Washburn Hall Renovations Contract Documents Summary

This file comprises the standard contract documents and specifications for the Washburn Hall Renovations project at the University of Rhode Island Kingston Campus, a state-funded construction initiative managed by the State of Rhode Island Department of Administration, Division of Purchases, in coordination with the University of Rhode Island Board of Trustees. The project involves comprehensive renovation work including selective demolition, structural modifications, mechanical and electrical system upgrades, fire protection installation, and interior finishes across basement through attic levels of the existing building. The contract documents include detailed architectural, structural, mechanical, electrical, and fire protection drawings and specifications organized into 28 divisions covering concrete work, carpentry, thermal protection, doors and hardware, finishes, sprinkler systems, HVAC, and electrical systems. The contract utilizes the AIA Document A101-2017 Standard Form of Agreement with a stipulated sum basis of payment and incorporates AIA Document A201-2007 General Conditions of the Contract for Construction as modified by the Owner. The Design Agent is BL Companies with key representatives including Jessie Moberg, AIA (Architect), John R. Malary, PE (Structural Lead), and Jesse E. Vose, PE (MEP Lead), and the Project Manager is Kayla Verbitsky, AIA, with the University of Rhode Island.

The contract establishes a five percent retainage requirement from each progress payment, with the Owner making payments within thirty working days following written approval and the Design Agent's certificate approval. Final payment is due thirty working days after issuance of the Design Agent's final Certificate for Payment and written approval by the Owner, contingent upon submission of all closeout documentation including as-built plans, warranties, and manuals. Contract modifications require written approval from the Owner, and the contractor must pay subcontractors the full amount within ten working days of receipt of payment from the Owner. Per Rhode Island law, three percent of the Contract Sum is withheld until thirty calendar days after Final Completion and compliance with R.I. Gen. Laws 44-1-6 requirements. The contract is governed by Rhode Island Procurement Regulations and General Laws, which control in case of any conflicts with Contract Documents. Mechanics liens may not be placed against the project per R.I. Gen. Laws 34-28-31, and dispute resolution follows the Public Works Arbitration Act procedures. The contractor must maintain a regular place of business in Rhode Island and must be properly licensed by all necessary governmental authorities to do business in the state.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Standard Contract Documents-State Bid

Rev. 1/2/14

PROJECT MANUAL

Washburn Hall Renovations UCRMD Enabling

University of Rhode Island

Kingston Campus

October 21, 2026

BL Project No.:2503449 URI Project No.: KC.G.WASH.2024.001

Rev. 1/2/14

Owner: University of Rhode Island Board of Trustees, University of Rhode Island and State of Rhode Island

In care of: Office of Capital Program Design & Delivery University of Rhode Island 210 Flagg Road, Suite 204

Kingston, Rhode Island 02881 Attn: Kayla Verbitsky, AIA, Project Manager P: 401.874.2096

Design Agent: BL Companies – Architect Jessie Moberg, AIA, NCARB 2346 Post Road Suite 100, Warwick, RI 02886 tel: 401-400-4492 | direct: 781.619.9509

Consultant: BL Companies – Structural Lead John R. Malary, PE 355 Research Parkway, Meriden, CT 06450 tel: 203.630.1406 | direct: 203.608.2481

Consultant: BL Companies – MEP Lead Jesse E. Vose, PE

355 Research Parkway, Meriden, CT 06450 tel: 203.630.1406 | direct: 203.608.2495

PROJECT MANUAL

Washburn Hall Renovations UCRMD Enabling

University of Rhode Island

Kingston Campus

October 21, 2026

BL Project No.:2503449

BL Companies Standard Contract Documents-State Bid URI Washburn Hall – UCRMD Enabling

Rev. 8/31/26 TABLE OF CONTENTS October 21, 2026 00 0110-1

DOCUMENT 00 0110 - TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 0010 Cover 00 0050 Title Page 00 0110 Table of Contents 00 0115 List of Drawings

00 5200 Agreement Form 00 5200 AIA Document A101 - 2017 00 6140 Waiver of Lien Form 00 7000 General Conditions 00 7000 AIA Document A201 - 2007 00 7200 URI Standard Documents

SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 1000 Summary 01 1010 Attachment A1 – Site Utilization 01 1010 Attachment A2 – Site Utilization Plans 01 1010 Attachment A3 – Site Plan – Lay-Down Area 01 2000 Price and Payment Procedures 01 2010 Attachment A - Price and Payment Procedures 01 2020 Attachment B - MBE Utilization Form 01 2030 Attachment C – Small Project Changes 01 2100 Allowances 01 2600 Contract Modification Procedures 01 3000 Administrative Requirements 01 3010 Attachment A – Administrative Requirements 01 3020 Attachment B – Small Project Changes 01 3100 Project Management and Coordination 01 3233 Photographic Documentation 01 3300 Submittal Procedures 01 3310 Attachment A – Submittal Procedures 01 3320 Attachment B – Small Project Changes 01 4000 Quality Requirements 01 5000 Temporary Facilities and Controls 01 5005 Temporary Project Signage 01 5600 Temporary Protection of Existing Construction 01 5640 Tree Protection and Preservation 01 5716 Temporary Pest Control 01 5719 Temporary Environmental Controls 01 6000 Product Requirements 01 6010 Attachment A – Product Requirements 01 6020 Attachment B – Small Project Changes 01 7000 Execution Requirements 01 7010 Attachment A – Execution Requirements 01 7020 Attachment B – Small Project Changes 01 7300 Execution 01 7320 Waste Management 01 7330 Attachment A – Waste Management 01 7331 Attachment B – Small Project Changes 01 7700 Close Out Procedures 01 7800 Closeout Requirements

October 21, 2026 00 0110-2

01 7810 Attachment A – Closeout Requirements 01 7820 Attachment B – Small Project Changes 01 7823 Operations and Maintenance Data 01 7839 Project Record Documents 01 7900 Demonstration and Training

DIVISION 02 – EXISTING CONDITIONS

02 4119 Selective Demolition

DIVISION 03 – CONCRETE

03 3000 Cast-in-Place Concrete

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 1000 Rough Carpentry

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 9200 Joint Sealant

DIVISION 08 – OPENINGS

08 1113 Hollow Metal Doors and Frames 08 1416 Flush Wood Doors 08 7100 Door Hardware 08 8000 Glazing

DIVISION 09 – FINISHES

09 2116 Gypsum Board Assemblies 09 3000 Tiling 09 3050 Transition Strips 09 5113 Acoustical Panel Ceilings 09 6513 Resilient Base and Accessories 09 6519 Resilient Tile Flooring 09 6723 Resinous Flooring 09 6813 Modular Carpeting 09 9100 Painting

DIVISION 21 – FIRE SUPPRESSION

21 1313 Wet-Pipe Sprinkler Systems

DIVISION 23 – HEATING, VENTILATION, AND AIR-CONDITIONING

23 0050 General Conditions for Mechanical Work 23 0517 Sleeves and Sleeve Seals for HVAC Piping 23 0518 Escutcheons for HVAC Piping 23 0519 Meters and Gages for HVAC Piping and Ducts 23 0523 General-Duty Valves for HVAC Piping 23 0529 Hangers and Supports for HVAC Piping and Equipment 23 0553 Identification for HVAC Piping and Equipment

October 21, 2026 00 0110-3

23 0713 Duct Insulation 23 0719 HVAC Piping Insulation 23 0800 Commissioning for HVAC 23 0923.11 Control Valves 23 0923.12 Control Dampers 23 0923.14 Flow Instruments 23 0923.27 Temperature Instruments 23 2113 Hydronic Piping 23 2116 Hydronic Piping Specialties 23 3113 Metal Ducts 23 3300 Air Duct Accessories 23 3346 Flexible Ducts 23 3713 Diffusers, Registers, and Grilles 23 7223.19 Packaged Indoor Fixed Plate Energy Recovery Units

DIVISION 26 – ELECTRICAL

260050 General Requirements for Electrical Work 260519 Low-Voltage Electrical Power Conductors and Cables 260526 Grounding 260529 Hangers and Supports for Electrical Systems 260530 Firestopping for Electrical Systems 260533 Conduit and Raceways

260548.16 Seismic Controls for Electrical Systems

260553 Identification for Electrical Systems 260923 Occupancy Sensors 262416 Panelboards 262726 Wiring Devices 262813 Fuses 262816 Enclosed Switches and Circuit Breakers 262923 Variable-Frequency Motor Controllers 265119 LED Interior Lighting 265213 Emergency and Exit Lighting

