This document is a Request for Proposal (RFP) issued by the Office of State Procurement (OSP) of the Arkansas Department of Transformation and Shared Services (TSS) for the Arkansas Economic Development Commission (AEDC) to obtain services for an International Office in Korea. The objective is to attract more Korean businesses to Arkansas, leading to job creation and capital investment, particularly in the state's targeted industries such as advanced manufacturing, agtech, professional services, IT, life sciences, and logistics.

The RFP outlines the minimum qualifications for prospective contractors, which include at least 5 years of experience providing similar services to another U.S. state in Korea, fluency in English and Korean, and knowledge of corporate site selection and foreign direct investment. The contractor will be required to maintain an office in Seoul, provide monthly and quarterly reports, and plan and support high-level trade missions. The initial contract term is 4 years, with options to renew for up to 3 additional 1-year terms. Pricing must be proposed in U.S. dollars, and the state may order more or less than the estimated quantities. The state will evaluate proposals based on technical factors and cost, with the possibility of discussions with the highest-ranked offeror(s) prior to award.

View the file

Other files

File Type Posted
S000000338 Q & A.pdf PDF
S000000338 Sample Services Contract.pdf PDF
S000000338 Technical Proposal Packet~1.docx DOCX document
S000000338 Official Solicitation Price Sheet.xlsx XLSX spreadsheet
S000000338 Contract and Grant Disclosure.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF ARKANSAS

DEPARTMENT OF TRANSFORMATION AND SHARED SERVICES

OFFICE OF STATE PROCUREMENT

501 Woodlane St., Ste. 220

Little Rock, Arkansas 72201-1023

REQUEST FOR PROPOSAL

SOLICITATION DOCUMENT

SOLICITATION INFORMATION

Solicitation Number: S000000338 Solicitation Issued: July 18, 2024

Description: International Office

Department: Arkansas Economic Development Commission

SUBMISSION DEADLINE AND DELIVERY OF RESPONSE DOCUMENTS

Proposal Opening Date: August 5, 2024 Proposal Opening Time: 2:00 PM, Central Time

Proposal submissions for this Request for Proposal must be submitted through ARBuy, the State’s eProcurement system. It can be accessed at arbuy.arkansas.gov. Proposals received after the submission deadline may be rejected as untimely.

LIVE PROPOSAL OPENING INFORMATION

Teams Meeting Link: Join the meeting now

Meeting ID: Meeting ID: 221 187 120 497

Passcode: Passcode: ywY5Lk

Call in (audio only): 501.244.3310 or find a local number

TSS OFFICE OF STATE PROCUREMENT CONTACT INFORMATION

TSS OSP Procurement Specialist:

Tiffany Maddox Procurement Specialist’s Direct Phone Number:

501-324-9320

Email Address: Tiffany.Maddox@arkansas.gov TSS OSP’s Main Number: 501-324-9316

TSS OSP Website: transform.ar.gov/procurement/ https://arbuy.arkansas.gov/ https://teams.microsoft.com/l/meetup-join/19%3ameeting_NmI5NjQzODktZjY3OS00NDE3LWI0ZGYtNGRiMjgzZWY0ZTMz%40thread.v2/0?context=%7b%22Tid%22%3a%225ec1d8f0-cb62-4000-b327-8e63b0547048%22%2c%22Oid%22%3a%229e90e135-bbe1-4767-b7b7-ba808ff42eae%22%7d https://dialin.teams.microsoft.com/6b6513dc-a034-48d2-8d06-7e711c4ecc0b?id=719036839 mailto:Tiffany.Maddox@arkansas.gov https://www.transform.ar.gov/procurement/

Rev 5/2024

SECTION 1 – GENERAL INFORMATION AND INSTRUCTIONS

1.1 INTRODUCTION

This Request for Proposal (RFP) is issued by the TSS Office of State Procurement (TSS OSP) for the Arkansas Economic Development Commission (AEDC) to obtain pricing and a contract(s) for International Office in Korea.

Contract(s) will be awarded to the Prospective Contractor determined to have submitted the proposal that is the most advantageous to the State. Direct all questions, comments, or concerns regarding this solicitation to the TSS OSP, not the Department.

1.2 TYPE OF CONTRACT

A. As a result of this RFP, TSS OSP intends to award a contract to a single Contractor.

B. The anticipated starting date for any resulting contract is October 01, 2024, except that the actual contract start date may be adjusted unilaterally by the State for up to three (3) calendar months. By submitting a signed proposal in response to the RFP, the Prospective Contractor represents and warrants that it will honor its proposal as being held open as irrevocable for this period.

C. The initial term of a resulting contract will be for four (4) years. Upon mutual agreement by the Contractor and Department, the contract may be renewed by TSS OSP for up to three (3) additional one-year terms or portions thereof, not to exceed a total aggregate contract term of seven (7) consecutive years.

1.3 DEFINITION OF TERMS

A. Unless otherwise defined herein, all terms defined in Arkansas Procurement Law have the same meaning herein.

B. “CRM” means Customer Relationship Management.

C. “Prospective Contractor” means a responsible offeror who submits a proposal in response to this Solicitation.

D. The terms “Request for Proposal,” “RFP,” and “Solicitation” are used synonymously in this document.

E. “Requirement” means a term, condition, provision, deliverable, Specification, or a combination thereof, that is obligated under the Solicitation, resulting contract, or both.

