This statement of work outlines wetland restoration services required by the Natural Resources Conservation Service on the Leisure property in Pennsylvania. The contractor will implement conservation practices including critical area seeding, wildlife habitat planting, tree and shrub establishment, wetland enhancement, and wetland restoration to improve degraded wetlands and habitat. Specific deliverables include constructing shallow potholes and swales per the design drawings, installing erosion controls, seeding, and establishing trees and shrubs. The contractor must complete the work by May 1, 2024 and provide maintenance for the next two growing seasons. The related federal contract opportunity was issued by the Department of Agriculture for the Leisure Property Wetland Restoration project in Lebanon County, Pennsylvania.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
WETLAND RESTORATION SERVICES
NATURAL RESOURCES CONSERVATION SERVICE (NRCS)
I. OBJECTIVE
The objective of this contract is to obtain services in the Commonwealth of Pennsylvania (PA) for implementation of the Wetland Restoration project on the Leisure property to enhance degraded wetlands and improve habitat for wetland dependent wildlife.
Landowner details are listed below:
Randy Leisure
1689 PA-934
Annville, PA 17003
Please see Attachment 4 - Location Map.
II. BACKGROUND
The United States Department of Agriculture (USDA) NRCS has authority to administer voluntary conservation easement programs. Depending on the program, NRCS is authorized to acquire easement rights from participating landowners to achieve program purposes such as restoring and protecting wetlands, grasslands, and forest land resources, restoring and enhancing floodplains, and maintaining and improving habitat for at-risk plants and animals. NRCS is the lead agency within the United States Department of Agriculture charged with administering these programs.
III. SCOPE OF WORK
The purpose of implementing the (342) Critical Area Seeding, (420) Wildlife Habitat Planting, (620) Tree/Shrub Establishment, (659) Wetland Enhancement and (657) Wetland Restoration conservation practices are to:
• Improve the degraded wetland functions,
• Enhance plant communities, animal habitats, especially for waterfowl, wading and shore birds, neotropical migrants, reptiles and amphibians and other wetland dependent wildlife
• Restore wetland hydrology
• Seed disturbed areas associated with the wetland enhancement.
Please see Attachment 6 for Conservation Plan and associated Job Sheets.
The proposed project includes the creation of potholes and performing tile search (Wetland Restoration, 657), seeding and mulching (Critical Area Seeding, 342 & Wildlife Habitat Planting, 420), and tree and shrub planting (Tree/Shrub Establishment, 612):
1. Randy Leisure Property (Tract 12938)
a. Install E&S controls as per details specified on the Construction Drawings (attachment 3) and
Construction Specification 8 (attachment 2)
b. Mow and apply herbicide treatment to work site, as per a Conservation Pan Job Sheet PA 315, prior to excavation activities.
c. Perform tile search in the vicinity of the planned potholes, per drawings. Any existing tile lines identified will be blocked or extended to a constructed pothole per the Construction Specifications and Drawing (attachment 2&3). Block tile drains in accordance with the plan set and guidance from inspector.
d. Strip topsoil and stockpile within the limits of the Spoil Area(s).
e. Begin construction of potholes, swales and berms (See attachment 3 – Construction Drawings) on the landscape in accordance with the plans.
f. Begin to fill the existing diversion swale, on the North Field, and install R-4 rip-rap as shown on the plan.
g. Install plantings per plans, restore wetlands and improve wildlife habitat. Note: standing water in the potholes may be ephemeral and not persist through the growing season.
h. After applying topsoil and achieving final grade; all disturbed areas shall be seeded and stabilized as per the Construction Specifications (attachment 2).
i. Conservation Cover (seeding) shall by applied to as described in the Construction Specification
6 (attachment 2) and Conservation Plan Job Sheets PA327 (attachment 5).
j. Trees and Shrubs shall be established as per Construction Specification 6 (attachment 2) and
Conservation Plan Job Sheets PA612 (attachment 5)
k. A maintenance plan consisting of mowing, weed whacking, and tree herbicide treatments shall be completed to control weeds and help with the establishment of the permanent grasses, trees, and shrubs. Refer to as Construction Specification 6 (attachment 2) for timing and outline of maintenance to be performed.
