This is an Addendum #1 for Richmond Community Schools regarding the replacement of entrance doors at both the Elementary School and High School locations. The project has a completion deadline of April 1, 2025, though bidders can propose alternative completion dates with justification. The scope includes replacing doors at Richmond High School (doors 12 and 13, serving men's and women's locker rooms) and Will L. Lee Elementary School (doors 32, 33, and 35). Specific requirements include recessed exterior handles, gray exterior finish to match existing doors, and keyed mullions for the Lee Elementary doors.
The document provides photographic documentation of the current doors at both locations. The high school doors are currently blue with signage identifying locker rooms, while the elementary school doors show a mix of blue doors (32 and 33) and gray doors with vision panels (35). For additional hardware specifications beyond the rough outline provided, bidders must schedule an appointment with the Director of Human Resources. No pricing information, funding sources, or set-aside requirements are specified in this addendum.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum #1
REPLACEMENT OF ENTRANCE DOORS - ELEMENTARY SCHOOL AND HIGH SCHOOL
April 1, 2025, is a tight deadline for this work to be completed. Is this a hard deadline, or does this have some flexibility?
If the project completion date of April 1, 2025, is not possible, bidders should include an alternate later date for completion and the justification for the later date.
Should the exterior handles be recessed to match the other doors in the district?
Yes
Exterior finish, should it be painted blue or gray to match the other doors?
Gray to match the other doors
Should the Mullions at the Lee doors (door numbers 32, 33, and 35) have a keyed Mullion?
Yes
Will any hardware sets be released beyond the rough outline listed under each proposal heading?
Please make an appointment with Jamie Thiel, Director of Human Resources, by emailing to jthiel@richmond.k12.mi.us.
Are there any pictures or drawings detailing the orientation/ intent of the openings being replaced?
Door numbers 12 and 13 at Richmond High School:
mailto:jthiel@richmond.k12.mi.us
Door numbers 32, 33, and 35 at Will L. Lee Elementary School: