RWP - H1 Heater.pdf
PDF 313 KB Posted
- Attached to
- Request for White Paper - Heater Modernization
- Solicitation number
- FA9101269BH1HM
About this file
This is a Request for Whitepapers (RWP) from the Department of the Air Force's Arnold Engineering Development Complex (AEDC) seeking qualified performers to execute the H-1 Heater Modernization project at Arnold Air Force Base, Tennessee. The RWP is issued under Other Transaction Authority (10 U.S.C. § 4022) and targets AEDC Velocity Alliance Consortium Performers and Industry Partners via SAM.gov. The applicable NAICS code is 811310 (Commercial and Industrial Machinery and Equipment Repair and Maintenance) and PSC code is J045 (Maintenance, Repair, and Rebuilding of Equipment). The submission deadline is 24 September 2026, with submissions required in PDF format via secure portal, with schedules attached in native Primavera .xer or MS Project .mpp formats.
The modernization project encompasses design, engineering, evaluation, procurement, demolition, fabrication, installation, programming, inspection, demonstration, testing, and documentation to restore a 40-year-old indirect-fired air heater system to original design specifications. Performers must demonstrate technical competency in five areas: combustion and burner systems (NFPA 85/86 compliance), safety instrument systems and burner management systems (SIL 3 per IEC 61508), industrial controls integration (Emerson RX3i PLCs and GE Cimplicity HMI), pressure vessel and piping design (ASME compliance), and professional engineering certification (Tennessee PE license). Whitepaper responses must not exceed 15 pages and include three examples of past performance with customer references, a technical narrative, IP/data rights confirmation (with unlimited data rights to AEDC), demonstration of compliance with at least one of three 10 U.S.C. § 4022(d) conditions, firm fixed-price milestone pricing for base milestones (valid for 180 days minimum), estimated schedules for optional milestones, and CMMC compliance or equivalent safeguards documentation. Government evaluation uses Best Value determination across three equally weighted criteria: technical competency and capability, schedule feasibility, and cost/price realism. Base milestones (Prototype Type A—Proof of Concept/Business Process) include five design review gates (CRR, PDR, CDR, FDR) with success defined by approved SOW, RTD, site plan, comprehensive engineering analyses stamped by a Tennessee PE, detailed AutoCAD-compatible schematics and P&IDs, and independent SIL 3 safety analysis. Optional unpriced milestones (Prototype Type E—Operational Utility) require physical demonstration of continuous operation at original design specifications, verification of inlet pressure range reliability, pressure differential limits, safety valve timing under 1.0 second, thermal guarding (accessible surfaces not exceeding 120°F), acoustic compliance, and seamless control room interface integration with AEDC Plant Control System. The Government Point of Contact is Haley M. K. Smith, Agreements Officer at haley.smith.10@us.af.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Statement of Objectives (SOO).pdf | ||
| SOO_Appendix B_Design Review Expectations.pdf | ||
| SOO_Appendix C_AEDC Standards.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS AIR FORCE TEST CENTER (AFMC)
EDWARDS AIR FORCE BASE CALIFORNIA
Project Subject H-1 Heater Modernization
Document Type Request for Whitepapers (RWP)
Target Audience AEDC Velocity Alliance Consortium Performers and Industry
Partners via SAM.gov
Applicable NAICS Code 811310 (Commercial and Industrial Machinery and Equipment
Repair and Maintenance)
Applicable PSC Code J045 (Maintenance, Repair, and Rebuilding of Equipment)
Acquisition Authority 10 U.S.C. § 4022 Other Transaction Authority (OTA)
1.0 Introduction and Purpose
Arnold Engineering Development Complex (AEDC), is issuing this Request for Whitepapers
(RWP) to identify a qualified Performer to execute the H-1 Heater Modernization project at
Arnold Air Force Base (AAFB), Tennessee.
The existing H-1 Heater is an indirect-fired air heater that is currently over 40 years old.
Originally designed to provide intermediate temperature air to the mixing header and heated inlet air to the high-temperature H-2 Heater, the system has operated under reduced capacity for a significant period. The existing equipment is approaching the end of its expected operational life and presents critical risks regarding operational reliability, personnel safety, and regulatory compliance.
