VHA NRM Project Application Summary
This is a Veterans Health Administration (VHA) National Real Estate Management (NRM) project application for capital asset renovation at the Danville VA Medical Center (VISN 12, Station 550). Project 550-25-108 involves renovating bathrooms in Building 103 (rooms 107B, 107C, 136C, 159C) and restrooms 6/7 in Building 72, totaling approximately 2,177 square feet of renovated space. The project is categorized as addressing Architectural Barriers and corrects Facility Condition Assessment (FCA) deficiencies (primary deficiency #306162 with a condition grade of D), with 40 percent of total project costs dedicated to correcting FCA issues. The project has received VISN-level funding approval and is scheduled with a design obligation date of December 15, 2024 (FY2025) and a construction obligation date of December 15, 2025 (FY2026).
The total project cost is $584,146, comprising design costs of $92,868 (18.90 percent) and construction costs of $491,278. Design will be completed by an Architect/Engineer under the FY2025 Operating Plan, and construction will be executed by contract under the FY2026 Operating Plan. Scope improvements include installation of grab bars, mounted mirrors, accessible lockers, roll-in showers, updated bathroom signage, required turning clearances, door swing modifications, pipe sleeve insulation, accessible locker identification, benches, and replacement of toilet exhaust fans, all per VA accessibility guidelines and standards. An independent fire code review is required for this project. No documentation was submitted with the application.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VHA NRM Project Applications Capital Assets
Print Close
NRM Project Application for VISN 12 - 550 Danville
Project Update History
Original Entry Date/Time: 6/21/2024 8:29:38 AM
Last Modified Date/Time: 9/6/2024 9:50:36 AM
Modified By: VHA12\VHAMIWKormaD
General Data Section
Project Number: 550-25-108 SCIP Project Number:
Project Title: Renovate Bathrooms B103 PRRTP & B64/72 Approval Level: VISN Funding Approved
Mental Health Project? No
Station-Level Funded Project? No
Project in Leased Space? No
Budget Category: FY2025 Operating Plan
Project Category: Architectural Barriers
Design Method: Architect/Engineer - FY2025 Operating Plan
Construction Method: Contract - FY2026 Operating Plan Army Corps of Engineers Contracting or Project Management?
(Additional Army Corps of Engineers fields will only be shown if Yes.) No
Is an independent fire code review required? Yes
Planned Obligation Data Section
Design Obligation Date: 12/15/2024 (FY 2025)
Construction Obligation Date: 12/15/2025 (FY 2026)
Special Categories Data Section
Special categories may appear here based on the Fiscal Year of Design/Construction Obligation Date.
FCA Data Section
Does this Project Correct FCA Deficiency?
(Additional FCA fields will be shown only if Yes.) Yes
FCA Condition Grade: D
% Total Project Cost Related to Correcting FCA Deficiencies: 40 %
FCA Primary System: Access
Primary FCA Deficiency Individual Rec #: 306162
Construction Cost Data Section
Construction $: $491,278
Design $: $92,868 Design %: [Calculated] 18.90 % Total Project Cost: [Calculated] $584,146
Other New Building GSF Project Costs: $0
Other New Building GSF: 0
New Utility Building GSF Project Costs: $0
New Utility Building GSF: 0
Renovated GSF Project Costs: $584,146
Total Renovated GSF: 2,177 Total Building Demolition Project Costs:
Total Building Demolition GSF:
Energy Data Section
Does Project Result in Energy or Water Savings?
(Additional Energy fields will be shown only if Yes.) No
Scope Justification Section
Description (Scope of Work):
This project includes renovating Building 103 bathrooms 107B, 107c, 136c, 159c, and restrooms 6/7 in building 72. The total amount of renovated space is approximately 2,177 sq. ft.
Justification:
This project will correct the following FCA deficiencies, 306162, 42239, and 27984. In building 103, grab bars, mounted mirrors, accessories, required turning clearances, door swing, and pipe sleeve insulation will be renovated per accessibility guidelines/ standards. Bathroom signage will be updated as well. In building 72, this project will provide accessible lockers and turning clearances, in addition to, benches and accessible locker identification for administration areas. Roll in showers will be installed per VA accessibility guidelines. Toilet exhaust fans will be removed and replaced.
Documentation Section
No documentation was returned.