F. “Responsive Proposal” means a proposal submitted in response to this Solicitation that conforms in all material respects to this RFP.

G. “Shall” and “must” mean the imperative and are used to identify Requirements.

H. “Specification” means any technical or purchase description or other description of the physical or functional characteristics, or of the nature, of a commodity or service. “Specification” may include a description of any Requirement for inspecting, testing, or preparing a commodity or service for delivery.

I. “State” means the State of Arkansas. When the term “State” is used herein to reference any obligation of the State under a contract that results from this Solicitation, that obligation is limited to the Department using such a contract.

1.4 SOLICITATION SCHEDULE

For informational purposes, TSS OSP is providing a Solicitation Schedule; however, dates listed and noted with an asterisk (*) are anticipated dates only and are subject to change at the discretion of the State. All times are listed in Central Time.

TABLE A: TENTATIVE SOLICITATION SCHEDULE

ACTIVITY DATE

RFP Release to Prospective Contractors July 18, 2024

Deadline for Prospective Contractor Questions July 24, 2024

Answers to Questions Posted to ARBuy* July 30, 2024

Proposal Due Date August 5, 2024 @ 2 pm

Initial Proposal Evaluation* August 12, 2024

Interviews* Aug 14 – Aug 15, 2024

Final Proposal Evaluation* August 15, 2024

Discussions Kick Off Meeting* August 19, 2024

Finalize Discussions* August 20, 2024

Post Anticipation to Award* August 26, 2024

Award Contract* October 1, 2024

1.5 CLARIFICATION OF SOLICITATION

A. Submit questions requesting clarification of information contained in this Solicitation via the

Solicitation posting in ARBuy by the date and time listed in Table A.

1. For each question submitted, Prospective Contractor should reference the specific Solicitation item number to which the question refers, as applicable.

2. Prospective Contractors’ written questions will be consolidated and responded to by the State as deemed appropriate. The State’s consolidated written response is anticipated to be posted to the Solicitation posting in ARBuy by the close of business on the date provided in Table A. If Prospective Contractor questions are unclear or non-substantive in nature, the State may request clarification of a question(s) or decline to answer.

B. The Prospective Contractor should notify the TSS OSP Procurement Specialist of any Requirements that precludes the Prospective Contractor from submitting a Responsive Proposal.

C. Prospective Contractors may contact the TSS OSP Procurement Specialist with non-substantive questions at any time prior to the proposal opening.

D. An oral statement by TSS OSP will not be part of any contract resulting from this Solicitation and may not reasonably be relied on by any Prospective Contractor as an aid to interpretation unless it is reduced to writing and expressly adopted by TSS OSP.

E. Only an addendum written and authorized by the State will modify the Solicitation.

1.6 RESPONSE DOCUMENTS

A. All proposal responses must be submitted through ARBuy, the State’s eProcurement system. The system can be accessed at arbuy.arkansas.gov.

1. Prospective Contractors must be registered in ARBuy to submit proposals responses.

B. Technical Proposal Packet

1. Prospective Contractors shall utilize the Technical Proposal Packet to submit their responses.

2. The following items are proposal Submission Requirements and must be submitted as part of a Prospective Contractor’s proposal response.

a. Signed Proposal Signature Page; signature may be ink or digital.

https://arbuy.arkansas.gov/

b. Technical Proposal response to the Information for Evaluation section included in the Technical Proposal Packet, which must be in the English language.

c. Completed Official Solicitation Price Sheet attached to the Solicitation in ARBuy.

i. Pricing must be proposed in U.S. dollars and cents.

ii. Quantities stated are estimates only and are not guaranteed. Prospective Contractor must submit unit price on the estimated quantity and unit of measure specified.

• The State may order more or less than the estimated quantity on term contracts, and the Contractor shall sell to the Department quantities ordered at no more than the submitted price.

iii. If pricing documents do not allow for accurate pricing, Prospective Contractor should notify the OSP Procurement Specialist at least seventy-two (72) hours before the proposal opening time.

iv. Prices must be firm offers and adjustments may be negotiated at the time of contract renewal.

• Include this bullet if price increase is an option: A request for a price increase must include supporting documentation demonstrating that the increase in contract price is based on an increased cost to the Contractor and that the proposed pricing is still competitive in the marketplace. The State has the right to approve or deny any request for a price adjustment.

v. Discount from list pricing is not acceptable unless requested elsewhere in the Solicitation.

vi. State or local sales taxes should not be included in the price. Trade discounts should be deducted from the unit price and the net price should be shown in the pricing response.

d. Recommended Options Form

i. The Recommended Options form included in the Technical Proposal Packet allows Prospective Contractors to identify any recommended options or optional service ideas that may benefit the State that were not included in the Requirements and the proposed solution.

e. Copy of Prospective Contractor’s Equal Opportunity Policy

i. Pursuant to Arkansas Code Annotated § 19-11-104, OSP requires a Prospective Contractor bidding on a state contract to submit a copy of the Prospective Contractor’s Equal Opportunity (EO) Policy.

ii. Prospective Contractors not required by law to have an EO Policy must submit a written statement to that effect.

f. Proposed Subcontractors Form (see SRV-1, section 14)

3. The following items, which must be submitted prior to a contract award to the Prospective Contractor, may also be included with the Prospective Contractor’s proposal:

a. EO 98-04: Contract and Grant Disclosure Form (see SRV-1, section 11)

b. Voluntary Product Accessibility Template (VPAT), if applicable

4. Prospective Contractors should not include any other documents or ancillary information, such as a cover letter or promotional/marketing information.