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

284621.11 Addressable Fire-Alarm Systems

END OF DOCUMENT

Rev. 1/2/14 LIST OF DRAWINGS October 21, 2026 00 0115-1

DOCUMENT 00 0115 - LIST OF DRAWINGS

Dwg. No. Drawing Title __

All drawings are dated September 11, 2026

GENERAL

G0.00 COVER SHEET

G0.01 CODE ANALYSIS

STRUCTURAL

S0.01 STRUCTURAL GENERAL NOTES

S1.00 BASEMENT AND FOUNDATION PLAN

S1.01 FIRST FLOOR FRAMING PLAN

S1.02 SECOND FLOOR FRAMING PLAN

S1.03 THIRD FLOOR FRAMING PLAN

S2.00 STRUCTURAL SECTIONS

S3.00 TYPICAL DETAILS

ARCHITECTURAL

A0.01 GENERAL INFORMATION, PARTITION TYPES AND DETAILS

AD1.00 BASEMENT DEMOLITION PLAN

AD1.01 FIRST FLOOR DEMOLITION PLAN

AD1.02 SECOND FLOOR DEMOLITION PLAN

AD1.03 THIRD FLOOR DEMOLITION PLAN

AD1.04 ATTIC DEMOLITION PLAN

AD1.05 ROOF DEMOLITION PLAN

AD2.00 BASEMENT DEMOLITION RCP

AD2.01 FIRST FLOOR DEMOLITION RCP

AD2.02 SECOND FLOOR DEMOLITION RCP

AD2.03 THIRD FLOOR DEMOLITION RCP

A1.00 BASEMENT FLOOR PLAN

A1.01 FIRST FLOOR PLAN

A1.02 SECOND FLOOR PLAN

A1.03 THIRD FLOOR PLAN

A1.04 ATTIC PLAN

A1.05 ROOF PLAN

A2.00 BASEMENT FLOOR REFLECTED CEILING PLAN

A2.01 FIRST FLOOR REFLECTED CEILING PLAN

A2.02 SECOND FLOOR REFLECTED CEILING PLAN

A2.03 THIRD FLOOR REFLECTED CEILING PLAN

A6.01 DOOR SCHEDULE, ELEVATIONS, AND DETAILS

A8.00 BASEMENT AND FIRST FLOOR FINISH PLAN

A8.01 SECOND FLOOR FINISH PLAN & FURNITURE PLAN

A8.02 THIRD FLOOR FINISH PLAN & FURNITURE PLAN

Rev. 1/2/14 LIST OF DRAWINGS October 21, 2026 00 0115-2

FIRE PROTECTION

FP001 FIRE PROTECTION NOTES, DESIGN CRITERIA, LEGEND, &

ABBREVIATIONS

FP102 SECOND FLOOR & THIRD FLOOR PLAN

FP501 DETAILS

MECHANICAL

M001 NOTES, SYMBOL LEGEND, & ABBREVIATIONS

MD102 SECOND FLOOR MECHANICAL DEMOLITION PLAN

MD103 THIRD FLOOR MECHANICAL DEMOLITION PLAN

M102 BASEMENT & SECOND FLOOR MECHANICAL PLANS

M103 THIRD FLOOR MECHANICAL PLAN

M104 ATTIC & ROOF MECHANICAL PLAN

M501 MECHANICAL DETAILS

M502 MECHANICAL DETAILS

M601 MECHANICAL SCHEDULES

ELECTRICAL

E001 ELECTRICAL SYMBOL LEGENDS, NOTES & ABBREVIATIONS

E002 TELECOMMUNICATION NOTES

ED101 BASEMENT FLOOR ELECTRICAL DEMOLITION PLAN

ED102 SECOND & THIRD FLOOR ELECTRICAL DEMOLITION PLANS

E101 BASEMENT & SECOND FLOOR POWER PLANS

E102 THIRD FLOOR & ATTIC POWER PLANS

E122 SECOND & THIRD FLOOR LIGHTING PLANS

E501 DETAILS

E502 DETAILS

E601 PANELBOARD SCHEDULES

E602 SCHEDULES & PARTIAL RISER DIAGRAM

E603 PARTIAL FIRE ALARM RISER DIAGRAM & MATRIX

04/03/15 AGREEMENT FORM

00 5200-1

DOCUMENT 00 5200 – AGREEMENT FORM

PART 1 – GENERAL

1.1 The Agreement Form to be utilized on this project is AIA Document A101-2007 as amended, a copy of which follows this page.

stallardy Text Box A101-2017

Document A101® – 2017 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

Init.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

ADDITIONS AND DELETIONS:

The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added necessary information and where the author has added to or deleted from the original AIA text.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

The parties should complete A101®–2017, Exhibit A, Insurance and Bonds, contemporaneously with this Agreement. AIA Document A201®–2017, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.