The successful modernization of the H-1 Heater is a prerequisite to supporting the addition of a new H-2 Heater (which is being provided through a separate, parallel effort). This RWP seeks whitepaper submissions from Performers demonstrating the capability to design, engineer, evaluate, and commission a fully functional H-1 Heater system that restores the system to its original design specifications.
2.0 Project Scope and Key Objectives
The modernization scope encompasses all engineering, analysis, evaluation, procurement, demolition, fabrication, installation, programming, inspection, demonstration, testing, and documentation necessary to design, deliver, and commission a fully functional H-1 Heater system. The key objectives are included in Attachment 1 – Performance Parameters.
3.0 Instructions for Performer's Response
The Performer shall submit a white paper, not to exceed 15 pages, that details, at a minimum, the following:
3.1 Technical Competency
The Performer must provide evidence demonstrating their capability to satisfy the project requirements established in Attachment 1 – Performance Parameters. Evidence shall consist of no more than three examples of successful past performance of efforts that include one or more of the following:
1. Combustion & Burner Systems: Demonstrated capability in designing and fabricating or overhauling indirect-fired industrial air heaters and multi-burner systems complying with NFPA 85 and NFPA 86.
2. Safety Instrument Systems & BMS: Experience developing and certifying SIL 3
Burner Management Systems per IEC 61508.
3. Industrial Controls Integration: Demonstrated competency programming Emerson
RX3i PLCs using Proficy Machine Edition and designing GE Cimplicity HMI systems.
4. Pressure Vessel and Piping Design: Ability to perform mechanical, structural, and fluid flow analyses, design carbon steel pressure boundaries , and fabricate systems in accordance with ASME Boiler and Pressure Vessel Code and power/process piping standards.
5. Professional Engineering Certification: Formal capability to deliver final engineering documents, drawings, and analyses stamped by a Professional Engineer (PE) licensed in the State of Tennessee.
All past experience examples shall include, at a minimum, a detailed description of the work, a description of how it is relevant to the above criteria, metrics demonstrating successful performance, and a point of contact (name, position, and contact information) for the customer.
The Performer must also provide a brief technical narrative outlining how they intend to satisfy the project requirements and adhere to the technical constraints.
3.2 Intellectual Property (IP) & Data Rights
The Performer shall explicitly state their compliance with Article: Intellectual Property Rights in accordance with part 3 of the AEDC Velocity Consortium Request for Whitepaper. The
Government requires Unlimited Data Rights to all Performer-provided technical data, analysis, drawings, software, code, and programming produced in performance of this effort. Performers must provide a formal, written confirmation in their whitepaper confirming that all prototype designs, software source codes (for PLC and HMI), and drawings will be delivered as the property of AEDC in native formats (e.g., AutoCAD, native PLC/HMI formats).
3.3 10 U.S.C. 4022(d) Appropriate Use of Authority
Pursuant to 10 U.S.C. § 4022(d), other transaction agreements for prototype projects may only be entered into if:
1. There is at least one nontraditional defense contractor or nonprofit research institution participating to a significant extent in the prototype project;
2. All significant participants in the transaction other than the Federal Government are small businesses or nontraditional defense contractors; or
3. At least one-third of the total cost of the prototype project is to be paid out of funds provided by sources other than the Federal Government.
Note: Performers must demonstrate compliance with at least one of these conditions in their whitepaper submission.
3.4 Pricing and Schedule
The Performer must structure their business proposal to align with the milestone types defined in
Section 6.0:
• Base Milestones (Prototype Type A - Proof of Concept / Business Process): The
Performer must provide firm, fixed milestone pricing and a detailed resource-loaded schedule (WBS Level 3 or better, exported in the native file format).
• Optional Milestones (Prototype Type E - Operational Utility): The Performer is not required to provide milestone pricing or a Rough Order of Magnitude (ROM) cost estimate. However, the Performer is required to provide an estimated schedule, task durations, and sequence showing how these optional milestones fit into the overall project lifecycle.