C. Redacted copy of the Technical Proposal Packet https://www.transform.ar.gov/wp-content/uploads/Services-Contract-SRV-1-Fillable-Form-V.3.6.27.22.pdf https://www.transform.ar.gov/wp-content/uploads/Services-Contract-SRV-1-Fillable-Form-V.3.6.27.22.pdf https://www.section508.gov/sell/vpat/

1. One (1) redacted (marked Redacted) copy of the Prospective Contractor’s proposal response (see Proprietary Information), if applicable.

D. Prospective Contractors should not alter language in Solicitation document(s) or Official Proposal Price Sheet provided by the State.

E. Prospective Contractor’s proposals cannot be altered or amended after the proposal opening except as permitted by law or rule.

F. Prospective Contractors may submit multiple proposals.

SECTION 2 – REQUIREMENTS

2.1 BACKGROUND AND CURRENT ENVIRONMENT

South Korea has steadily risen among the ranks of nations investing and creating jobs in the United States, especially over the past decade. Furthermore, South Korean companies are increasingly adept in sectors Arkansas has identified as target sectors for economic development, including metals manufacturing, information technology, mobility & transportation, and food & beverage production. The AEDC has been duly engaged with the South Korean business community but believes that a full-time representative presence in the market would improve our competitiveness in attracting more South Korean foreign direct investment (FDI). Therefore, the AEDC is issuing this RFP to identify a Contractor to serve in this capacity.

2.2 OBJECTIVE AND GOALS

The Department seeks to attract more Korean businesses to Arkansas, leading to job creation and capital investment. More specifically to recruit foreign direct investment of Korean companies in our targeted industries, which include:

• Advanced Manufacturing (including Aerospace and Defense, Firearms and Ammunition, Food and

Beverage, Metal Fabrication, and Mobility and Transportation)

• Agtech and Forestry

• Professional Services

• Information Technology (including Data Sciences, FinTech, and Cyber)

• Life Sciences (including Bioinformatics, Medical Devices, and Innovative Healthcare)

• Logistics and Distribution

2.3 PROSPECTIVE CONTRACTOR MINIMUM QUALIFICATIONS

A. The Prospective Contractor shall have a minimum of five (5) years' experience providing services of similar size and scope as described in this RFP.

B. The Prospective Contractor shall have a minimum of five (5) years’ experience providing services of similar size and scope as described in this RFP to another U.S. State in Korea.

C. The Prospective Contractor’s staff shall be fluent in English and Korean.

D. The Prospective Contractor’s staff assigned to the resulting contract shall be Korean residents.

E. The Prospective Contractor shall have a knowledge of corporate site selection and foreign direct investment activities.

2.4 GENERAL REQUIREMENTS

A. The Contractor shall have an existing business address or establish such an address within three (3) months of contract execution, in Seoul South Korea that will be designated as the State of Arkansas Korea Office’s mailing address.

B. The Contractor shall be available during business hours in Central Standard Time as needed by AEDC while still performing business during South Korean business hours.

C. The Contractor shall have a working knowledge of Arkansas economy and industry and why businesses should locate in Arkansas.

D. The Contractor shall include all travel expenses, conference or trade show registrations and expenses, and other expenses incurred while performing job duties in the total annual cost on the Official Bid Price Sheet.

2.5 PROJECT PLAN AND APPROACH

A. The Contractor shall provide a proposed Action Plan during the Discussions Phase detailing plans to accomplish the goals and contract activities including but not limited to:

1. List of trade shows and conferences planned to attend

2. List of targeted business outreach and how you plan to identify leads for AEDC

3. Tracking leads and follow ups

B. The Contractor shall prepare and provide a sample market industry report during the Discussions Phase.

C. The Contractor shall provide a list of all entities that the Contractor represents during the Discussions Phase and as requested by AEDC throughout the life of the contract.

2.6 LEAD GENERATION/BUSINESS RECRUITMENT

A. The Contractor shall develop and maintain relationships with Korean companies that have a presence in Arkansas through regular communication and meetings with leadership in Korea.

B. The Contractor shall build relationships with prospective Korean companies and convert those relationships into leads that are passed on to the AEDC Business Development team.

C. The Contractor shall report qualified leads in Salesforce and email to AEDC Asia Office Director and/or AEDC Business Development Team.

D. The Contractor shall provide ongoing support and follow up communication regarding current Korean prospective companies as requested by the AEDC Asia Office Director or AEDC Business Development Team.

E. The Contractor shall notify designated AEDC contact within twenty-four (24) hours of any contracts that exist or arise that might cause a conflict of interest for the Contractor or their staff and would inhibit them from representing Arkansas.

2.7 PROMOTING ARKANSAS

A. The Contractor shall represent Arkansas at industry trade shows and conferences in Korea, which includes preparing and staffing a booth and scheduling meetings.

B. The Contractor shall attend industry association meetings and embassy events in Korea to promote Arkansas.

C. The Contractor shall provide a quarterly schedule of trade shows and conferences in Korea that would be most beneficial to AEDC.

