CLIN 0002: Pre-Placed Crypts

• CLIN 0003: Option #1

• CLIN 0004: Option #2

• CLIN 0005: Option #3

• CLIN 0006: Option #4

The Government intends to award a single contract for CLIN 001 - CLIN 002 at the time of award.

Due to the availability of funding, CLIN 0003 through CLIN 0006 are Options. Options may be awarded if funding is available at the time of the award. If funding is unavailable at the time of the base contract award, the Option CLINS may be exercised within 180 calendar days after issuance of the base contract award.

This investment will develop approximately 33.6 acres of undeveloped land to provide 36,511 gravesites, including both casket and cremation sites in new burial sections as follows:

1. Casketed remains:

a. 18,533 pre-placed crypt full casket gravesites

b. 2,124 traditional casket gravesites

2. Cremated remains:

a. 10,854 in-ground cremation

b. 5,000 columbarium niches

CLIN 0001 – Base Bid – General Construction:

The total performance period is 912 days from the Notice to Proceed. By the end of the performance period, all work shall be satisfactorily completed and ready for custody, transfer, and acceptance by NCA. All punch list items shall be satisfactorily addressed, all commissioning completed, and all training accomplished.

The Base Bid work of this contract includes phased requirements. These phases are referred to as Early Turnover (ETO) and Remainder of the work. The ETO shall be completed and accepted by NCA for operation within 252 calendar days from Notice to Proceed. Completion of the ETO work will follow procedures like those for final completion and acceptance, with the facilities within the ETO being completed and turned over to the Cemetery for use to begin operation of the Cemetery while the remaining work is completed. While the work of the ETO is being performed, work for the remainder of the project can also be performed.

Work of the Contract includes but is not limited to site demolition, general construction, relocation and installation of new site utilities, installation of pre-placed burial crypts, grading and utility stub outs for Satellite Maintenance building and yard, columbarium niches, gravesite locator building, replacement and upgrades to painted finishes and carpeting in the Administration/ Public Information Center (PIC) Building, replacement of electrical service panels in Buildings 3001,3002 and 3003, roadway improvements, new roads, walks, grading, drainage, fencing, site furnishings, landscaping and irrigation necessary removal of existing structures and construction and certain other items and all other work necessary to construct the project. By the end of the performance period, all work shall be satisfactorily completed and ready for custody, transfer, and acceptance by NCA. All punch list items shall be satisfactorily addressed, all commissioning completed, and all training accomplished.

In addition to the gravesite expansion, the following elements will be included in this project:

1. Access roads and parking to include:

a. New access roads and parking with curb and gutter

b. Cortege overflow staging lanes

2. Sheridan Road improvements

3. Demolition as depicted in design drawings.

4. Utility Relocation, as shown in design drawings.

5. Grading, utilities, drainage, irrigation, and landscaping

6. Temporary trailers to support VA staff and cemetery visitors during construction (for example, restroom trailer, office space, etc.)

7. Site furnishings (benches, trash receptacles), signage, and flower watering stations.

8. Install Entrance Gate and Signage.

9. Install chain-link fence and concrete mow strip of the entire Sylvan Springs perimeter.

10. Construct a Gravesite Locator (Kiosk) facility

11. Administration Building/PIC (existing cemetery)

c. Repaint the interior and replace the existing carpet.

12. Maintenance Complex (existing cemetery)

a. Bldg. 3001

i. Replace existing electrical panels.

ii. Install a new electrical generator.

b. Bldg. 3002

i. Replace existing electrical panels.

c. Bldg. 3003

i. Replace existing electrical panels.

13. Upgrade the physical security systems for the entire cemetery, including the administration building and maintenance complex, to meet the 1 October 2020 Physical Security and Resiliency Design Manual, revised 1 June 2023, including automatic security gates at the admin/maintenance complex.