3.5 Cybersecurity and CMMC Compliance
Because the project involves Controlled Technical Information (CTI) and Controlled
Unclassified Information (CUI), the Performer must show they possess a Cybersecurity Maturity
Model Certification (CMMC) rating or equivalent safeguards. Performers must explicitly highlight that all cybersecurity requirements flow down to subcontractors and partners, and that overall compliance remains the sole responsibility of the prime Performer.
4.0 Evaluation Details
Whitepapers will be evaluated on the Performer's capability to execute the modernization of the
H-1 Heater within the constraints and performance parameters defined in the Statement of
Objectives. The Government will evaluate submissions using a Best Value determination based on the following criteria of equal importance:
1. Technical Competency and Capability: Evaluation of the Performer's demonstrated capability, engineering experience, and technical approach to meeting all mechanical, electrical, and control system requirements, including safety shutoff valve compliance, SIL 3 burner management systems, and ASME-compliant design.
2. Schedule Feasibility: Evaluation of the realism, logical sequencing, and completeness of the proposed execution schedule, particularly regarding design review gates and coordination of facility outages and road closures.
3. Cost/Price Realism: Evaluation of the completeness, realism, and alignment of the milestone pricing and estimated schedule for unpriced options with the proposed technical approach.
*Pricing Constraints – Proposal Validity:
Based on market standard practices, all Firm-Fixed Price (FFP) submissions for the
Business Process and Proof of Concept (PoC) phases (i.e., Prototype A design milestones for both the Base Requirement and all Optional Projects) must remain valid and binding for a minimum of 180 days from the date of the initial Other Transaction Prototype
(OTP) award. Rough Order of Magnitude (ROM) estimates for subsequent fabrication phases (Prototype E) are exempt from this hold but must reflect accurate market conditions at the time of submission.
5.0 Successful Prototype Definition
Success criteria are defined for each of the prototype types included in this transaction:
5.1 Prototype Type A: Proof of Concept / Business Process [Base Milestones]
• Prototype Goal: To validate the engineering feasibility, safety integrity, and controls compatibility of the H-1 Heater Modernization design before physical fabrication.
• Completion Metrics & Standards:
o Development of a complete, detailed Statement of Work (SOW) and
Requirements Traceability Document (RTD).
o Delivery of an approved Site Plan, Hazard Tracking Log, and Project Risk
Assessment.
o Approval of comprehensive engineering analyses (mechanical, structural, electrical power, and fluid flow) stamped by a licensed Tennessee Professional
Engineer.
o Delivery of detailed schematics and P&ID drawings compatible with AutoCAD, proving controls compatibility with Emerson RX3i PLCs, Proficy software, and
GE Cimplicity HMI.
o Independent safety analysis proving that the Burner Management System (BMS) achieves a Safety Integrity Level (SIL) 3 rating.
• Validation Method: Successful execution and formal sign-off (via AAFB Form 1683) of the five required design review gates: Contractor Readiness Review (CRR), Preliminary
Design Review (PDR), Critical Design Review (CDR), and Final Design Review (FDR), with all deficiencies (AAFB Form 1565) resolved or dispositioned.
5.2 Prototype Type E: Operational Utility [Unpriced Optional Milestones]
• Prototype Goal: To physically demonstrate the operational utility and performance restoration of the modernized H-1 Heater system in an operational testing environment.
• Completion Metrics & Standards:
o Continuous Heating Performance: Demonstrating capability to continuously operate at the original design point as stated in the requirements documents.
o Inlet Pressure Range: Reliable continuous operation across the inlet pressure range stated in the requirements documents.
o Pressure Differential Limit: Verification that total system pressure loss through the heater, inlet, discharge ducting, and valves does not exceed the parameters stated in the requirements documents.
o Safety Valve Timing: Proving that all safety shutoff valves (main and pilot burners) close in less than 1.0 second on loss of power or control signal.
o Thermal Guarding: Verification that all accessible surfaces within 8 ft of working areas do not exceed 120°F.
o Acoustics: Sound levels must not exceed the parameters stated in the requirements documents.
o Control Room Interface: Seamless command, feedback, and read-only safety diagnostics communication between the local PLC, the BMS, and the central
AEDC Plant Control System.