AGREEMENT made as of the day of in the year (In words, indicate day, month and year.)

BETWEEN the Owner:

(Name, legal status, address, telephone and facsimile numbers, and website)

State of Rhode Island, acting by and through the Department of Administration, Division of Purchases,One Capitol Hill, Second Floor Providence, Rhode Island 02908-5855

401.578.8100 (telephone); 401.574.8387 (facsimile) www.puchasing.ri.gov and The University of Rhode Island Board of Trustees 35 Campus Avenue, Green Hall Kingston, Rhode Island 02881 on behalf of the User Agency:

(Name, legal status, address, telephone and facsimile numbers, and website)

The University of Rhode Island 45 Upper College Road Kingston, Rhode Island 02881

401.874.1000 (telephone) and the Contractor:

(Name, legal status, address, telephone and facsimile numbers, and website) for the following Project:

(Name, location and detailed description)

The Design Agent:

The Owner and Contractor agree as follows.

Init.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

(Paragraph Deleted)

The Owner and Contractor agree as follows.

TABLE OF ARTICLES

1 THE CONTRACT DOCUMENTS

2 THE WORK OF THIS CONTRACT

3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

4 CONTRACT SUM

5 PAYMENTS

6 DISPUTE RESOLUTION

7 TERMINATION OR SUSPENSION

8 MISCELLANEOUS PROVISIONS

9 ENUMERATION OF CONTRACT DOCUMENTS

EXHIBIT A INSURANCE AND BONDS

ARTICLE 1 THE CONTRACT DOCUMENTS

The Contract Documents consist of this Agreement, Conditions of the Contract (General Conditions, Supplementary Conditions (if any), and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.

ARTICLE 2 THE WORK OF THIS CONTRACT

The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others. No part of the Work shall be performed by Subcontractors without the Owner’s prior written consent.

ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

§ 3.1 The date of commencement of the Work shall be the later of: (i) the issuance of the Purchase Order by the Owner; and (ii) the (Paragraph Deleted) date set forth in a notice to proceed issued by the User Agency.

(Paragraphs Deleted)

§ 3.2 The Contract Time shall be measured from the date of commencement of the Work.

§ 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:

(Check one of the following boxes and complete the necessary information.)

[ ] Not later than ( ) calendar days from the date of commencement of the Work.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

[ ] By the following date:

§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates:

Portion of Work Substantial Completion Date

§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.

ARTICLE 4 CONTRACT SUM

§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. Subject to additions and deductions as provided in the Contract Documents, the Contract Sum shall be:

§ 4.2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum:

Item Price

§ 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement.

(Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.)

Item Price Conditions for Acceptance

§ 4.3 Allowances, if any, are specified in the Bid Proposal Form and are included in the Contract Sum.

(Paragraph Deleted)

(Table Deleted)

§ 4.4 Unit prices, if any, are specified in the Bid Proposal Form and include all costs, including without limitation, labor, materials, services, regulatory compliance, overhead, and profit necessary for the completion of the Work. Unit prices shall be used for both additions to, and deletions from the Work.

§ 4.5 Liquidated damages, if any:

(Insert terms and conditions for liquidated damages, if any.)

.1 In the event that there is one date for Substantial Completion of the Work, the Contractor shall pay the Owner the sum stipulated in this Section 4.5.1 as liquidated damages, and not as a penalty, for each calendar day of delay until the Work is substantially complete: $________________.