D. The Contractor shall, at his/her own expense, travel to Arkansas at least once per year to learn of new initiatives, meet stakeholders, and participate in AEDC meetings.

E. The Contractor shall stay up to date on Arkansas’ business climate, targeted industries, initiatives, and resources that are of interest to Korean companies considering Arkansas.

F. The Contractor shall work with AEDC marketing to periodically update Korea-specific marketing materials, translating materials into Korean as needed.

2.8 MARKET INTELLIGENCE

A. The Contractor shall assist with research on Korean companies and market trends in Korea, as requested by the AEDC Asia Office Director or AEDC Business Development.

B. The Contractor shall provide recommendations on industries and companies in Korea that AEDC should focus recruitment efforts on.

C. The Contractor shall provide updates on political or economic current events in Korea and insight on how it might affect foreign direct investment.

D. The Contractor shall provide cultural and protocol guidance to AEDC as requested.

E. The Contractor shall prepare company briefings for meetings, trade shows, and conferences.

2.9 TRADE MISSION PLANNING AND SUPPORT

A. The Contractor shall coordinate high level missions when requested for the Governor, Secretary of

Commerce, or AEDC Executive Director.

B. The Contractor shall book meetings with executives of Korean companies, make hotel and transportation reservations, assist with briefing materials, and provide protocol guidance.

C. The Contractor shall act as a translator for introductory meetings and travel planning.

2.10 REPORTING

A. The Contractor shall provide monthly reports to the designated AEDC contact including but not limited to activity of notable meetings, conferences, trade shows attended, and a list of leads that need to be followed up by the AEDC Business Development Team.

B. The Contractor shall provide quarterly financial reports to the designated AEDC contact, including all invoices, reflecting all expenses related to this contract.

C. The Contractor shall provide an annual market industry report to the designated AEDC contact. The report must, at minimum:

1. Reflect industry in Korea

2. Include trends in the economy of Korea

3. Identify potential opportunities that Arkansas can take advantage of.

D. The Contractor shall enter all leads and contacts in Salesforce or other CRM designated by AEDC.

E. The Contractor shall provide all reports in English and U.S. Currency.

2.11 STAFFING

A. The Contractor shall be required to provide a Staffing Plan during the Discussions phase.

B. AEDC shall have the right to approve or reject proposed staff members prior to the finalization of the plan after Contract Award.

C. The Contractor shall include, in the Staffing Plan, a provision to address the vacancies of key personnel. In the event of the vacancy of a key person, the Contractor shall provide replacement candidates to AEDC for review within fifteen (15) calendar days of the contractor notifying AEDC of the vacancy. AEDC shall have the right to approve or reject proposed replacements if they do not meet the minimum requirements set forth in the RFP.

D. The Contractor shall replace key personnel upon request by AEDC for justified reasons including but not limited to performance, behavior, and security.

E. The Contractor shall provide and maintain sufficient staffing resources to provide timely service for the life of the contract.

F. The Contractor shall not propose resources who are currently engaged full time on other contracts with the State. A single resource may not hold more than one full time position with the State.

G. The Contractor shall designate specific staff to manage this contract. AEDC shall have final approval over designated staff.

H. The Contractor shall obtain written authorization from designated AEDC contact prior to subcontracting any services after the execution of the contract. This must include but is not limited to event planning services, catering, hotels, etc.

2.12 DATA OWNERSHIP & END OF CONTRACT TRANSITION

A. The State shall retain sole ownership, right, title, and interest to all data collected and stored by the

Contractor under a resulting contract, excluding intellectual property and exclusions governed by applicable State and Federal laws.

B. At the end of the contract and after confirmed transfer of 100% of the State-owned data, deliverables, and products the Contractor has created, developed, produced, and managed while performing the services outlined in this RFP back to the State or their designee, the Contractor shall destroy all copies of the State-owned data the Contractor possesses.

C. The Contractor shall ensure all data received as part of the Contract is used solely for the purpose of this contract and not shared, reused, or disseminated to any other party or entity without the express written consent of the AEDC designated representative or as otherwise required under applicable State and Federal laws.

D. Upon termination or expiration, should any subsequent contract for this or similar services be awarded to a provider other than the Contractor, the Contractor shall, to the greatest extent possible and reasonable, cooperate with the ADE in initiating a smooth and orderly transition to the next contractor.

2.13 PERFORMANCE STANDARDS

A. State law requires that qualifying contracts for services include Performance Standards for measuring the overall quality of services that a Contractor shall provide.

B. The State may be open to negotiations of Performance Standards prior to contract award, prior to the commencement of services, or at times throughout the contract duration.

C. Performance Standards shall not be amended unless they are agreed to in writing and signed by the parties.

D. Failure to meet the minimum Performance Standards as specified will result in the assessment of damages.

E. In the event a Performance Standard is not met, the Contractor will have the opportunity to defend or respond to the insufficiency. The State has the right to waive damages if it determines there were extenuating factors beyond the control of the Contractor that hindered the performance of services. In these instances, the State has final determination of the performance acceptability.

F. Should any compensation be owed to the Department due to the assessment of damages, Contractor shall follow the direction of the Department regarding the required compensation process.