14. Obtain state/local construction permitting as required.

15. Compliance with all erosion control measures per plans and specifications.

CLIN 0002 – Base Bid – Pre-Placed Crypts:

1. Casketed remains:

c. 18,533 pre-placed crypt full casket gravesites

d. 2,124 traditional casket gravesites

2. Cremated remains:

c. 10,854 in-ground cremation

d. 5,000 columbarium niches

Procure, manufacture, deliver, off-load, and store all pre-placed crypts; furnish and deliver them to the site.

Option Items Subject to Budget Adequacy:

CLIN 0003 – Option #1:

Install Maintenance Storage Yard and associated site work, including but not limited to pavements, curbs, drainage, fencing and gates, signage, landscaping, and irrigation.

CLIN 0004 – Option #2:

Install maintenance material storage building, including but not limited to site work, pavements, curbing, concrete foundations, concrete walls, structural steel, and standing seam metal roofing.

CLIN 0005 – Option #3:

Install Satellite Maintenance Building and associated site work including but not limited to site work, utilities, concrete foundations, concrete slab, engineered metal building, HVAC system, concrete masonry walls, metal wall panels, standing seam metal roof, doors, windows, interior finishes, landscaping, irrigation, signage, and all other work necessary to construct the building.

CLIN 0006 – Option #4:

Demolish and Replace Committal Shelter #4 (in the main cemetery) along with associate site work, concrete foundations, concrete piers, curbs, paving, standing seam metal roof, landscaping, irrigation, site furniture, and signage.

Period of Performance:

The total period of performance of this contract is not to exceed 912 calendar days after issuance of the Notice to Proceed (NTP). Note that if Option CLINs 0003 - 0006 are awarded, all Option work must be completed within the 912 calendar days period of performance. The Early Turnover (ETO) shall be completed and accepted by NCA for operation within 252 calendar days from Notice to Proceed. By the end of the performance period, all work shall be satisfactorily completed and ready for custody, transfer, and acceptance by NCA. All punch list items shall be satisfactorily addressed, all commissioning completed, and all training accomplished.

///END///

PART II – PROPOSAL INFORMATION

2.1 INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

a) Hard copies of bidding documents will not be provided. The solicitation, all bidding documents, subsequent solicitation amendments, award notification, and all other solicitation-related information will be posted to the website https://sam.gov/ (Contract Opportunities).

b) A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount by the time set for receipt of proposals will require rejection of the bid in all cases except those listed in FAR 28.101-4 and may be cause for rejection even then.

Offerors shall submit an original bid bond complete with original signatures, original notary stamps, & corporate seals. The BID BOND shall be included in the emailed proposal and emailed to the Contracting Officer, Jeffrey Gerbensky, at Jeffrey.Gerbensky@va.gov and Contract Specialist, Joshua Gibson, at Joshua.Gibson2@va.gov and the original bid bond mailed to ATTN: Jeffrey Gerbensky at the address in Block 8 of SF 1442 by the proposal due date and time.

c) The bidder to whom the award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

d) All bond transmittal envelopes or other packaging shall be clearly marked with the solicitation number, offeror(s) name, and return address.

e) To avoid delays, all bonds should be mailed using the fastest traceable means (i.e., FedEx, UPS, etc.).

https://sam.gov/ mailto:Jeffrey.Gerbensky@va.gov

2.2 INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

1. Request for Proposal

This is a Request for Proposal (RFP) in accordance with FAR Part 15. The award will be made to the offeror whose proposal represents the “best value” to the Government utilizing the Best Value Tradeoff process.

A responsibility determination will be made in accordance with FAR 9.1, Responsible Prospective Contractors. All proposals shall be subject to evaluation by a team of Government personnel.

In accordance with FAR 52.215-1, Instructions to Offeror-Competitive Acquisition, the Government intends to evaluate proposals and award a contract without discussions with offerors. Therefore, the offeror's initial proposal should contain the offeror’s best terms from a cost, price, and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them necessary.

If the Offeror communicates in its proposal any qualifications, exceptions, exclusions, or conditions to the proposed prices in the Offeror's proposal documents, the Contracting Officer may reject the proposal and exclude the Offeror from further consideration.