.2 In the event that the Project is scheduled to be completed in phases, and there is more than one date for Substantial Completion of the Work, the Contractor shall pay the Owner an aggregate amount equal to the sums stipulated in this Section 4.5.2 as liquidated damages, and not as a penalty, for each calendar day of delay until the Work for each phase is substantially complete:

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

Phase Liquidated Damages Sum

.3 The Owner and the Contractor have reasonably determined the sums set forth in this Section 4.5 to be a fair estimate of the Owner’ actual damages which are difficult to ascertain in the event of delay.

§ 4.6 Other:

(Paragraph Deleted)

The Owner shall not be liable to the Contractor or any Subcontractor for claims or damages of any nature caused by or arising out of any delays. The sole remedy against the Owner for delays shall be the allowance of additional time for completion of the Work.

ARTICLE 5 PAYMENTS

§ 5.1 Progress Payments § 5.1.1 Based upon Applications for Payment submitted to the Design Agent by the Contractor and Certificates for Payment issued by the Design Agent and approved by the Owner in writing, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.

§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month.

§ 5.1.3 The Owner shall make payment of the certified amount, less retainage, to the Contractor not later than the 30 th working day following written approval by the Owner.

(Paragraph Deleted)

§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor and approved by the Design Agent and the Owner in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to substantiate its accuracy, as the Design Agent and the Owner may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment.

§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.

§ 5.1.6 In accordance with AIA Document A201™–2007, General Conditions of the Contract for Construction as modified by the Owner, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:

§ 5.1.6.1 The amount of each progress payment shall first include:

.1 That portion of the Contract Sum properly allocable to completed Work;

.2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing; and

.3 That portion of Construction Change Directives that the Design Agent determines, in the Design Agent’s professional judgment, to be reasonably justified.

§ 5.1.6.2 The amount of each progress payment shall then be reduced by:

.1 The aggregate of any amounts previously paid by the Owner;

.2 The amount, if any, for Work that remains uncorrected and for which the Design Agent has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

A201–2007 as modified by the Owner;

.3 For Work performed or defects discovered since the last payment application, any amount for which the Design Agent may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document A201–2007 as modified by the Owner; and

.4 Retainage withheld pursuant to Section 5.1.7.

§ 5.1.7 Retainage § 5.1.7.1 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold the following amount, as retainage, from the payment otherwise due: five (5%) percent.

(Paragraph Deleted)

§ 5.1.7.1.1 Deleted.

(Paragraph Deleted)

§ 5.1.7.2 Deleted.

(Paragraph Deleted)

§ 5.1.7.3 Except as set forth in this Section 5.1.7.3, upon Substantial Completion of the Work, the Contractor may submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant to this Section 5.1.7. The Application for Payment submitted at Substantial Completion shall not include retainage as follows:

(Paragraph Deleted)

The amount of five (5%) percent shall be retained by the Owner through the date of Substantial Completion of the Work and then after the date of Substantial Completion of the Work in accordance with R.I. Gen. Laws § 37-12- 10.1.

§ 5.1.8 If final completion of the Work is materially delayed through no fault of the Contractor, the Owner shall pay the Contractor any additional amounts in accordance with Article 9 of AIA Document A201–2007 as modified by the Owner.

§ 5.1.9 Except with the Owner’s prior written approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site.

§ 5.1.10 Within 10 working days of receipt of any progress payment from the Owner, the Contractor must pay its Subcontractors the full amount included for each such Subcontractor within the Contractor’s Application for Payment in accordance with the provisions of AIA A201 – 2007, General Conditions of the Contract for Construction as modified by the Owner.

§ 5.2 Final Payment § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, less the amount withheld pursuant to § 5.1.7.3, shall be made by the Owner to the Contractor when:

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Article 12 of AIA Document A201–2007 as modified by the Owner, and to satisfy other requirements, if any, which extend beyond final payment; and

.2 a final Certificate for Payment has been issued by the Design Agent and approved in writing by the Owner;

.3 the Contractor has submitted its final release and final releases from all of its Subcontractors and suppliers in a form acceptable to the Owner; and

4 the Contractor has submitted to the Owner all close-out documents, including without limitation, all as-built plans, warranties, manuals, and other materials set forth in the Contract Documents.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

§ 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 working days after the issuance of the Design Agent’s final Certificate for Payment and written approval by the Owner.

§ 5.3 Interest Payments due and unpaid under the Contract shall bear interest from the date payment is due in accordance with the provisions of “Prompt Payment by Department of Administration,” R.I. Gen. Laws §§ 42-11.1-1 et seq.