SECTION 3 – SELECTION

3.1 SELECTION PROCESS

A. TSS OSP will review each Technical Proposal Packet to verify Submission Requirements have been met. Technical Proposal Packets that do not meet Submission Requirements will be rejected and will not be evaluated.

1. The State may conduct cost checks based on the cost submitted by each Prospective Contractor on the completed pricing response.

a. Prospective Contractors submitting Responsive Proposals with a proposed cost that falls twenty-five percent (25%) or more from the average submitted cost may be asked to justify their submitted cost.

b. Should TSS OSP request clarification and/or additional information regarding cost, Prospective Contractors shall provide clarification and/or additional information as specified by the request.

B. A Department-appointed Evaluation Committee will evaluate and score Responsive Proposals.

Evaluation will be based on Prospective Contractor’s response to the Information for Evaluation section included in the Technical Proposal Packet and the pricing submitted by the Prospective Contractor.

1. Cost information will be provided to the members of the Evaluation Committee (Evaluators) to allow them to determine which proposal(s) is the most advantageous to the State.

2. Evaluators will individually review and evaluate proposals and complete an Individual Score Worksheet for each proposal. Individual scoring for each Evaluation Criteria will be based on the scoring description in Table B: Scoring Table.

TABLE B: SCORING TABLE

SCORE DESCRIPTION

The response provides metrics clearly establishing that the Prospective Contractor is reliable and capable of fully performing the required services.

The response provides metrics suggesting that the Prospective Contractor’s level of performance may be acceptable, but it does not clearly establish that the Prospective Contractor is reliable and capable of fully performing the required services.

The response provides metrics clearly establishing that the Prospective Contractor is unreliable and incapable of fully performing the required services.

3. After initial individual evaluations are complete, the Evaluators will meet to discuss their individual scores. At the initial consensus meeting, each Evaluator will be afforded an opportunity to discuss his or her score for each evaluation criteria.

4. After Evaluators have had an opportunity to discuss their individual scores with the committee, the Evaluators will be given the opportunity to change their initial individual scores, if they feel that is appropriate.

5. The final individual scores of the Evaluators will be recorded on the Consensus Scoresheets and averaged to determine the group or consensus score and rank for each proposal.

6. Other agencies, consultants, and experts may also examine documents at the discretion of the Department.

C. Prospective Contractors submitting Responsive Proposals will be contacted by TSS OSP to schedule an interview.

1. Prospective Contractors shall attend the interview as scheduled by TSS OSP.

2. Evaluators will complete an Individual Score Worksheet for each interview. Evaluation will be based on Prospective Contractor’s responses to questions presented during the interview Individual scoring for each interview will be based on the Scoring Descriptions in 3.1.B.1.

3. During a final consensus meeting, after all interviews are complete, Evaluators will have the opportunity to discuss the interviews and change their individual interview scores on the Consensus Scoresheet, if they feel that is appropriate.

a. The final individual scores of the Evaluators will be recorded on the Consensus Scoresheets and averaged to determine the group or consensus score and rank for each proposal.

4. Should the State receive only one (1) Responsive Proposal, the State may forgo the interview portion of the evaluation if the proposal has received the Maximum Weighted Score Possible for the Experience, Solution, and Risk subsections.

a. In this scenario, the proposal would automatically receive the maximum weighted score possible for the interview subsection.

D. Should the State request clarification and/or additional information Prospective Contractors’ responses, Prospective Contractors shall provide clarification and/or additional information as specified by the State.

E. TSS OSP will submit responses and pricing received from the interviewed Perspective Contractors, along with the Evaluation Committee’s recommendation to the Department for review and approval to move into Discussions.

3.2 TECHNICAL PROPOSAL SCORE

A. The Information for Evaluation section has been divided into subsections.

1. Each subsection has been assigned a maximum point value of ten (10) points. The total point value for each subsection is reflected in the table below as the Maximum Raw Points Possible.

2. The Department has assigned Weighted Percentages to each subsection according to its significance.

INFORMATION FOR EVALUATION

SUBSECTIONS

MAXIMUM

RAW

POINTS

POSSIBLE

SUBSECTION’S

WEIGHTED

PERCENTAGE

* MAXIMUM

WEIGHTED

SCORE

POSSIBLE

Experience 10 20% 140

Solution 10 30% 210

Risk 10 20% 140

Interview 10 30% 210

Total Technical Score 40 100% 700

*Subsection’s Percentage Weight x Total Technical Maximum Weighted Score = Maximum Weighted Score Possible for the subsection.

B. The proposal’s weighted score for each subsection will be determined using the following formula:

(A/B)*C =D

A = Actual Raw Points received for subsection in evaluation

B = Maximum Raw Points possible for subsection

C = Maximum Weighted Score possible for subsection

D = Weighted Score received for subsection

C. The proposal’s weighted scores for subsections will be added to determine the Total Technical Score for the proposal.

D. Proposals that do not receive a minimum Total Technical Score of 300 will not be subject to further consideration in the Solicitation process. The pricing for proposals that do not receive a minimum Total Technical Score of 300 will not be scored.

3.3 COST SCORE

A. When scores are applied to pricing, the maximum amount of cost points will be given to the proposal with the lowest annual grand total as shown in Table One (1) on the completed Official Solicitation Price Sheet. (See Grand Total Score for maximum points possible for cost score.)