• Validation Method: Successful physical execution of the approved Verification Plan and
System Test Plan (including on-site, air-on testing in coordination with AEDC personnel), completion of training, and formal sign-off of the Verification Readiness
Review (VRR) and System Readiness Review (SRR).
6.0 Program Milestones
The execution schedule is structured into sequential milestones. Every milestone must be completed and approved by the Government to progress the program. No specific target dates are included; the Performer shall propose durations and sequencing in their whitepaper.
Milestone Type Prototype
Mapping SOW Deliverable Reference
Milestone 1:
Project Kickoff
Meeting
[Base
Milestone]
Proof of
Concept /
Business
Process
(Type A)
Statement of Work (SOW), Requirements
Traceability Document (RTD)
Milestone 2:
Contractor
Readiness
Review (CRR)
[Base
Milestone]
Proof of
Concept /
Business
Process
(Type A)
CRR Package, Project Schedule, Risk
Assessment Matrix
Milestone 3:
Preliminary
Design Review
(PDR)
[Base
Milestone]
Proof of
Concept /
Business
Process
(Type A)
PDR Package, Process System Schematics, Mechanical Drawings/Analysis, Structural
Drawings/Analysis, Electrical/Control Design, O&M Plan (Draft), Verification Plan (Draft)
Milestone 4:
Critical Design
Review (CDR)
[Base
Milestone]
Proof of
Concept /
Business
CDR Package, Finalized Site Plan, Process
System Schematics, Mechanical/Structural/Electrical Drawings &
Process
(Type A)
Analysis, Demolition Plan (Draft), Manufacturing
Plan (Draft), Installation Plan (Draft), Verification & System Test Plan (Draft)
Milestone 5:
Final Design
Review (FDR)
[Base
Milestone]
Proof of
Concept /
Business
Process
(Type A)
FDR Package (Approved State), Construction
Drawings, Final SOW & RTD, Finalized
Demolition/Manufacturing/Installation Plans, Approved Verification & System Test Plans
Milestone 6:
Completion of
Fabrication and
Installation
[Unfunded
Option]
Operational
Utility (Type
E)
As-Built Drawings, System Configuration, Demolition/Manufacturing/Installation
Completion Evidence
Milestone 7:
Verification
Readiness
Review (VRR)
[Unfunded
Option]
Operational
Utility (Type
E)
VRR Package, User Manuals, Training Material, Personnel Qualifications
Milestone 8:
Performance
Testing and
Demonstration
[Unfunded
Option]
Operational
Utility (Type
E)
Performance Testing Results, Demonstration
Results, Verification Summary, RTD (Final)
Milestone 9: On-
Site Training and Orientation
[Unfunded
Option]
Operational
Utility (Type
E)
Completed Training Records, Operational
Handoff Documentation
Milestone 10:
System
Readiness
Review (SRR)
[Unfunded
Option]
Operational
Utility (Type
E)
SRR Package, Signed AEDC-1683 indicating
Approval, Certified Modernized H-1 Heater
System
7.0 Submission Details
• Submission Deadline: 24 September 2026
• Submission Format: Electronic submission via secure portal in PDF format. Technical and Business volumes must be separated. Schedules must be attached in native formats
(Primavera .xer or MS Project .mpp).
• Government Point of Contact (POC):
Haley M. K. Smith, Agreements Officer
AFTC/PZIA (Arnold) haley.smith.10@us.af.mil
8.0 Attachments
The following reference documents govern this modernization effort:
mailto:haley.smith.10@us.af.mil
1. Attachment 1: Statement of Objectives (SOO) H-1 Heater Modernization
2. Attachment 2: Performance Parameters (Distribution D, Export)
3. Attachment 3: Appendix A – Reference Drawings (Distribution D)
4. Attachment 4: Appendix B – Design Review Expectations
5. Attachment 5: Appendix C – AEDC Standards
6. Attachment 6: Appendix D – Road Load Limits (Distribution D)