This document is a Contract Discrepancy Notice template issued by the Idaho Transportation Department (ITD) for performance monitoring related to the procurement of a self-propelled broom. The notice serves as a formal mechanism for ITD to document compliance issues identified during contractor performance oversight. The template is structured to identify discrepancies requiring contractor response and observations that may warrant future attention. The document includes designated sections for detailed descriptions of non-compliance issues, relevant contract references, required corrective actions, contractor resolutions with estimated completion dates, and ITD approval or rejection of proposed remedies. The notice format requires sign-off from both the contractor and ITD contract monitor to document understanding of deficiencies and confirmation of resolution.

The discrepancy notice process outlined in this document establishes a formal monitoring and correction protocol without specifying pricing terms, set-asides, incumbent vendor information, or funding sources. The template indicates that multiple discrepancies can be addressed within a single notice through additional tables as needed, and distinguishes between mandatory contractor responses to identified discrepancies and optional responses to observations. Contract-specific details such as the final contract number, exact contract name, and performance specifications are referenced as "TBD" or to be inserted, indicating this is a standardized form adapted for the self-propelled broom procurement. The document does not contain information regarding budget allocation, funding sources, or special contracting designations for this particular acquisition.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ879 - Attachment 5 - Contract Discrepancy Notice

Contract No:
TBD
Contract Name:
Self Propelled Broom

Discrepancy Information: This Contract Discrepancy Notice identifies the Discrepancy(ies) found by ITD while monitoring the Contractor’s performance required per the referenced contract. Items identified as “Discrepancy” require a response from the Contractor. Items identified as “Observation” are areas of concern that may lead to a future Discrepancy if not addressed. Observations do not require a response unless otherwise noted in this notice.

ITD has identified the following Discrepancy(ies):

(Add additional tables for multiple discrepancies)

Description of Discrepancy:
Describe the discrepancy in detail and explain how the contractor is out of compliance. Attach photos or other supporting documents and reference here.
Contract Reference:
Site the document name, attachment #, and section # of the requirement out of compliance.
Required Action:
Site the required corrective action from the contract.
Contractor’s Resolution:
Contractor to describe action that will be taken to correct the discrepancy in order to become compliant with the contract.
Estimated Resolution Date:
Contractor to provide estimated date it anticipates resolving the discrepancy by.

ITD Contract Monitor - Check appropriate box with regard to Contractor’s resolution

Accept ☐
Partially Accept ☐
Reject ☐

Reason for Rejection or Partially Accepted

Anticipated Follow Up Date on Resolution

ITD Contract Monitor Signature

Date

Contractor - Sign below to indicate your understanding of the Discrepancy(ies) and your responsibility for resolution.

Contractor Printed Name

Title

Contractor Signature

Date

Resolution

ITD Contract Monitor – Sign below to indicate that each Discrepancy has been resolved based on the actions detailed in the Contractor’s Resolution for each Discrepancy.

ITD Contract Monitor Signature

Date

ITD has identified the following Observations (no response required):

Description of Observation:
Describe the observation in detail and explain how it may lead to a non-compliance issue in the future. Attach photos or other supporting documents and reference here.
Contractor’s Response (optional):
Contractor to describe action that will be taken to correct the discrepancy in order to become compliant with the contract.

2 | Page dhb RFQ879 Self Propelled Broom 04/25 image1.png

File details come from the government source that posted it. Updated .