Ridgway G Loop Electrical.pdf
PDF 1 MB Posted
- Attached to
- Ridgway SP - G Loop Electric, REPLACE
- Solicitation number
- IFB1 : 2024000150
- Issued by
- Ouray County, Colorado
About this file
This document is the bid specification for the Ridgway SP - G Loop Electric project issued by the Colorado Division of Parks and Wildlife. The project consists of installing an electrical distribution system in the Pa-Co-Chu-Puk G Loop campground located in Ridgway State Park, including removing existing electrical components and connecting to the existing primary service. The new system will provide 50-amp service at the campsites, and water and sewer connections will also need to be relocated. An optional pre-bid conference is scheduled for March 6, 2024, and bids are due by March 19, 2024, with a tentative contract award on April 5, 2024 and a notice to proceed on April 29, 2025. The contract completion date is tentatively set for July 28, 2025.
The bid schedule includes over 30 bid items for various electrical components, infrastructure removal and replacement, and site work. Payment will be based on unit prices, with mobilization paid in two installments. The bid requires a 5% bid bond for proposals over $50,000 and 100% performance and labor/material bonds for contracts over $150,000. Preferences are available for Service-Disabled Veteran-Owned Small Businesses and for using at least 80% Colorado labor. The project is subject to Davis-Bacon prevailing wage requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ADDENDUM 1.pdf | ||
| Ridgway G Loop Electrical_Drawings.pdf | ||
| SBP-6.14 BidBond.docx | DOCX document | |
| APPENDIX.pdf | ||
| Pre-Bid Meeting Agenda_G Loop.pdf | ||
| Pre-Bid Attendance List_G Loop Electric.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ridgway SP - G Loop Electric
BIDDING AND CONTRACT INFORMATION
PROJECT NO. C24RG1
IFB1: 2024*0150
PRE-BID CONFERENCE: 03/06/2024 at 2:00 pm
BID OPENING: 03/19/2024 at 1:30 pm
TABLE OF CONTENTS
C24RG1
BIDDING AND CONTRACT INFORMATION
Starting Page
Invitation for Bids Bid Schedule Measurement and Payment Instructions to Bidders Apprenticeship Utilization Survey Contractor’s Qualifications and References
SPECIFICATIONS
CONSTRUCTION DRAWINGS
APPENDICES
Appendix A .......................................... Labor and Material Bond and Performance Bond
Appendix B ............................................... General Conditions for Capital Construction
Appendix C ................................................................ Sample Construction Contract
Appendix D ................................................................ Davis Bacon Prevailing Wages
END OF TABLE OF CONTENTS
INVITATION FOR BIDS
The Colorado Division of Parks and Wildlife is accepting sealed bids for installing an electrical distribution system in the Pa-Co-Chu-Puk G Loop campground located in Ridgway State Park.
The project also includes removing some existing electrical components and completing connections to the existing primary service. The new system will be configured to provide 50-amp service at the campsites. Water and sewer connections will also need to be moved.
Sealed bids will be received by Colorado Parks and Wildlife, 6060 Broadway, Denver CO 80216 until 03/19/2024 at 1:30 pm, after which the bids will then be made public. Bids shall be submitted using the form provided in the project specifications. On-line bid submittals are not accepted.
A five-percent (5%) Bid Bond, certified check, or cashier’s check is required with bid proposals of $50,000.00 or more.
Optional Pre-bid conference: 03/06/2024 at 2:00 pm at the project site.
Project Address: Ridgway State Park
28555 HWY 550
Ridgway, CO 81432 Ouray County
Project Coordinates: Latitude: 38°14'55.73"N Longitude: 107°45'50.11"W View Google Map Location
Contractor Questions: All questions related to the project shall be submitted via e-mail to the Design Engineer, Joel Catlin at joel.catlin@state.co.us. The deadline for questions is 03/12/2024 at 5:00 pm. Questions submitted after the deadline will not be addressed. All questions and answers will be posted as solicitation amendments on the Vendor Self Service (VSS) website. Bidders may not automatically be notified of the existence of a modification or addendum. It is the responsibility of the bidder to check the VSS website periodically to see if any modifications have been issued. Failure to retrieve such modifications and include their provisions in your bid response may result in your bid being deemed non-responsive.
Plans and specifications are available for all bidders on the web at: www.colorado.gov/vss
The following is a tentative project schedule, which will be revised and expanded by the selected Contractor and submitted to the Project Manager for review:
OPTIONAL PRE-BID CONFERENCE 03/06/2024 at 2:00 pm
WRITTEN QUESTIONS DUE 03/12/2024 at 5:00 pm
BID OPENING 03/19/2024 at 1:30 pm
NOTICE OF AWARD 04/05/2024 (Tentative)
NOTICE TO PROCEED 04/29/2025 (Tentative)
SUBSTANTIAL COMPLETION 7/28/2025 (Tentative) https://www.google.com/maps/@38.2464068,-107.7638838,2033m/data=!3m1!1e3?entry=ttu http://www.colorado.gov/vss
BID SCHEDULE
DEPARTMENT OF NATURAL RESOURCES
COLORADO PARKS AND WILDLIFE
STATE OF COLORADO
Proposes to furnish all labor, equipment, materials, and incidentals needed to complete the Ridgway SP - G Loop Electric. The work shall be completed in 120 calendar days from the date of the Notice to Proceed. We have read and made, the “Instructions to Bidders”, the “General Conditions for Capital Construction”, the Written Specifications, and the Construction Drawings part of this bid.
