This document is a Questions and Answers (Q&A) file for Request for Quote (RFQ) 47QMCA26Q0002, which concerns the procurement of trailers for the Navy. The solicitation involves purchasing 37 break-bulk trailers with specific technical requirements, including air ride suspension with a dump valve, ISO pockets with removable locks compatible with 20', 40', and 6'8" containers, and chain/key slots. The procurement is a small business set-aside under NAICS code 336212, with no preference for contractors who have previously built similar trailers for the Navy. The previous contract (47QMCA18D000G) was awarded to American Material Handling for 33 trailers under solicitation 47QSMD20R0001.
Key details include restrictions on international sourcing, with products from China and India not being acceptable, and all delivery locations within the United States. The government will evaluate past performance according to RFO-2025-12.203(a)(2) and is using simplified procedures under the Revolutionary FAR Overhaul. The solicitation will have a short extension for final questions and answers, as noted in Amendment 003. Technical specifications include requirements for suspension type, load securement, and container compatibility, with some details to be clarified by EXWC (Expeditionary Warfare Center) during the procurement process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Please verify the quantity. The SAM description states qty of 34 but Attachment 1 states qty of 37.
Answer: The RFQ Description in SAM was partially incorrect, written as thirty-seven but numbered as “34”. See Amendment 001 for correction.
2. Can you provide clarification on how “Past Performance” will be evaluated?
Answer: Past performance shall be evaluated in accordance with RFO-2025-12.203(a)(2), Past Performance.
3. Is the government looking for overall Past Performance, or past performance on a specific build?
Answer: Past performance shall be evaluated in accordance with RFO-2025-12.203(a)(2), Past Performance.
4. Is there a preference for contractors who have previously built and delivered this trailer to the Navy based on specific build past performance?
Answer: No, there is no preference for previously awarded requirements.
5. Is there previous solicitation/award information available? (i.e. contract awardees, contract number, specs, delivery/quantity information, etc.)
Answer: Yes, the previous contract number is 47QMCA18D000G, American Material Handling with a quantity of 33 from solicitation 47QSMD20R0001.
6. Do you have a “scoring weight” for how this will be awarded? (i.e. Past Performance, Special Features, Warranty, Maintenance Availability, Delivery Terms/Schedule)
Answer: No, this procurement is under simplified procedures listed in RFO-2025-12 of the Revolutionary FAR Overhaul.
7. Please confirm if any of these trailers will be shipped overseas (for FET calculation purposes).
Answer: All delivery locations are listed on RFQ47QMCA26Q0002 and all are in the United States.
8. Please confirm whether using Asian, Indian or Chinese products that adhere to the specifications are acceptable?
Answer: The US does not have trade agreements with China or India and those sources of supply will not be considered. “Asian” refers to a continent with many countries to include China and India. The US does not have a trade agreement with the Asian continent but does with some countries in Asia.
9. Can the Government confirm if the break-bulk trailer is a flatbed or provide a sample photo?
Answer: Yes
10. Have these trailers been procured before with similar specifications?
Answer: Yes, they have been procured in the past with similar specifications.
11. May we request an extension to the response time?
Answer: See Amendment 003 to RFQ47QMCA26Q0002
12. Non-Manufacture Rule Question: FAR Clause 52.219-6 Notice of Total Small Business Set-
Aside applies in this solicitation. According to the ‘SBA Non-manufacturer Rule Class Waiver List’, a waiver applies to NAICS code 336212. It is our understanding there is a ‘Notice to waive the Nonmanufacturer Rule’ for ‘Trailers’ according to Federal Register Volume 73 No 235 Page 74220 (December 5th, 2008); and a waiver for ‘Truck Trailer’ according to Federal Register Volume 74 No 77 Page 18603 (April 23, 2009). For this solicitation does a waiver apply to allow a small business to propose a large manufacturer’s trailer?
Answer: The clause concerning the non-manufacture rule is RFO 52.219-33, Non- Manufacture Rule and is prescribed at RFO-2025-19.104-3(e)(1)(2). This clause was not incorporated in the RFQ per the prescription.
13. Suspension question: There are a few sub-categories of air ride:
Fixed, the suspension system doesn’t move and isn’t adjustable Slide, the suspension system’s placement can be adjusted along a portion of the trailer Slide Rear, the rear axle can slide (like above) and the front axle is fixed
Can you please clarify the requirement?
Answer: Air ride suspension shall include a dump valve to allow (Hold, raise, lower with auto dump), located at rear, recessed in to back of trailer. Sliding rear axle(s) are not specified and are not required
14. Load Securement question: The specification indicates “Chain/key slots (outer and center)”.
What is the required quantity?
Answer: EXWC shall clarify quantities, GSA suggests same as stake pockets- 24” on center.
15. Auxiliary Features:
The specification indicates “ISO pockets with removable locks”. Can you please provide more details?
Answer: The ISO pockets with removeable, interchangeable locks shall be compatible with the specified 20’ + 40’ ISO containers and6’8” Tricon containers.
16. Would the Government consider extending the RFQ closing date?
Answer: There will be a short extension to post the final questions and answers. See Amendment 003.