2. Gender

Whenever the feminine gender is used in this solicitation and contract documents, it shall be considered to include masculine.

3. Electronic Copies of Drawings

The government makes no guarantee of the accuracy of electronic copies of drawings.

4. System for Award Management (SAM)

Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. An award cannot be made until the contractor has registered. Offerors are encouraged to ensure that they are registered in SAM prior to submitting their proposal.

5. Availability of Solicitation Documents

All solicitation-related documents will be published to Contract Opportunities at https://sam.gov.

Amendments: Amendments to Solicitation No.36C10F25R006 will be posted at https://sam.gov. Paper copies of the amendments will NOT be individually mailed. By registering to the Receive Notification list at https://sam.gov, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Potential Offerors are advised that they are responsible for obtaining and acknowledging any amendments to the solicitation. Failure to acknowledge an amendment may result in your proposal being considered non-responsive.

6. Plan Holder’s List/Mailing List

For viewing a list of interested vendors (i.e., plan holders List) and receiving notifications or emails of changes regarding a solicitation, the U.S. General Services Administration has these features available (https://sam.gov/). For this solicitation, go to https://sam.gov/ and register as a vendor or enter your http://www.sam.gov/ https://sam.gov/ https://sam.gov/ https://sam.gov/ username and password to log in. If you wish for General Contractors, Subcontractors, Suppliers, Plan Rooms, or Print Shops to have the ability to contact you, click on "Add me to Interested Vendors" for the solicitation.

7. VETS 4212

Title 38, USC Section 4212(d), and Public Law 105-339 require that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS 4212 reporting information can be made electronically at https://www.dol.gov/agencies/vets/programs/vets4212. FAR 22.1303(c) states The Act requires submission of the VETS-4212 Report in all cases where the contractor or subcontractor has received an award of $150,000 or more, except for awards to State and local governments and foreign organizations where the workers are recruited outside of the United States.

8. Required registration with the Contractor Performance Assessment Reporting System

(CPARS)

(As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $750,000. Agency evaluations of contractor performance, including both negative and positive evaluations, prepared under this subpart shall be provided to the contractor as soon as practicable after completion of the evaluation. The contractor will receive a CPARS-system-generated notification when an evaluation is ready for comment. Contractors shall be afforded up to 14 calendar days from the date of notification of availability of the past performance evaluation to submit comments, rebutting statements, or additional information. Agencies shall provide for review at a level above the contracting officer to consider disagreements between the parties regarding the evaluation. The ultimate conclusion on the performance evaluation is a decision of the contracting agency.

Each contractor whose contract award is estimated to exceed $750,000 is required to register with the CPARS database at the following web address: Contractor Performance Assessment Reporting System (www.cpars.gov). Help in registering can be obtained by contacting CPARS Support E-mail (webptsmh@navy.mil) or by calling (207) 438-1690. Registration should occur no later than 30 calendar days after the contract award and must be kept current should there be any change to the contractor’s registered representative.

Failure to have a current registration with the CPARS database or to reassign the report to the VA contracting officer within those thirty days will result in the Government’s evaluation being placed on file in the database with a statement that the contractor failed to respond.

9. Pre-Proposal Conference & Jobsite Walkthrough

a) A pre-proposal conference and job site walkthrough is tentatively scheduled for Wednesday, September 10, 2025, at 10:00 AM Central Time (11:00 AM ET). The pre-proposal conference will commence with a brief presentation at Sylvan Springs Park, located at 300 Halsey St., Saint Louis, MO 63125, across the street from the Jefferson Barracks National Cemetery, followed by a job site walk-through.

b) In the event of inclement weather, the presentation will be conducted within the administration building at the Jefferson Barracks National Cemetery, situated at 2900 Sheridan Rd., Saint Louis, MO 63125.

https://www.dol.gov/agencies/vets/programs/vets4212 http://www.cpars.gov/ mailto:webptsmh@navy.mil

c) Attendance at the pre-proposal conference requires the offeror to comply with any applicable Federal laws, including requirements under the Privacy Act and the Paperwork Reduction Act, which may include providing information about their vaccination status. No questions will be answered at the site visit; all questions must be submitted in writing to the Contracting Officer at Jeffrey.Gerbensky@va.gov and the Contract Specialist at Joshua.Gibson2@va.gov.

d) For parties unable to attend the job site walkthrough in person, an amendment to this solicitation will be issued that contains a sign-in sheet for all people in attendance and any information shared by the government with those in attendance.