Technical Specifications related to construction materials and methods for work embraced under this Contract shall consist of references to, but not limited to, the Colorado Department of Transportation Most Current Standard Specifications for Roads and Bridge Construction. Special attention should be given to these references and revisions noted within.
UNITS: LF= linear foot, SF= square foot, SFF= square face foot, LS= lump sum, SY= square yard, CY= cubic yard, TON= tons, AC= acres
Service Disabled Veteran Owned Small Business Statement (SDVOSB): The undersigned bidder shall certify by checking below that the corporation, partnership, or sole proprietorship IS or IS NOT claiming a 5% bid preference in accordance with C.R.S. 24-103-211. SDVOSB certification must be included with your bid.
Is: Is Not:
Colorado Labor: The undersigned bidder shall certify by indicating the percentage of Colorado labor of the total workforce to be utilized for this project in accordance with C.R.S. 8-17-101.
Colorado Labor shall be employed to perform at least 80% of the work on a public works project greater than $500,000.00. A written justification for not meeting this percentage must be included with your bid.
% of Colorado Labor: ___________
Addendum Inclusion Statement: The undersigned bidder shall certify by listing below that all Addendums have been considered and included as part of the Contractor’s proposal. The Addendum numbers that the Contractor has included as part of his proposal shall be listed in the space provided.
Addendums:
Base Bid: Furnish and install all materials and labor for the completion of the Base Bid Improvements per the Construction Drawings and Specifications.
Base Bid Items: Quantity Unit Unit Cost Total Item Cost
1. Mobilization 1 LS $ $
2. Furnish and Install 600A Electrical Panel 2 EA $ $
3. Furnish and Install 400A Electrical Panel 1 EA $ $
4. Furnish and Install Circuit Breakers 100A or less
4 EA
5. Furnish and Install Circuit Breakers 125A or less
4 EA
6. Furnish and Install 100A RV Pedestal 45 EA $ $
7. Furnish and Install Junction Boxes 45 EA $ $
8. Install EV Charging Station Supplied By Owner
2 EA
9. Furnish and Install 3 ½” PVC Conduit for Transformer Feeds
40 LF
10. Furnish and Install 2 ½” PVC Conduit for Transformer Feeds
80 LF
11. Trenching/Boring and Furnishing and Installing 2” PVC Conduit for Secondary Service
3000 LF
12. Trenching/Boring and Furnishing and Installing 1 ½” PVC Conduit for Secondary Service
2500 LF
13. Trenching/Boring and Furnishing and Installing 1 1/4” PVC Conduit for Secondary Service
1600 LF
14. Trenching/Boring and Furnishing and Installing 3/4” PVC Conduit for Pedestal Taps
780 LF
15. Furnish and Install Secondary 3#500MCM Copper Feeds
50 LF
16. Furnish and Install Secondary 3#350MCM Copper Feeds
300 LF
17. Furnish and Install Secondary 3#3/0AWG+6AWG Copper Feeds
2900 LF
18. Furnish and Install Secondary 3#2/0AWG+6AWG Copper Feeds
900 LF
19. Furnish and Install Secondary 3#1AWG+6AWG Copper Feeds
2400 LF
20. Furnish and Install Secondary 3#3AWG+8AWG Copper Feeds
300 LF
21. Furnish and Install Ground Rods, Clamps, GEC
6 EA
22. Remove and Replace Secondary Transformers
3 EA
23. Remove and Replace Transformers Surge Arrestors
3 EA
24. Furnish and Install Meter Enclosures 4 EA $ $
25. Furnish and Install Feeder Demand Sub- Meters
19 EA
26. Remove and Dispose of Existing Service Switches at Transformer Pads
18 EA
27. Remove and Dispose of Existing Concrete Bollards at Transformer Pads
15 EA
28. Remove and Dispose of Existing Yard Hydrant, Piping, Valves, and Electrical RV Pedestals
45 EA
29. Furnish and Install New Yard Hydrant, Service Line, Valves, and Piping
45 EA
30. Move Sanitary Sewer Connection 45 EA $ $
31. Furnish and Install 4” Concrete Flatwork 250 SF $ $
32. Perform Revegetation 1 LS $ $
Base Bid AMOUNT _$______________________
Base Bid AMOUNT:(PLEASE WRITE OUT BID AMOUNT)
DOLLARS
(A Corporate Signature Block)
Company Name
A Corporation
Date , 20
Colorado VSS Vendor ID# (if available) _____________________________________
By President Attested to by Secretary
(A Partnership Signature Block) A limited partnership of , general partner;
doing business as (dba)
Company Name
Colorado VSS Vendor ID# (if available) _____________________________________ by General Partner
(A Sole Proprietorship Signature Block) A Sole Proprietorship of (dba)
Colorado VSS Vendor ID# (if available) _____________________________________ by Owner
MEASUREMENT AND PAYMENT
The following descriptions delineate the Work, materials, and how measurements of completed Work will be made and paid for, for each bid item in the Bid Schedule. The Bidder is to read these definitions and price their proposal accordingly.
Bid Item 1 – Mobilization This bid item includes the mobilization of personnel, equipment and supplies at the project site in preparation for the Work, as well as the establishment and maintenance for the duration of the Contract of the Contractor’s sanitary facilities, protective fencing and barricades not included elsewhere, necessary facilities, and all other costs incurred or labor and operations which must be performed prior to beginning the other items under the Contract. This item shall include any costs for required bonding of this project. This item shall also include marshalling, disassembly and security of all items indicated on the Construction Drawings or Specifications or installed as part of mobilization and demobilization from the site. Payment will be made in two installments: the first 60% will be paid on the first month’s pay estimate, and the remaining 40% after the final cleanup has been completed and approved.
Bid Item 2 - Furnish and Install 600A Electrical Panel This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to provide a 600A electrical panel as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit and conductors, connection and testing, backfill, compaction, and compaction testing. Payments will be made based on a completed, installed electrical panel at the bid price for each electrical panel.
Bid Item 3 - Furnish and Install 400A Electrical Panel This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to provide a 400A electrical panel as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit and conductors, connection and testing, backfill, compaction, and compaction testing. Payments will be made based on a completed, installed electrical panel at the bid price for each electrical panel.
Bid Item 4 - Furnish and Install Circuit Breakers 100A or less This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to provide a 100A or less circuit breaker as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit and conductors, connection and testing, backfill, compaction, and compaction testing. Payments will be made based on a completed, installed circuit breaker at the bid price for each circuit breaker.
Bid Item 5 - Furnish and Install Circuit Breakers 125A or less This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to provide a 125A or less circuit breaker as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit and conductors, connection and testing, backfill, compaction, and compaction testing. Payments will be made based on a completed, installed circuit breaker at the bid price for each circuit breaker.
Bid Item 6 - Furnish and Install 100A RV Pedestal This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to provide a 100A RV pedestal as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing. Payments will be made based on a completed, installed RV pedestal at the bid price for each RV pedestal.
Bid Item 7 - Furnish and Install Junction Boxes This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to provide junction boxes as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing. Payments will be made based on a completed, installed junction box at the bid price for each junction box.
Bid Item 8 - Install EV Charging Station Supplied By Owner This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to install an EV charging station provided by Owner as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing. Payments will be made based on a completed, installed, functioning EV charging station at the bid price for each EV charging station.
Bid Item 9 - Furnish and Install 3 ½” PVC Conduit for Transformer Feeds This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services furnish and install 3 ½” PVC conduit from the transformer to the panel board as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing.
Payment will be made at the contract unit price, in linear feet, for the actual distance from the transformer to the panel board.
Bid Item 10 - Furnish and Install 2 ½” PVC Conduit for Transformer Feeds This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to furnish and install 2 ½” PVC conduit from the transformer to the panel board as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing.
Payment will be made at the contract unit price, in linear feet, for the actual distance from the transformer to the panel board.
Bid Item 11 - Trenching/Boring and Furnishing and Installing 2” PVC Conduit for Secondary Service This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to furnish and install 2” PVC conduit from the panel board to the junction boxes at the campsites as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 12 - Trenching/Boring and Furnishing and Installing 1 ½” PVC Conduit for Secondary Service This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to furnish and install 1 ½” PVC conduit from the panel board to the junction boxes at the campsites as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 13 - Trenching/Boring and Furnishing and Installing 1 1/4” PVC Conduit for Secondary Service This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to furnish and install 1 1/4” PVC conduit from the panel board to the junction boxes at the campsites as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 14 - Trenching/Boring and Furnishing and Installing 3/4” PVC Conduit for Pedestal Taps This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to furnish and install 3/4” PVC conduit from the junction boxes to the pedestal taps at the campsites as noted on the plans and specifications. This pay item includes, but is not limited to: excavation, placement of conduit, backfill, compaction, and compaction testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the junction box to the pedestal.
Bid Item 15 - Furnish and Install Secondary 3#500MCM Copper Feeds This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to bring 3#500MCM copper feeds from the panel board to the junction box as noted on the plans and specifications. This pay item includes, but is not limited to: placement of conductors, connections and testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 16 - Furnish and Install Secondary 3#350MCM Copper Feeds This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to bring 3#350MCM copper feeds from the panel board to the junction box as noted on the plans and specifications. This pay item includes, but is not limited to: placement of conductors, connections and testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 17 - Furnish and Install Secondary 3#3/0AWG+6AWG Copper Feeds This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to bring 3#3/0AWG+6AWG copper feeds from the panel board to the junction box as noted on the plans and specifications. This pay item includes, but is not limited to: placement of conductors, connections and testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 18 - Furnish and Install Secondary 3#2/0AWG+6AWG Copper Feeds This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to bring 3#2/0AWG+6AWG copper feeds from the panel board to the junction box as noted on the plans and specifications. This pay item includes, but is not limited to: placement of conductors, connections and testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 19 - Furnish and Install Secondary 3#1AWG+6AWG Copper Feeds This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to bring 3#1AWG+6AWG copper feeds from the panel board to the junction box as noted on the plans and specifications. This pay item includes, but is not limited to: placement of conductors, connections and testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 20 - Furnish and Install Secondary 3#3AWG+8AWG Copper Feeds This bid item includes all labor, materials, equipment, electrical permit, submittals, and independent testing services to bring 3#3AWG+8AWG copper feeds from the panel board to the junction box as noted on the plans and specifications. This pay item includes, but is not limited to: placement of conductors, connections and testing. Payment will be made at the contract unit price, in linear feet, for the actual distance from the panel board to the junction box.
Bid Item 21 – Furnish and Install Ground Rods, Clamps, GEC This bid item includes all labor, materials, equipment, electrical permit, and submittals to furnish and install ground rods as noted on the plans and specifications. All required components will not be measured or paid for separately, but shall be included in the overall bid price each. Payments will be made based on a completed, installed ground rod at the bid price for each ground rod.
Bid Item 22 - Remove and Replace Secondary Transformers This bid item includes all labor, materials, equipment, electrical permit, and submittals to remove and replace secondary transformers as noted on the plans and specifications. The contractor shall provide for removal and disposal of transformers at an approved off-site location. Payments will be made based on a completed, installed transformer at the bid price for each transformer.
Bid Item 23 – Remove and Replace Transformers Surge Arrestors This bid item includes all labor, materials, equipment, electrical permit, and submittals to replace transformer surge arrestors as noted on the plans and specifications. The contractor shall provide for removal and disposal of surge arrestors at an approved off-site location.
Payments will be made based on a completed, replaced surge arrestor at the bid price for each surge arrestor.
Bid Item 24 - Furnish and Install Meter Enclosures This bid item includes all labor, materials, equipment, electrical permit, and submittals to furnish and install meter enclosures as noted on the plans and specifications. Payments will be made based on a completed, installed meter enclosure at the bid price for each meter enclosure.
Bid Item 25 - Furnish and Install Feeder Demand Sub-Meters This bid item includes all labor, materials, equipment, electrical permit, and submittals to furnish and install feeder demand sub-meters as noted on the plans and specifications.
Payments will be made based on a completed, installed sub-meter at the bid price for each sub-meter.
Bid Item 26 - Remove and Dispose of Existing Service Switches at Transformer Pads This bid item includes all labor, materials, and equipment for the removal of the existing service switches at the transformer pads as noted in the plans and specifications. The contractor shall provide for removal and disposal of service switches at an approved off-site location. Payments will be made based on the removal of the service switch at the bid price for each service switch.
Bid Item 27 - Remove and Dispose of Existing Concrete Bollards at Transformer Pads This bid item includes all labor, materials, and equipment for demolition of the existing concrete bollards at the transformer pads as noted in the plans and specifications. The contractor shall provide for removal and disposal of materials at an approved off-site location. Payments will be made based on the removal of the bollard at the bid price for each bollard.
Bid Item 28 - Remove and Dispose of Existing Yard Hydrant, Piping, Valves, and Electrical RV Pedestals This bid item includes all labor, materials, and equipment for demolition of the existing yard hydrants, associated piping and valves, and electrical RV pedestals as noted in the plans and specifications. The contractor shall provide for removal and disposal of materials at an approved off-site location. Payments will be made based on the removal of the RV pedestals at the bid price for each RV pedestal.
Bid Item 29 - Furnish and Install New Yard Hydrant, Service Line, Valves, and Piping This bid item includes all labor, materials, equipment, submittals, and independent testing services to provide a new yard hydrant. This pay item includes, but is not limited to:
excavation, placement of new service line from the main to the hydrant, tapping saddle, corporation stop, piping, valves, fittings, backfill, compaction, and compaction testing, timbers, gravel, and asphalt. Payments will be made based on a completed, installed yard hydrant at the bid price for each hydrant.
Bid Item 30 – Move Sanitary Sewer Connection This bid item includes all labor, materials, equipment, submittals, and independent testing services to move the existing sanitary sewer connection to the new location shown on the drawings. This pay item includes, but is not limited to: excavation, piping, sewer hatch, concrete, backfill, compaction, and compaction testing. Payments will be made based on a completed moved sewer connection at the bid price for each connection.