B. The amount of cost points given to the remaining proposals will be allocated by using the following formula:

(A/B)*C =D

A = Lowest estimated cost

B = Second (third, fourth, etc.) lowest estimated cost

C = Maximum Points for lowest estimated cost

D = Total price points received

3.4 GRAND TOTAL SCORE

The Technical Score and Cost Score will be added together to determine the Grand Total Score for the proposal. The State may move forward to Discussions with the Prospective Contractor determined reasonably susceptible of being selected for award.

MAXIMUM

POINTS

POSSIBLE

Technical Proposal 700

Cost 300

Maximum Possible Grand Total Score 1,000

3.5 EXPLANATION OF THE SUBSECTIONS OF THE TECHNICAL PROPOSAL

A. Experience

1. The Experience subsection included in the Technical Proposal Packet allows Prospective Contractors to differentiate themselves based on their experience, technical capability, and understanding of the State’s specific needs.

2. Prospective Contractors should identify expertise in the form of a claim and provide relevant experience to support each claim.

3. Prospective Contractors should use verifiable metrics (number of accounts, size of accounts, years of experience, customer satisfaction ratings) to support each claim.

B. Solution

1. The Solution subsection included in the Technical Proposal Packet allows Prospective Contractors to differentiate themselves based on their proposed solution and/or approach to solve the State’s specific needs.

2. Prospective Contractors should provide a high-level overview of the Prospective Contractor’s proposed solution and/or approach to services using the Requirements outlined in the RFP.

3. Proposed solutions should be non-technical and include the Prospective Contractor’s recommendations for meeting the objectives and Requirements of the RFP.

4. Additional service options and recommendations above and beyond those included in proposed solution should be included in the Recommended Options Form.

C. Risk

1. The Risk subsection included in the Technical Proposal Packet allows Prospective Contractors to identify and prioritize major risks that they reasonably foresee could potentially prevent or impair the Prospective Contractor’s delivery of the solution as offered in the proposal or to otherwise fail to meet the State’s desired outcome, specifications, and performance standards, and how they will mitigate, manage, and/or minimize each risk listed.

a. Prospective Contractors should include sources, causes, or actions that are both within and beyond the control of the Prospective Contractors that they reasonably foresee may cause cost increases, delays, amendments, or dissatisfaction to the State.

b. Risks should be described in simple, clear, and non-technical terms.

c. Prospective Contractor should explain how the Prospective Contractor will mitigate, manage, and/or minimize each risk listed.

i. The Documented Performance cell should include details such as how many times any identified risk was previously mitigated and the impact on the Prospective Contractor’s performance in terms of time, cost, and client satisfaction.

D. Interview

1. The Interview will allow Prospective Contractors to further demonstrate their experience in providing the services outlined in the RFP.

a. Each Prospective Contractor meeting the Submission Requirements will be contacted by TSS OSP to schedule an interview. Prospective Contractors shall attend the interview as scheduled by TSS OSP.

b. Prospective Contractors shall identify one (1) Project Lead at the time of interview confirmation who shall attend the interview as part of the evaluation process.

c. The Evaluation Committee will interview the Prospective Contractor’s identified Project Lead using a pre-determined set of interview questions. Follow up questions may be asked based on responses given by the Project Lead.

3.6 DISCUSSIONS

A. The State will move forward into Discussions with the responsible Prospective Contractor(s) whose proposal(s) have been determined to be reasonably susceptible to being selected for award.

B. Discussions may be conducted with the highest-ranking Prospective Contractor based on the Grand Total Score for each proposal or with multiple Prospective Contractors reasonably susceptible of being awarded a contract.

C. Should the State choose to engage in Discussions with the highest-ranking Prospective Contractor, the Prospective Contractor invited to participate in Discussions shall provide all documents required during Discussions.

1. Should the Department determine, through the Discussions process, that the Prospective Contractor’s solution, approach, timelines, deliverables, expectations of the State, or a combination thereof make the Prospective Contractor no longer reasonably susceptible of being awarded a contract, the Department may abandon Discussions with that Prospective Contractor through a written justification to TSS OSP, and may proceed to additional rounds of Discussions with the next highest-ranking Prospective Contractor.

D. Should the State choose to engage in Discussions with multiple Prospective Contractors contemporaneously, each Prospective Contractor invited to participate in Discussions shall provide all documents required during Discussions.

1. Should a Prospective Contractor not provide the required documents within timeframes requested by TSS OSP or choose not to engage in the Discussions process, the Prospective Contractor’s proposal will be considered withdrawn and will not be subject to further consideration in the Solicitation process.

E. If Discussions necessitate material revisions of proposals, each responsible Prospective Contractor reasonably susceptible of being awarded a contract will be provided an opportunity to revise its proposal for the purpose of submitting a best and final offer.

F. During the Discussions Kick Off Meeting, the Prospective Contractor shall provide the following documents to the State:

1. A detailed scope of work clearly identifying the Prospective Contractor’s understanding, implementation, and performance of services required in this RFP, including all activities required by the Contractor and all activities expected by the State/Participating Entities

2. A Risk Management Plan intended to mitigate any risks, including but not necessarily limited to, the risks identified in the Risk Plan submitted in the Prospective Contractor’s Technical Proposal Packet

3. A proposed financial summary, including:

a. The completed pricing response and Recommended Options Form submitted in the Prospective Contractor’s Technical Proposal Packet

b. A proposed payment schedule

4. Proposed project management and reporting templates

G. During the Discussions Kick Off Meeting, the Prospective Contractor shall address questions and/or concerns the State may have to the satisfaction of the State.