10. Pre-Proposal Inquiries & Requests for Information

All requests for information or clarification must be submitted via email to Jeffrey.Gerbensky@va.gov and Joshua.Gibson2@va.gov by Wednesday, September 17, 2025, at 12:00 PM Eastern Time (ET).

Email subject line shall include Jefferson Barracks National Cemetery Phase 1 Development RFP #:

36C10F25R0006.

The Government’s responses to RFI questions or comments will be posted to https://sam.gov/ under

RFP # 36C10F25R0006.

11. Proposal Due Date, Time & Place of Submission

The proposal due date is Monday, September 29, 2025, by 3:00 PM Eastern Time (ET), as prescribed in Box 13 of Standard Form 1442, and must be submitted via email to the Contracting Officer at Jeffrey.Gerbensky@va.gov and the Contract Specialist at Joshua.Gibson2@va.gov. In the subject line of any e-mail sent, identify “JBNC Phase 1 | 36C10F25R0006”. Late submissions will not be accepted.

NO FAX proposals will be accepted. All submitted materials will become the property of the Government and will not be returned. Regardless of the manner you choose to deliver your package, it is the Offeror’s responsibility to make sure it is received before the submission deadline.

12. Liquidated Damages

In accordance with Federal Acquisition Regulation 36.206, liquidated damages will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date. See Section 4, FAR Clause 52.211-12 Liquidate Damages – Construction (SEPT 2000).

If the Contractor fails to complete each separate part or stage of the work within the time specified in the contract for that part or stage, or any extension, the Contractor shall pay to the Government as liquidated damages the following amounts:

PART OR STAGE OF THE WORK LIQUIDATED DAMAGES FOR EACH DAY

OF DELAY

Early Turn Over (ETO) Phase [252 calendar days after NTP]

Actual Damages Incurred

Post-ETO Phase [912 calendar days after

NTP]

$2,248.00 mailto:Jeffrey.Gerbensky@va.gov mailto:Joshua.Gibson2@va.gov https://sam.gov/

13. Subcontracting Plan

a. Small Business Subcontracting Plan. Each large business offeror shall provide a Small Business

Subcontracting Plan that contains all of the elements required by FAR 52.219-9. If the large business does not have an approved Master Plan or approved Commercial Plan, then an Individual Subcontracting Plan must be submitted that includes an assurance that small businesses will be given the maximum practicable opportunity to participate in contract performance. The Subcontracting Plan is not a requirement for evaluation in source selection but rather a requirement for award to a large business, and the plan, as negotiated, will be incorporated into any resultant contract. Upon request by the CO, the apparent successful offeror (if a large business) shall submit and negotiate a subcontracting plan.

b. The subcontracting plan must address all requirements defined in FAR 19.704, Subcontracting plan requirements, including proposed subcontracting to SDVOSBs or VOSBs. The 2024 VA subcontracting goals listed below are based on total procurement dollars expended and are the suggested minimum goals for VA-administered subcontracting plans.

Small Business 17.5% Veteran-Owned Small Business 7.0% Service-Disabled Veteran-Owned Small Business

5.0%

Small Disadvantaged Businesses (includes Section 8(a))

5.0%

Woman-Owned Small Business 5.0% Historically Underutilized Business (HUB) Zone Small Business

3.0%

2.3 SOLICITATION NOTICE OF TIERED SET-ASIDE EVALUATIONS

This procurement is set aside based on an order of priority as established in 38 U.S.C. 8127. To help determine the eligibility of Prime contractors to participate in this solicitation, the Government will use the Small Business Administration (SBA) small business size standard associated with the NAICS code applicable to this solicitation – see below:

• NAICS Code is 237990

• SBA Small Business Size Standard is $45 M.