IV. DELIVERABLES
The Contractor shall follow the statement of work and applicable regulations to provide Wetland Restoration services for the associated property. The primary task for this Statement of Work is completion of the (657) Wetland Restoration, (420) Wildlife Habitat Plant, and (612) Tree/Shrub Planting. In order to accomplish this objective, the Contractor will follow the NRCS approved design to construct the shallow potholes as shown on the construction drawings (See attachment 3 – Construction Drawings). Temporary erosion and sedimentation controls will be installed prior to construction and permanent seeding will be completed after construction.
Attachments included in this design package:
• Attachment 1 – Statement of Work (SOW)
• Attachment 2 - Construction Specifications (CS)
a. CS 5 – Pollution Control
b. CS 6 – Seeding Sprigging and Mulching
c. CS 8 – Mobilization and Demobilization
d. CS 21 – Excavation
e. CS 26 – Top Soiling
f. CS 45 – Plastic Pipe
g. CS 61 – Rock Riprap
• Attachment 3 - Construction Drawings
a. See Cover Sheet for Drawing Index
• Attachment 4 – Davis-Bacon Act WD PA20230006
• Attachment 5 - Conservation Plan Job Sheets
a. Job Sheet PA 315 – Herbaceous Weed Treatment
b. Job Sheet PA 420a – Wildlife Habitat Planting, Wet Site Mix
c. Job Sheet PA 420b – Wildlife Habitat Planting, Upland Mix
d. Job Sheet PA 420c – Wildlife Habitat Planting, Wetland Mix
e. Job Sheet PA 490 – Tree and Shrub Site Preparation
f. Job Sheet PA 612a – Shrub Establishment
g. Job Sheet PA 612b – Tree Establishment
Details on the proposed project are included in the NRCS approved construction drawings and specifications package. Upon completion of the practices, the site will meet the current NRCS hydrology, soils and vegetative criteria for a wetland.
The Contractor is responsible for having current knowledge of requirements of Pennsylvania State law associated with the services being solicited.
A Pre-Construction meeting will be held onsite by NRCS prior to the bid submittal date that the contractor, or a representative of the contractor, may attend. Questions and answers during the visit will be recorded and posted for all in, and not, in attendance.
NRCS will complete construction stakeout of the proposed potholes prior to construction. The contractor is responsible to conduct onsite surveys and check grades to ensure their work meets the requirements in the construction drawings and specifications.
NRCS will inspect the installation of the practices during construction. It is understood that the inspections will take place regularly and at critical times during construction. The Contractor will effectively communicate to the appropriate NRCS Field Office the status of the project, beginning when first on site and through completion. Upon completion of each pothole (with topsoil replaced) the NRCS inspector will perform an as-built survey to determine the final volume of excavation performed for each pothole. The as-built surface will be compared to the original ground surface to verify that the potholes are built to the dimension noted in the design prior to payment. The contractor is advised to perform and submit their own calculated excavation quantity for review by the COR.
The Contractor will conduct a final “check-out and walk- through” of the installed practices with an NRCS representative(s) before equipment is demobilized. The contractor is required to sign a certification of conformance stating that the work was installed as per the approved design.
A Contractor Maintenance Plan is included for the following two full growing seasons after the permanent seeding and tree & shrub planting are complete. Maintenance tasks for the growing season directly after the grasses and tree/shrubs are planted is to be considered in the planting bid item. The maintenance bid items are considered full growing seasons after initial planting. i.e. assume fields are seeded winter 2023/2024 and Trees & Shrubs are planted March/April 2024; maintenance tasks for the 2024 growing season would be considered in the seeding/planting bid item. Growing seasons 2025 and 2026 would be considered the additional maintenance years and are separate bid items. This is outlined in the Construction Specifications (attachment 2) and in the Conservation Plan Job Sheets (attachment 5).
