This document is a Questions and Answers (Q&A) file for a Natural Resources Conservation Service (NRCS) solicitation for ACEP-WRE Emergent Wetland Seeding in Clark County, Illinois, with solicitation number 12FPC125Q0056. The Q&A covers key project details including contractor responsibilities for seeding, site preparation, and quality control. Hydroseeding is acceptable, and most sites can be seeded with a no-till drill, though site accessibility may depend on water levels and weather conditions. The contractor will be responsible for determining site preparation methods, and while fertilizer and mulching are not expected, alternative or replacement seed species may be necessary as determined by the Contracting Officer (CO). NRCS will conduct site-specific inspections, and weather has been factored into the period of performance, with potential modifications for extreme weather events.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question # Answer

1 New Contract

2 N/A

3 See section (viii) of Combined Synopsis/Solicitation.

4 The contractor.

5 The scope of work is detailed in Attachment A - Specifications of the Combined Synopsis/Solicitation.

6 Contractor will need to determine best method of site preparation and seeding. Hydroseeding is acceptable.

7 NRCS

8 See question #3

9 Fertilizer is NOT expected.

10 Mulching is NOT expected.

11 See seeding list.

12 Alternative or replacement seed or species maybe necessary as determined by CO.

QC will be required by the contractor. NRCS inspections on a site by site basis will occur. If a site has been determined as planted per the specifications it will be considered complete. Weather has been factored into the period of performance. If extreme weather events occur any modifications to the period of performance will be made by the CO.

Yes, most sites would be accessible to seed with a no till drill (some sites will be dependent on water levels/weather).

15 Erosion control is not needed.It mentions erosion control, but no specifications?

What is the required grass type to be planted?

Will there be a contingent plan or alternative grass type for this scope if Prairie Cord Grass as shown to be used from the list provided is not available?

How will NRCS determine replant and or quality control in the event of inclement weather during work in progress?

Is there a Scope of Work (SOW/PWS)?

Will this scope of work require Hydroseeding or conventional tillage with mechanical seeding?

Who is responsible for landowner notification prior to property access?

What is the expected start and completion date?

What is the expectation of fertilizer and or not needed?

What is the expectation and form of straw or mulch overlay for seed protection and germination or not needed?

Can all these fields be seeded with a notill drill?

Are the seeds provided by the contractor or the government?

Natural Resources Conservation Service (NRCS)

ACEP-WRE Emergent Wetland Seeding

Illinois State Office

Solicitation No. 12FPC125Q0056

Clark County Question/Comment/Clarification

Is this a brand new contract OR is (was) an incumbent performing these services?

If there is an incumbent, could you please provide the current / previous contract number?

What is the performance period?