(a) Tiered evaluations, including large business concerns. Offerors are advised that proposals will be grouped by the socioeconomic category based on the business size of the offeror that submits the proposal, and that each proposal will only be evaluated once. Evaluation will occur in the highest tier for which the requirement is met. For example, a VOSB concern will only be evaluated in tier 2, and a small business concern will only be evaluated in tier 3. The tier chart is as follows:

Tier Socio-economic Group Tier 1 SDVOSB Tier 2 VOSB Tier 3 Small Business (HUBZone and 8(a) having priority) Tier 4 Large Business

(b) The Government reserves the right to use any of the techniques outlined in FAR 15.404-1 to ensure award at a fair and reasonable price.

In accordance with 38 U.S.C. § 8127(h), the Contracting Officer will evaluate proposals received in response to this solicitation in the following order of priority:

(1) Tier 1 Offers, if any, submitted by SDVOSB concerns. If no offers were submitted by SDVOSB concerns, or if no offers would result in an award at a fair and reasonable price that offers the best value to the United States, withdraw the SDVOSB set-aside, document the basis for not making an award within this tier, and proceed to the set-aside for VOSB concerns.

(2) Tier 2 Offers, if any, submitted by VOSB concerns. If no offers were submitted by VOSB concerns, or if no offers would result in an award at a fair and reasonable price that offers the best value to the United States, withdraw the VOSB set-aside, document the basis for not making an award within this tier, and proceed to the set-aside for small business concerns, with Historically Underutilized Business (HUB) Zone small business concerns and 8(a) participants having priority.

(3) Tier 3 Offers, if any, submitted by Small Business concerns. If no offers were submitted by

Small Business concerns, or if no offers would result in an award at a fair and reasonable price that offers best value to the United States, withdraw the Small Business concerns set-aside, document the basis for not making an award within this tier, and proceed to the Large business concerns

(4) Tier 4 Offers, if any, submitted by Large Business concerns. If no offers were submitted by large business concerns, or if none of the offers would result in an award at a fair and reasonable price that offers the best value to the United States, cancel the solicitation, document that cancellation in a memorandum for the record, and conduct additional market research to inform a follow-on acquisition strategy.

The following clauses apply to the associated tiers:

• 52.219-3 only applies to tier 3

• 52.219-6 only applies to tier 3

• 52.219-9 only applies to tier 4

• 52.219-14 only applies to tier 3

• 52.219-16 only applies to tier 4

• 52.236-1 only applies to tier 4

• 52.242-5 only applies to tier 4

• 852.219-70 only applies to tier 4

• 852.219-73 only applies to tier 1

• 852.219-74 only applies to tier 2

• 852.219-75 only applies to tiers 1 and 2

• 852.236-72 only applies to tier 4

2.4 OFFEROR SUBMISSION INSTRUCTIONS

Submitted proposals that do not adhere to the following instructions may be deemed unacceptable and ineligible for an award:

Proposals will be submitted electronically in two separate volumes.

i. Volume I – Technical Proposal: This volume/file shall be the Technical Proposal and shall include the offeror’s responses for Factors 1, 2, and 3 (including sub-factors). Maximum Page

Limit for Technical Proposal: No more than 75 pages; page limit excludes CPARS reports.

Volume I – Technical Proposal Format

Tab Description

Title Page See Method of Submission, item b., below.

Factor 1 – Relevant Experience

Sub-factor 1.1 – Project Experience

Sub-factor 1.2 – Project Organizational Chart and Key Personnel

Factor 2 – Construction/Project Management

Sub-factor 2.1 – Technical Approach

Sub-factor 2.2 – Capacity to Perform Work

Sub-factor 2.3 – Schedule

Factor 3 – Past Performance

Additional Information: Provide the Offeror's core team members if a Joint Venture (JV) is used, including Prime General Contractor, Joint Venture teaming partner, and/or mentor-protégé partner.