Bid Item 31 - Furnish and Install 4” Concrete Flatwork This bid item includes all labor, materials, equipment, submittals, and independent testing services to furnish and install concrete flatwork. This pay item includes, but is not limited to:
excavation, placement of 6” compacted subgrade, compaction and compaction testing, forming and concrete. Payment will be made at the contract unit price, in square feet, for the actual area installed.
Bid Item 32 - Perform Revegetation This bid item includes all labor, materials, equipment, submittals, and independent testing services for site restoration and reseeding at the completion of the project. NOTE that there is a Ridgway - specific seed mix called for in the project specifications. This pay item includes, but is not limited to: grading, top soiling, and reseeding. All required components will not be measured or paid for separately, but shall be included in the overall lump sum price. Payment will be made at the lump sum bid price, with progress payments authorized based on percentage of the project completed.
As a footnote to the bid items, the following items have NOT been included as specific pay items and ARE to be considered incidental to the construction for which they are required:
Testing
State electrical permits and inspections
Water, watering, and dust control
Dewatering
Temporary facilities and utilities
Traffic control
Barricades and other required safety provisions
This concludes the bid items listed in the proposal. The only payments made under this contract are for the bid items listed herein, and no additional payments will be made to the Contractor for work specified or shown in these Contract Documents. If any discrepancies exist, the Contractor shall notify the Project Manager in writing, requesting clarification.
END OF SECTION
INSTRUCTIONS TO BIDDERS
PROJECT: Ridgway SP - G Loop Electric
PROJECT NO: C24RG1
1. Bidders must review the plans and specifications, construction site and conditions in their entirety, and determine the problems that may be encountered in performing the work.
The bidder shall include any costs associated with his/her findings in the prices quoted in the proposal. Documents will be available on the State of Colorado VSS website www.colorado.gov/vss. No additional copies of the drawings and specifications will be provided by the Division of Parks and Wildlife at any time before or after the bid opening.
2. All work must conform to the requirements stated in the “General Conditions for Capital Construction”.
3. All questions concerning this project shall be in writing directed to the Project Manager identified in the Invitation for Bids. The Invitation for Bids also identifies important dates and deadlines for this project.
4. BID SCHEDULE:
A. The bidder shall include on the signature page, their Vendor ID (if available) obtained from registration on the Colorado VSS website.
B. The bidder shall complete the Minority Business, Service Disabled Veteran Owned Small Business and Colorado Labor statements as well as acknowledge addendum(s) on the first page of the Bid Schedule.
C. All bid items shall include a unit and extended price or the bid will be disqualified. The bidder shall write in words and numerically the total base bid and add/alternate (if applicable) amounts on the included Bid Schedule. If conflicts exist between the written words and the numerical amount, the actual line item unit cost shall take precedence.
D. The Bid Schedule shall be signed manually in ink:
1) If the bidder is a corporation, use the corporate signature block, insert the name of the state in which the company was incorporated, and include the Employer Identification Number (E.I.N.) in the appropriate spaces. The bid must be signed by an officer (President or Vice President), and the title indicated. The signature of the officer shall be attested to by the Secretary and properly sealed. Cross out incorrect titles and insert correct ones, if necessary.
2) If the bidder is a partnership, use the partnership signature block. Cross out the word "Limited" if the partnership is a general one. Print each partner's name and note the proportion of the partnership that each partner has. The majority or general partner must sign the proposal. The same person must sign the contract, if awarded. Print the company name in the appropriate space.
3) If the bidder is a proprietorship, use the sole proprietorship signature block, print in the owner's name, Social Security number, and the business name in the blanks provided, and the owner signs the owner blank.
5. BID BOND: A bid bond is required for all competitive sealed bids when the price exceeds
$50,000. A bid guarantee in an amount not less than five percent (5%) of the total bid price must be submitted in the form of a firm commitment, such as a bid bond, bank money order, certified check or cashier's check. Checks or money orders should be made payable to the Treasurer, State of Colorado. An irrevocable letter of credit is not acceptable as a bid guarantee. Failure to furnish a bid guarantee in the proper form and amount by the time set for opening of bids may be cause for rejection of the bid.
6. PERFORMANCE BOND, LABOR AND MATERIAL BOND: The successful bidder shall furnish a bond in the amount of 100% of the contract price for performance and for material and labor payment when bid is equal to or exceeds $150,000. The bond shall be executed on the standard State of Colorado form. The State requests that the Surety and Contractor leave the date of the Contract found on the first page of each bond form, blank and we will ‘pen’ in the date after the Controller executes the Contract. These bonds will be submitted along with the standard State Agreement form within 10 days of the "Notice of Award."
7. RESIDENT BIDDER PREFERENCE: When a contract for commodities or services is to be awarded to a bidder (projects >$500,000), a resident bidder shall be allowed a preference against a nonresident bidder equal to the preference given or required by the state in which the nonresident bidder is a resident. (§24-103-906 C.R.S.) A resident bidder is authorized to transact business in the State of Colorado, maintains a place of business in Colorado and pays unemployment compensation taxes.
8. SERVICE DISABLED VETERAN OWNED SMALL BUSINESSES (SDVOSB’s): SDVOSB’s, who are incorporated or organized in Colorado or maintain a place of business or have an office in Colorado and who are officially registered and verified as a SDVOSB by the Center for Veteran Enterprise within the U.S. Department of Veterans Affairs. (www.vip.vetbiz.gov), may receive a 5% preference on their bid. This preference applies only to the price, and the SDVOSB’s must still meet all other qualifications required in the bid. SDVOSB’s claiming this preference shall submit documentation of SDVOSB certification Issued through the U.S. Department of Veterans Affairs in their response to the solicitation. Bid submissions without this documentation will not be given a preference.
9. COLORADO LABOR: Colorado Labor shall be employed to perform at least eighty percent (80%) of the work on a public works project (>$500,000) per CRS 8-17-101. BIDS/CORE notice to require bidder to indicate 80% Colorado labor in bid or proposal and provide written justification if the 80% Colorado labor is not included in the bid. The justification is a requirement of the bid or proposal submittal. State Agency shall waive the 80% requirement and post justification on its web site; if there is reasonable evidence to demonstrate insufficient Colorado labor to perform the work and, if compliance with the 80% would create an undue burden that would substantially prevent a project from proceeding to completion.
Posting of the agency’s written waiver should include but not be limited to contractor’s justification for insufficient available Colorado labor and the agency’s determination that there is an undue burden negatively impacting the project schedule, budget/appropriation, quality/standards of care or any other specific requirement of the project due to compliance with the 80% Colorado labor requirement. The posting of rational should be made on the date of the award and remain for not less than thirty (30) calendar days in a conspicuous web site location of the state agency under the title – “Reporting Requirements for Public Projects as per HB13-1292”.
10. BUILD AMERICA, BUY AMERICA
A. As required by Section 70914 of the Bipartisan Infrastructure Law (also known as the Infrastructure Investment and Jobs Act), P.L. 117-58, on or after May 14, 2022, none of the funds under a federal award that are part of Federal financial assistance program for infrastructure may be obligated for a project unless all of the iron, steel, manufactured products, and construction materials used in the project are produced in the United States, unless subject to an approved waiver. The requirements of this http://www.vip.vetbiz.gov/ section must be included in all sub-awards, including all contracts and purchase orders for work or products under this program. Recipients of an award of Federal financial assistance are hereby notified that none of the funds provided under this award may be used for a project for infrastructure unless:
i. All iron and steel used in the project are produced in the United States--this means all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States;
ii. All manufactured products used in the project are produced in the United States — this means the manufactured product was manufactured in the United States; and the cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product, unless another standard for determining the minimum amount of domestic content of the manufactured product has been established under applicable law or regulation; and
iii. All construction materials are manufactured in the United States—this means that all manufacturing processes for the construction material occurred in the United States.
B. The Buy America preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment that are used at or within the finished infrastructure project, but are not an integral part of the structure or permanently affixed to the infrastructure project.
For further information on the Buy America preference, please visit https://www.doi.gov/grants/BuyAmerica.
Additional information can also be found at the White House Made in America Office website: https://www.whitehouse.gov/omb/management/madein-america
C. Waivers
When necessary, recipients may apply for, and the Department of the Interior (DOI) may grant, a waiver from these requirements, subject to review by the Made in America Office. The DOI may waive the application of the domestic content procurement preference in any case in which it is determined that one of the below circumstances applies:
i. Non-availability Waiver: the types of iron, steel, manufactured products, or construction materials are not produced in the United States in sufficient and reasonably available quantities or of a satisfactory quality;
ii. Unreasonable Cost Waiver: the inclusion of iron, steel, manufactured products, or construction materials produced in the United States will increase the cost of the overall project by more than 25 percent; or
iii. Public Interest Waiver: applying the domestic content procurement preference would be inconsistent with the public interest.
There may be instances where an award qualifies, in whole or in part, for an existing DOI general applicability waiver as described at:
https://www.doi.gov/grants/BuyAmerica/GeneralApplicabilityWaivers.
If the specific financial assistance agreement, infrastructure project, or non-domestic materials meets the criteria of an existing general applicability waiver within the limitations defined within the waiver, the recipient is not required to request a separate waiver for non-domestic materials. If a general applicability waiver does not already apply, and a recipient believes that one of the above circumstances applies to an award, a request to waive the application of the domestic content procurement preference may be submitted to the financial assistance awarding officer in writing. Waiver requests shall include the below information. The waiver shall not include any Privacy Act information, sensitive data, or proprietary information within their waiver request.
Waiver requests will be posted to https://www.doi.gov/grants/buyamerica and are subject to public comment periods of no less than 15 days. Waiver requests will also be reviewed by the Made in America Office.
1. Type of waiver requested (non-availability, unreasonable cost, or public interest).
2. Requesting entity and Unique Entity Identifier (UEI) submitting the request.
3. Department of Interior Bureau or Office who issued the award.
4. Federal financial assistance listing name and number (reference block 2 on
DOI Notice of Award)
5. Financial assistance title of project (reference block 8 on DOI Notice of
Award).
