This is a Request for Information (RFI) seeking industry feedback on the potential use of Project Labor Agreements (PLA) for an electrical distribution system repair project at Naval Station Everett, Washington. The design-build construction project includes repairing a 12.47 kV electrical distribution system, replacing separable splices with pad mounted sectionalizing cabinets, and ensuring base-wide electrical distribution meets UFC 3-550-01 standards.
The project is valued between $25-100 million with an anticipated 830-day performance period. NAVFAC Northwest requires responses to a questionnaire addressing contractor experience with PLAs, labor availability, wage comparisons, and potential cost impacts. Responses are due by December 20, 2024 at 12:00 PM PST via email to emily.m.slate.civ@us.navy.mil and jodus.d.hortin.civ@us.navy.mil. The project falls under NAICS code 236220 and has a DPAS rating of DO-C2. This market research will not result in a contract award and is for planning purposes only.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Labor Agreement (PLA) Request for Information (RFI) for Construction Project for Building Requirements, RM21-0324 - Electrical Distribution Feeder System Repair, Naval Station Everett, Naval Facilities Engineering Systems Command (NAVFAC) Northwest, Everett, WA
This is a request for information/market survey. This is not a request for proposal, request for quote, or an invitation for bid. There will be no solicitation, specification, or drawings available at this time.
Description: Naval Facilities Engineering Systems Command (NAVFAC), Northwest is soliciting comments from the public addressing the potential use of Project Labor Agreements (PLA) for the following construction project. The construction project is for building requirements in support of RM21-0324 Electrical Distribution Feeder System Repair, Everett, located in Washington State. The designated Defense Priorities and Allocation System (DPAS) priority rating for this project is DO-C2.
Construction may include, but is not limited to: Repair of existing 12.47 kV electrical distribution system including conductors and switches. Replacement of separable splices (bolt-T connections) with pad mounted sectionalizing cabinets and spice cabinets. Contractor must provide reliable and safe 12.47 kV electrical distribution base wide per Unified Facilities Criteria (UFC) 3-550-01 Exterior Electrical Power Distribution. Project will be design-build (DB). NAICS Code: 236220. In accordance with DFARS 236.204, the magnitude of construction is anticipated to be between $25,000,000 and $100,000,000. General period of performance is anticipated to be approximately 830 calendar days.
A PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement as described in 29 U.S.C. 158 (f). Federal Acquisition Regulation (FAR) policy states: Executive Order (E.O.) 14063, Use of Project Labor Agreements for Federal Construction Projects, requires agencies to use PLAs in large-scale construction projects (defined as a construction projects with a total estimated cost at or above $35M) to promote economy and efficiency in the administration and completion of Federal construction projects. When awarding a contract in connection with a large-scale construction project, agencies shall require use of a PLA for contractors and subcontractors engaged in construction on the project, unless an exception(s) at FAR 22.504(d) applies. Reference is made to: FAR Subpart 22.5 Use of Project Labor Agreements for Federal Construction Projects; provision, FAR 52.222-33 Notice of Requirement for Project Labor Agreement; and to clause, FAR 52.222-34 Project Labor Agreement.
In consideration of the above factors, and any others which may be deemed appropriate, the public is invited to provide responses on the use of a PLA for this construction project utilizing the attached questionnaire.
This is not an announcement of the availability of a solicitation nor is it a means of generating a plan holder’s list. This survey is for planning purposes only and shall not be construed as a Request for Proposal or as an obligation on the part of the Government. The Government does not intend to award a contract on the basis of this market survey or otherwise pay for the requested information. The Government will not provide a debriefing on the results of this survey. All information will be held in a confidential manner and will only be used for the purposes intended.
Submission Instructions: Responses shall be submitted on the attached questionnaire via email to emily.m.slate.civ@us.navy.mil and jodus.d.hortin.civ@us.navy.mil no later than 12:00 p.m. PST, 20 December 2024. Please title the subject line of your e-mail as “(Insert Company Name) – RM21-0324 PLA RFI Questionnaire – N4425525RF005”. Emails can be no larger than 5 MB in size. If more than 5 megabytes are needed, more than one email may be sent.
PLA Questionnaire Company Name: ________________________ Address: ________________________ UEI: ________________ CAGE Code: ________________
Point of Contact Name, Title, Phone Number, Email Address: ________________________
| Questions |
| Responses |
1) Are you responding as a representative of a government entity, union, contractor (union or non-union) and/or qualified small business?
2) Would the work involve specialized construction that is available from only a limited number of contractors or subcontractors? Explain in detail.
3) What is your understanding of the availability of union labor and non-union labor in this area for this type of project? Are you otherwise aware of national, regional, or local interest in participating in this project by union or non-union contractors. Explain in detail.
4) As a qualified contractor for a project of this type, would you be interested in participating in this project?
Would the requirement of a Project Labor Agreement (PLA) under this project impact your interest in any way? Explain in detail.
5) Are you aware of PLAs having been used on other similar construction projects in the area and/or other nearby areas? Explain in detail.
6) How do union wage rates compare to prevailing wage rates for this type of project and in this area, i.e., prevailing wage rates under the Construction Wage Rates Requirements statute (formerly known as the Davis-Bacon Act). Explain in detail.
7) Are there any ways in which the requirement of a PLA might increase costs on a project of this type in this area? Explain in detail.