The offeror shall provide DUNS/UEI (Unique Entity Identifier) numbers for itself and each of the Offeror's core team members (Prime General Contractor, Joint Venture, teaming partner, and/or mentor-protégé partner). The JV must be registered in the Center for Verification and Evaluation (CVE) as a Service-Disabled Veteran-Owned Small Business (SDVOSB).

ii. Volume II – Non-Technical Proposal: This volume/file shall be the Price Proposal and shall include the offeror’s responses for Factor 4. Maximum Page Limit for Price Proposal: No more than 30 pages.

Volume II – Price Proposal Format

Tab Description Title Page See Method of Submission, item b., below.

Tab 1 • Executed Solicitation, Offer and Award Form (SF-1442).

Offeror shall complete Blocks 14-20C.

• Signed acknowledgment of all solicitation amendments.

• Completed PRICE/COST SCHEDULE, including pricing for

ALL CLINs (page 6 of solicitation).

Tab 2 Scanned, legible copy of Executed Bid Guarantee (SF-24) Tab 3 Completed VAAR 852.219-75 VA Notice of Limitations on

Subcontracting—Certificate of Compliance.

Tab 4 Printed copy “Representations and Certifications” as submitted on https://www.sam.gov/portal/public/SAM

NOTE: Cover pages, title pages, index pages, PPQs, and CPARS Reports do not count towards page limitations. The Government will not review any information that exceeds the page limitation, including attachments, enclosures, charts, etc.

Method of Submission:

• The proposal must be submitted via email only. Adobe PDF is the only file format that will be accepted.

• The emailed proposal shall be sent to Jeffrey Gerbensky, Contracting Officer, at Jeffrey.Gerbensky@va.gov, and Joshua Gibson, Contract Specialist, at https://www.sam.gov/portal/public/SAM

Joshua.Gibson2@va.gov, and must be received by the due date and time specified in the solicitation.

• Emailed files must be no larger than 40MB each. If the file size exceeds 40MB, separate the document into multiple files and label them logically and sequentially (for example, Volume I - Part 1, Volume I - Part 2, etc.).

NOTE: While 40MB is the maximum message size, factors such as encryption can add overhead to a message, increasing its size. Therefore, there may be times when a message needs to be under 40MB to be sent successfully, taking into account this overhead. Also, ensure no special characters (#@$!&^*+) or slashes (/, \) in the document title.

• Offerors shall email the following documents to the Contracting Officer and Contract Specialist by the due date and time shown in Box 13a of the solicitation form SF-1442 (or, if applicable, as subsequently amended).

a. One (1) copy of their Volume I – Technical Proposal (for example, Volume I - Part 1, Volume I - Part 2, etc.) and one (1) copy of their Volume II – Price Proposal.

i. The first page of the proposal shall include the information identified in provision FAR

52.215-1 paragraph (c)(2). Paragraph (c)(2)(iii) is modified to read “A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation.” This statement should be placed on the first page of Volumes I and II with the contact information.

ii. The proposal shall not exceed the number of pages identified for each section/factor.

A page is considered to be the PDF file equivalent of one side of an 8 1/2” x 11” sheet of paper. Proposals shall contain all applicable information as required by the evaluation factors.

b. Each proposal Volume shall include a title page that contains the following information:

i. Solicitation Number,

ii. Solicitation Title,

iii. Contractor Name, address, email, SAM UEI, and DUNS

iv. Contractor Authorized Representative information

v. Volume Number (I or II)

vi. Volume Title (Technical Proposal or Price Proposal)

vii. Index of the sections contained in the proposal volume

c. Volume 1 – Technical Proposal shall include the following additional information.

i. Provide the Offeror's core team members if a Joint Venture (JV) is used, including

Prime General Contractor, Joint Venture teaming partner, and/or mentor-protégé partner. The offeror shall provide DUNS/UEI (Unique Entity Identifier) numbers for itself and each of the Offeror's core team members (Prime General Contractor, Joint Venture, teaming partner, and/or mentor-protégé partner). The JV must be registered in the Center for Verification and Evaluation (CVE) as a Service- Disabled Veteran-Owned Small Business (SDVOSB).

d. Volume 2 – Price Proposal shall include the following additional information.

i. Bid Guarantee (Bond): Please provide a scanned, legible copy of the Executed Bid

Guarantee (SF-24). Before scanning the bond, shade any raised seals with pencil lead to enhance their legibility, and email it to the Contracting Officer.