6. Federal Award Identification Number (FAIN).
7. Federal funding amount (reference block 11.m. on DO Notice of Award).
8. Total cost of Infrastructure expenditures (includes federal and non-federal funds to the extent known).
9. Infrastructure project description(s) and location(s) (to the extent known).
10. List of iron or steel item(s), manufactured goods, and construction material(s) the recipient seeks to waive from Buy America requirements.
Include the name, cost, countries of origin (if known), and relevant PSC or NAICS code for each.
11. A certification that the recipient made a good faith effort to solicit bids for domestic products supported by terms included in requests for proposals, contracts, and nonproprietary communications with the prime contractor.
12. A statement of waiver justification, including a description of efforts made (e.g., market research, industry outreach) by the recipient, in an attempt to avoid the need for a waiver. Such a justification may cite, if applicable, the absence of any Buy America-compliant bids received in response to a solicitation.
13. Anticipated impact if no waiver is issued. Approved waivers will be posted at https://www.doi.gov/grants/BuyAmerica/ApprovedWaivers; recipients requesting a waiver will be notified of their waiver request determination by an awarding officer.
Questions pertaining to waivers should be directed to the financial assistance awarding officer.
D. Definitions
i. “Construction materials” includes an article, material, or supply that is or consists primarily of:
1. non-ferrous metals;
2. plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables);
3. glass (including optic glass);
4. lumber; or
5. drywall.
ii. “Construction Materials” does not include cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives.
iii. “Domestic content procurement preference’’ means all iron and steel used in the project are produced in the United States; the manufactured products used in the project are produced in the United States; or the construction materials used in the project are produced in the United States.
iv. “Infrastructure” includes, at a minimum, the structures, facilities, and equipment for, in the United States, roads, highways, and bridges; public transportation; dams, ports, harbors, and other maritime facilities; intercity passenger and freight railroads; freight and intermodal facilities; airports; water systems, including drinking water and wastewater systems; electrical transmission facilities and systems; utilities; broadband infrastructure; and buildings and real property.
Infrastructure includes facilities that generate, transport, and distribute energy.
v. ‘‘Project’’ means the construction, alteration, maintenance, or repair of infrastructure in the United States.
11. APPRENTICESHIP UTILIZATION CERTIFICATION: In order to comply with CRS 24-92-115 regarding statutorily required utilization of apprenticeship programs for certain trades, the awarded bidder will be required to complete a copy of the compliance form available at <https://drive.google.com/file/d/1J4MSGuLyZTO3FgTcvgKrybAoalDkC8am/view> prior to execution of the contract. Please indicate on the Apprenticeship Utilization Survey document attached to the solicitation. Please review the “Special Considerations for Public Projects” section of the Contract Sample for additional details regarding applicable apprenticeship utilization statutes.
12. SUBMITTAL OF BID: The completed Bid must be received by the deadline identified in the Invitation for Bid. You must include as part of your bid the following items:
A. Provide completed Bid Schedule as described above.
B. Provide Bid Bond as described above.
C. SDVOSB certification issued through the U.S Department of Veterans Affairs (if applicable).
D. Colorado Labor Justification if not using 80% Colorado Labor (if applicable).
E. Apprenticeship Utilization Survey.
F. Contractor’s Qualifications and References Statement.
This information is to be enclosed in a sealed envelope marked "SEALED BID". Include the bid opening date and time.
https://drive.google.com/file/d/1J4MSGuLyZTO3FgTcvgKrybAoalDkC8am/view
The envelope shall be addressed to:
ATTN: Joel Catlin
CAPITAL DEVELOPMENT PROGRAM
COLORADO PARKS AND WILDLIFE
6060 BROADWAY
DENVER, CO 80216
Bidders Name and Address should appear in the Upper Left Corner of the envelope.
13. METHOD OF AWARD: The lowest responsible bid, taking into account the Colorado resident bidder preference provision of Colorado Law, will be determined by and the purchase order or contract will be issued, to the extent that the total dollar amount is within available funds to finance the construction. If all bids exceed such amount, the right is reserved to reject all bids. The Division of Parks and Wildlife reserves the right to reject any or all proposals, to waive informalities, and to accept any proposal deemed desirable.
Additive alternates will be used in determining the lowest responsible bidder within the amount available to finance the contract, added in the numeric order listed. An equal number of alternates shall be added to the base bid of each bidder within funds available to finance the contract for purposes of determining the lowest responsible bidder.
The bidder must be registered to do business in the State of Colorado with the Secretary of State www.sos.state.co.us. A Certificate of Good Standing will be required to process the Agreement.