H. During Discussions, the Prospective Contractor shall revise the discussions documents until agreement is made and the State has provided final approval.

1. The Prospective Contractor shall attend follow up Discussions meeting as determined necessary by the State. Reasonable effort will be made to accommodate scheduling conflicts.

I. During Discussions, the Prospective Contractor shall present a final draft of the Discussions documents to the State, including, at minimum:

1. A summary of all plans and scope of work developed during the discussions process and mutually agreed upon by the State and the Prospective Contractor

2. A detailed scope of work clearly identifying the Prospective Contractor’s implementation and performance of services required in this RFP, including all provisions negotiated and agreed upon by the State and the Prospective Contractor since the Discussions Kick Off Meeting

3. Description of deliverables in terms of simplified metrics

4. The Risk Management Plan

5. Project management and reporting templates

6. Financial summary, including:

a. The completed pricing response submitted in the Prospective Contractor’s Technical Proposal Packet

b. A list of agreed upon and accepted recommended options (with impact to price)

c. A payment schedule

d. Contact information for the Prospective Contractor’s key personnel

J. During Discussions, the Prospective Contractor shall present the final drafts of the items and shall summarize the coordination and planning completed during the discussion process.

K. Once approved by the State, final drafted documents will become part of the resulting contract.

L. The Prospective Contractor may determine which key personnel will attend the Discussions meetings.

3.7 ANTICIPATION TO AWARD

A. Once an anticipated Contractor has been determined, the anticipated award will be posted to the

Solicitation posting in ARBuy by the date and time listed in Table A.

1. It is the responsibility of Prospective Contractors to check the ARBuy website for the posting of an anticipated award.

B. Anticipated awards will generally be posted for a period of fourteen (14) days prior to the issuance of a contract. These notices are anticipated awards only and are subject to protest.

C. A contract resulting from this Solicitation is subject to State review and approval processes prior to award, which may include Legislative review.

3.8 PROSPECTIVE CONTRACTOR ACCEPTANCE OF EVALUATION TECHNIQUE

The submission of a Technical Proposal Packet signifies the Prospective Contractor’s understanding and agreement that some subjective value judgments will be made during the evaluation and scoring of the technical proposals.

SECTION 4 – SOLICITATON TERMS AND CONDITIONS

4.1 ACCEPTANCE OF REQUIREMENTS

A. A Prospective Contractor's past performance with the State may be used to determine if the

Prospective Contractor is responsible (OSP Rule R8:19-11-229).

1. Proposals submitted by Prospective Contractors determined to be non-responsible will be rejected.

B. A single Prospective Contractor must be identified as the prime contractor.

1. The prime Contractor shall be responsible for the resulting contract and jointly and severally liable with any of its subcontractors, affiliates, or agents to the State for the performance thereof.

C. By submission of a proposal, the Prospective Contractor represents and warrants:

1. That the prices in the proposal have been arrived at independently, without any collusion with another competing Prospective Contractor.

a. Collusion violates Arkansas Procurement Law and can lead to suspension, debarment, and can be referred to the Attorney General’s officer for investigation and appropriate legal action (Arkansas Code Annotated § 19-11-240 and 19-11-245).

2. That the Prospective Contractor has not retained a person to solicit or secure the resulting contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee, except for retention of bona fide employees or bona fide established commercial selling agencies maintained by the Prospective Contractor for the purpose of securing business.

D. Prospective Contractor should not discuss the Solicitation or proposal response, issue statements or comments, or provide interviews to public media during the Solicitation and award process.

E. Qualifications and services must meet or exceed the required Specifications as set forth in the Solicitation.

F. The State will not pay costs incurred in the preparation of a proposal.

4.2 GENERAL TERMS AND CONDITIONS

A. The Contractor must be registered as a vendor to receive payment and may register online by visiting https://www.ark.org/contractor/index.html and clicking the Start Here button.

B. The Prospective Contractor represents and warrants that, prior to being awarded any executed contract resulting from this solicitation, the Prospective Contractor has taken or shall take all actions necessary to receive payment from the State through Electronic Funds Transfer (EFT) for the services and/or commodities to be provided under any such contract. This includes, without limitation, the following actions:

1. Signing documents authorizing the State to make EFT payments into a bank account designated by the Prospective Contractor.

2. Providing all information requested by the State to set up EFT payments, including either a voided check or a letter from their financial institution that contains the following information:

a. Account holder’s name

b. Account number

c. Routing number

d. Financial institution official’s contact information and signature

3. In the event the EFT information changes, the Contractor shall be responsible for providing the updated information to the State. No interest or late payment penalty will apply if payment is https://www.ark.org/contractor/index.html delayed because of the Contractor’s failure to initially provide or update information necessary for the State to make EFT payment.

C. Pursuant to Arkansas State Procurement Law, the Contractor shall certify that, unless they offer to provide the goods or services for at least twenty percent (20%) less than the lowest certifying Prospective Contractor:

1. They are not engaged in and shall not, during the aggregate term of the resulting contract, engage in a boycott of Israel (Arkansas Code Annotated § 25-1-503),

2. They are not engaged in and shall not, during the aggregate term of the resulting contract, engage in a boycott of an Energy, Fossil Fuel, Firearms, or Ammunition Industry (Arkansas Code Annotated § 25-1-1102).