The executed Bid Guarantee (on form SF-24) original hard copy must be mailed to the address below and received by the Contracting Officer within five (5) business days of the proposal due date and time shown in Box 13a of solicitation form SF- 1442 (or applicable, as subsequently amended):

Office of Construction and Facilities Management (003C4B) 425 I Street NW Washington, DC 20001 Attn: Contracting Officer, Jeffrey Gerbensky

ii. Provide executed solicitation offer and Award (SF-1442). The offeror shall complete Blocks 14 to 20c.

iii. Provide a signed acknowledgment copy of all solicitation amendments (if applicable).

iv. Provide a printed copy of the offeror's “Representations and Certifications” as submitted on www.sam.gov.

v. Provide complete VAAR 852.219-75 VA Notice of Limitations on Subcontracting— Certificate of Compliance attachment.

NOTE: Late or incomplete proposals may be considered nonresponsive.

2.4.1 Volume I – Technical Proposal

Volume I – Technical Proposal

Technical Factors Factor 1 – Relevant Experience

Sub-factor 1.1 – Project Experience Sub-factor 1.2 – Project Organizational Chart and Key Personnel

Factor 2 – Construction/Project Management Sub-factor 2.1 – Technical Approach Sub-factor 2.2 – Capacity to Perform Work Sub-factor 2.3 – Schedule

Factor 3 – Past Performance Factor 1 – Relevant Experience

Sub-Factor 1.1 – Project Experience

The offeror shall provide a detailed summary of three (3) recent and relevant projects. The summary of each project must include the following information:

• Provide the project name & title, project location/address, contract number, contract total amount, and contract period of performance, point of contact (POC), email address, and current phone number.

• Provide the original project pricing, period of performance schedule, and detailed description of the project. Identify any changes/modifications experienced during the project period of performance and include a description of any potential impacts that price and/or schedule may have on each other related to completion of the project.

• Provide a detailed description of the project team (including major partners and/or subcontractors) involved in the performance of the project and explain each firm’s role on the project.

• Describe how sustainable design principles were incorporated into the project; indicate to what extent environmental program goals (e.g., Energy Star, Leadership in Energy, and Environmental Design) were achieved and how those achievements were recorded in the final documentation.

http://www.sam.gov/

• Describe the project’s safety record (i.e., number of lost time accidents/days).

Sub-factor 1.2 – Project Organizational Chart and Key Personnel

The offeror shall provide an organizational structure, including the organizational chart and supporting narrative description of the offeror’s key personnel and any major subcontractor(s) and their key personnel assigned to the performance of this project. Clearly describe the offeror’s responsibilities and provide any major subcontractor(s) roles and responsibilities, providing the following: 1) crypt and placement supplier, 2) columbarium niche supplier, 3) earthwork, 4) masonry, 5) irrigation system installer, and 6) columbarium cap stone supplier.

Additionally, the offeror shall provide the resumes for each key person identified below as assigned to the performance of this project. The resume of the key personnel must identify the years the person occupied the position, qualifications, and applicable certificates (including OSHA 30-hour Construction Safety) for each position, as follows:

a. Project Manager – Minimum Qualifications:

• Ten (10) years of experience leading on-site construction projects considered somewhat relevant, relevant, or very relevant, as defined in this solicitation.

• Bachelor’s degree in engineering, Construction, Architecture, or Landscape Architecture.

• Show evidence that the candidate meets Health & Safety qualifications as stated in specifications for key personnel (see Specification 01 35 26) at the time of submission of an offer.

b…

This is the start of the file's text. The full file is on GovTribe.