V. PERMITS
All federal, state and local requirements will be addressed prior to installation of the conservation practices.
PERFORMANCE TIMELINE:
Within the easement, construction of potholes, temporary erosion and sedimentation controls, temporary & permanent seeding, and establishment of trees & shrubs associated with the wetland enhancement by May 1, 2024.
Tree and shrub planting must take place in the spring (March -April) of 2024. Other tasks, besides maintenance, shall be completed in advance of these plantings. Year 1 of maintenance will be considered the 2024 growing season. The 2025 (year 2) and 2026 (year 3) growing seasons will be additional maintenance years. Year 2 and year 3 maintenance years are a separate bid items.
VI. CIVIL RIGHTS, PRIVACY OF INFORMATION AND PROGRAM DELIVERY
By signing this contract, the Contractor assures the USDA that the program or activities provided for under this agreement will be conducted in compliance with all applicable Federal civil rights laws, rules, regulations, and policies. Any and all information gained through this Statement of Work or in the process of carrying out the Wetland Restoration project are to be held confidential between the Contractor, NRCS, other designated partners and the landowner unless released by the landowner. Information gained may not be shared with others and are considered private to the landowner. The Contractor will protect the privacy of information collected during the technical assistance process according to the provisions of Section 1619 of the Food, Conservation and Energy Act of 2008.
VII. CONTRACTING OFFICER (CO)
The designated Contracting Agency for this Statement of Work is NRCS. All administrative matters regarding this Statement of Work shall be directed to the Contracting Specialist:
Amber Maestri, Contract Specialist USDA, Panama City FL
Phone: 850-614-3022 Email: amber.maestri@usda.gov
Only the CO may authorize changes to this Statement of Work.
VIII. CONTRACTING OFFICER’S REPRESENTATIVE (COR)
The designated COR for this Statement of Work is Mark Buckwalter. All deliverables and technical matters regarding the work involved in this Statement of Work shall be directed to the COR at the following address:
Mark Buckwalter, Civil Engineer USDA NRCS, Harrisburg State office
Office Phone: 717-237-2245 Cell Phone: 717-239-9253 Email: mark.buckwalter@usda.gov
| II. BACKGROUND |
| III. SCOPE OF WORK |
| IV. DELIVERABLES |
| Attachments included in this design package: |
| Attachment 1 – Statement of Work (SOW) |
| Attachment 2 - Construction Specifications (CS) |
| a. CS 5 – Pollution Control |
| b. CS 6 – Seeding Sprigging and Mulching |
| c. CS 8 – Mobilization and Demobilization |
| d. CS 21 – Excavation |
| e. CS 26 – Top Soiling |
| f. CS 45 – Plastic Pipe |
| g. CS 61 – Rock Riprap |
| Attachment 3 - Construction Drawings |
| a. See Cover Sheet for Drawing Index |
| Attachment 4 – Davis-Bacon Act WD PA20230006 |
| Attachment 5 - Conservation Plan Job Sheets |
| a. Job Sheet PA 315 – Herbaceous Weed Treatment |
| b. Job Sheet PA 420a – Wildlife Habitat Planting, Wet Site Mix |
| c. Job Sheet PA 420b – Wildlife Habitat Planting, Upland Mix |
| d. Job Sheet PA 420c – Wildlife Habitat Planting, Wetland Mix |
| e. Job Sheet PA 490 – Tree and Shrub Site Preparation |
| f. Job Sheet PA 612a – Shrub Establishment |
| g. Job Sheet PA 612b – Tree Establishment |
| V. PERMITS |
| PERFORMANCE TIMELINE: |
| VI. CIVIL RIGHTS, PRIVACY OF INFORMATION AND PROGRAM DELIVERY |
| VII. CONTRACTING OFFICER (CO) |
| Only the CO may authorize changes to this Statement of Work. |