D. Pursuant to Arkansas Procurement Law, the Contractor shall certify that the Contractor does not knowingly employ or contract with illegal immigrants and that the Contractor shall not knowingly employ or contract with illegal immigrants during the aggregate term of any contract with the State or any of its departments, institutions, or political subdivisions (Arkansas Code Annotated § 19-11-105).

E. Specifications, drawings, technical information, dies, cuts, negatives, positives, data, other such item furnished by the State to the Contractor, or a combination thereof hereunder or in contemplation hereof or developed by the Contractor for use hereunder shall:

1. Remain property of the State.

2. Be kept confidential as permitted or required by law.

3. Be used only as expressly authorized.

4. Be returned at the Contractor's expense to the F.O.B. destination point provided by the State, as requested by the State.

a. The Contractor shall properly identify items being returned.

F. The Contractor shall invoice the State as required by the Department and should not invoice the State in advance of delivery and acceptance of any goods or services (Arkansas Code Annotated § 19-4-1206).

1. The Contractor should invoice the agency by an itemized list of charges. The Department’s purchase order number and/or the contract number should be referenced on each invoice.

2. Payment will be made in accordance with applicable State of Arkansas accounting procedures upon acceptance of goods and services by the Department.

3. Payment will be made only after the Contractor has successfully satisfied the Department as to the reliability and effectiveness of the goods or services purchased as a whole.

G. The Contractor should be able to accept the State’s authorized VISA Procurement Card (p-card) as a method of payment. Price changes or additional fee(s) must not be levied against the State when accepting the p-card as a form of payment.

H. The Prospective Contractor shall certify that they are not a company owned in whole or with a majority ownership by the government of the People's Republic of China (a “Scrutinized Company”) and that they do not and shall not during the aggregate term of the resulting contract employ a Scrutinized Company as a contractor (Arkansas Code Annotated § 25-1-1203).

I. This RFP incorporates all terms of the Services Contract (SRV-1) Fillable Form (found here).

1. The contract template is attached to the Solicitation in ARBuy as a sample for your information only.

2. A Prospective Contractor’s proposal may be rejected if a Prospective Contractor takes exception to any terms, conditions, or Requirements in this RFP.

https://www.transform.ar.gov/wp-content/uploads/Services-Contract-SRV-1-Fillable-Form-V.3.6.27.22.pdf

J. The Prospective Contractor agrees and shall adhere to all terms, conditions, and Requirements if selected as the Contractor.

1. Items may only be modified if the legal requirement is satisfied and approved by the State during Discussions.

4.3 MINORITY AND WOMEN-OWNED BUSINESS

A. A minority-owned business is defined by Arkansas Code Annotated § 15-4-303 as a business owned by a lawful permanent resident of this State who is:

• African American

• American Indian

• Asian American

• Hispanic American

• Pacific Islander American

• A Service-Disabled Veteran as designated by the United States Department of Veteran Affairs

B. A women-owned business is defined by Act 1080 of the 91st General Assembly Regular Session

2017 as a business that is at least fifty-one percent (51%) owned by one (1) or more women who are lawful permanent residents of this State.

C. The Arkansas Economic Development Commission conducts a certification process for minority-owned and women-owned businesses. If certified, the Prospective Contractor’s Certification Number should be included on the Proposal Signature Page.

4.4 PROPRIETARY INFORMATION

A. The release of public records is governed by the Arkansas Freedom of Information Act (Arkansas

Code Annotated § 25-19-101 et. seq.).

B. Submission documents pertaining to the Solicitation become the property of the State and are subject to the Arkansas Freedom of Information Act (FOIA).

C. In accordance with FOIA, and to promote maximum competition in the State competitive sealed proposals, the State may maintain the confidentiality of certain types of information described in FOIA. Such information may include trade secrets and other information exempted from public disclosure pursuant to FOIA.

D. Consistent with and to the extent permitted under FOIA, any Prospective Contractor may designate appropriate portions of a proposal as confidential by submitting a redacted copy of the proposal. By so redacting any information contained in the proposal, the Prospective Contractor warrants that, after having received such necessary or proper review by counsel or other knowledgeable advisors, it has formed a good faith opinion that the portions redacted are not considered public records under

FOIA.

E. If a Prospective Contractor deems part of the information contained in a response not to be a public record, the Prospective Contractor should submit one (1) complete copy of the submission documents from which any proprietary or confidential information has been redacted in their proposal response. Except for the redacted information, the redacted copy must be identical to the original copy, reflecting the same pagination as the original and showing the space from which information was redacted.

F. The Prospective Contractor is responsible for identifying all proprietary information and for ensuring the electronic copy is protected against restoration of redacted data.

G. The redacted copy will be open to public inspection under the FOIA without further notice to the Prospective Contractor. If the State deems redacted information to be subject to a public record request under FOIA, the State will endeavor to notify the Prospective Contractor prior to release of the redacted record.

H. The State has no liability to a Prospective Contractor with respect to the disclosure of Prospective Contractor’s confidential or proprietary information ordered by a court of competent jurisdiction pursuant to FOIA or other applicable law.