If Federal funds are utilized for this project, the contract cannot be awarded to a contractor which has been disbarred or suspended or is otherwise excluded from or ineligible for participation in federal assistance programs. The excluded parties list can be found at the following web site: https://www.sam.gov/
14. UNIT COST: The price quoted in the proposal shall include the costs of labor, materials, equipment, and incidentals required to provide a fully complete and functioning unit as shown and described in the plans and specifications. The price stated in the proposal shall be complete, and represent total payment for each item in the proposal. No additional payment will be made for the work presented in the proposal.
15. INSURANCE: The successful bidder will be required to submit proof of insurance at the time of executing the agreement. Proof of insurance must be submitted on certificates showing the minimum coverage amounts.
A. The Contractor is required to procure and maintain at all times during the term of this contract the insurance coverage listed below:
1) Workers’ Compensation and Employer’s Liability Insurance, as required by state statute, including occupational disease, covering all of contractor or subcontractor employees acting within the course and scope of their employment.
2) Commercial General Liability Insurance written on ISO occurrence form CG 00 01 10/93 or equivalent, covering premises operations, fire damage, independent contractors, products and completed operations, blanket contractual liability, personal injury, and advertising liability with minimum limits as follows:
a. $1,000,000 combined single limit written on an occurrence basis;
b. $1,000,000 general aggregate;
c. $1,000,000 products and completed operations aggregate; and http://www.sos.state.co.us/ https://www.sam.gov/
d. $50,000 any one fire.
e. If any aggregate limit is reduced below $1,000,000 because of claims made or paid, the contractor shall immediately obtain additional insurance to restore the full aggregate limit and furnish to the State a certificate or other document satisfactory to the State showing compliance with this provision.
3) Automobile Liability Insurance covering any auto (including owned, hired and non-owned autos) with a minimum limit as follows: $1,000,000 each accident combined single limit.
4) The State of Colorado shall be named as an Additional Insured on the Commercial General Liability, Automobile Liability, policy insurance certificates and Colorado Parks and Wildlife must be named as the certificate holder for all coverages 1-3 noted above (leases and construction contracts will require the additional insured coverage for completed operations on endorsements CG 2010 11/85, CG 2037, or equivalent). Coverage required of the contract will be primary over any insurance or self-insurance program carried by the State of Colorado.
B. The Insurance shall include provisions preventing cancellation or non-renewal without at least 45 days prior notice to the State by certified mail.
C. The Insurance shall include a waiver of subrogation for all coverages.
D. The contractor will require all insurance policies in any way related to the contract and secured and maintained by the contractor to include clauses stating that each carrier will waive all rights of recovery, under subrogation or otherwise, against the State of Colorado, its agencies, institutions, organizations, officers, agents, employees and volunteers.
E. All policies evidencing the insurance coverage required hereunder shall be issued by insurance companies satisfactory to the State. No later than 15 days prior to the expiration date of any such coverage, the contractor shall deliver the State certificates of insurance evidencing renewals thereof.
16. If the successful bidder, upon acceptance of his bid by the OWNER, fails to execute such further contractual documents, and give such bond(s) (including any necessary coinsurance or reinsurance agreements) as may be required within ten (10) days after receipt of the Notice of Award, the contract may be terminated for default. In such event the CONTRACTOR shall be liable for any cost of procuring the work which exceeds the amount of his bid, and the bid guarantee shall be available toward offsetting such difference.
17. The bidder is not to give any information concerning his proposal to any other bidder or receive any information concerning another proposal.
18. SALES TAX: The Division of Parks and Wildlife is exempt from paying Colorado sales tax.
Any materials and supplies purchased for this contract are exempt. The Contractor will need to obtain an exemption number from the Department of Revenue for this project and each subcontractor is required to obtain one under the general contractor.
19. QUANTITIES: Quantities stated in the bid schedule and construction documents are estimates only and may increase or decrease during construction. The contractor will perform the required quantity of work based on the unit prices stated in the Bid Schedule except as provided in Section 4.2 of the "General Conditions for Capital Construction."
20. WORK STOPPAGE: Work stoppage is a possibility. The contractor must request all shutdowns or stoppages in writing. If a shutdown is granted, the Division will pay for only work that has been totally completed. No advanced payment of mobilization will be made.
21. CONSTRUCTION SCHEDULE: The Contractor shall submit a written project schedule and supporting data to the Project Manager as soon as possible after the receipt of the Notice of Award. The schedule shall describe key milestones and duration of project activities.
The supporting data for the schedule shall include a complete list of anticipated submittals and due dates, and the key ordering and delivery lead times. The Contractor shall schedule the sequence of construction to consider the delivery of long lead-time items. It shall be the Contractor's responsibility to notify the Project Manager of any problem in conforming to the Contract Documents, Specifications, and Construction Drawings for any element of the proposed improvements prior to its construction.
22. SCHEDULE OF SUBCONTRACTORS, MAJOR EQUIPMENT AND MATERIALS SUPPLIERS: The
Contractor shall provide the Owner, prior to the commencement of any Work, a detailed listing of subcontractors and major equipment and materials suppliers indicating their name, address, description of service or equipment and materials being provided, if they are a…
This is the start of the file's text. The full file is on GovTribe.