§ 5.4 Owner’s Rights § 5.4.1 The Owner shall have the right to deduct from any payments due to the Contractor the amount of any unpaid obligations owed to the State of Rhode Island by the Contractor, including without limitation, any and all unpaid taxes, the amount of any claim against the Contractor arising out of this Agreement, or any amount on account of any other reason permitted by applicable law.

§ 5.5 Pursuant to R.I. Gen. Laws § 44-1-6, the Owner shall withhold payment from the Contractor if the Contractor does not maintain a regular place of business in Rhode Island in the amount of three (3%) percent of the Contract Sum until 30 calendar days after Final Completion and compliance by the Contractor with the requirements of such section. The three (3%) percent withheld pursuant to R.I. Gen. Laws § 44-1-6 is not considered retainage which is held pursuant to § 5.1.7.

(Paragraph Deleted)

ARTICLE 6 DISPUTE RESOLUTION

§ 6.1 Initial Decision Maker Claims shall be referred to the Initial Decision Maker for initial decision. The Purchasing Agent appointed pursuant to the provisions of the “State Purchases Act,” R.I. Gen. Laws § 37-2-1 et seq., will serve as the Initial Decision Maker in accordance with the provisions of the State Purchases Act, State of Rhode Island Procurement Regulations, and this Section 6.1. An initial decision shall be required as a condition precedent to binding dispute resolution pursuant to Section 6.3 of any Claim arising prior to the date final payment is due.

§ 6.2 Mediation For any Claim not resolved by the Initial Decision Maker procedures set forth in Section 6.1, and prior to the implementation of the binding dispute resolution procedures set forth in Section 6.3, the Contractor shall have the option to pursue mediation, exercisable by written notice to the Owner within 30 calendar days of an Initial Decision. In the event of the exercise of such option by the Contractor, the Owner and the Contractor shall attempt to select a mediator, and in the event that the Owner and the Contractor cannot agree on a mediator, either party may apply in writing to the Presiding Justice of the Providence County Superior Court, with a copy to the other, with a request for the court to appoint a mediator, and the costs of the mediator shall be borne equally by both parties.

(Paragraph Deleted)

§ 6.3 Binding Dispute Resolution For any Claim not resolved by the Initial Decision Maker procedures set forth in Section 6.1, or mediation at the option of the Contractor pursuant to Section 6.2, the method of binding dispute resolution shall be determined in accordance with the provisions of the “Public Works Arbitration Act,” R.I. Gen. Laws §§ 37-16-1 et seq.

ARTICLE 7 TERMINATION OR SUSPENSION

§ 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–2007, as modified by the Owner. The Contract may also be terminated by the Owner: (i) in the event of the unavailability of appropriated funds; (ii) in the absence of a determination of continued need; or (iii) as otherwise provided in the State of Rhode Island Procurement Regulations General Conditions of Purchase or other applicable law.

§ 7.1.1 Deleted.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

§ 7.2 The Work may be suspended by the Owner as provided in: (i) the State of Rhode Island General Conditions of Purchase Regulation or other applicable law; or (ii) Article 14 of AIA Document A201–2007 as modified by the Owner.

ARTICLE 8 MISCELLANEOUS PROVISIONS

§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2007 or another Contract Document, the reference refers to: (i) the AIA Document A201 – 2007 or other Contract Document as modified by the Owner; and (ii) that provision in the AIA Document A201 – 2007 as modified by the Owner or other Contract Document as amended or supplemented by other provisions of the Contract Documents.

§ 8.2 Representatives for the Owner § 8.2.1 The Owner’s representative:

(Name, title, address, email address, and other information for the preferred methods of contact)

State of Rhode Island, acting by and through the Department of Administration, Division of Purchases One Capitol Hill Providence, Rhode Island 02903 James H. Libby, AIA, NCARB, LEED AP

401.712.3091 (telephone)

§ 8.2.2 The User Agency’s representative:

(Name, title, address, email address, and other information for the preferred methods of contact)

The University of Rhode Island Capital Program Design & Delivery 210 Flagg Rd., Suite 204 Kingston, Rhode Island 02881 James H. Libby, AIA, NCARB, LEED AP

401.712.3091 (telephone)

§ 8.2.3 The Design Agent’s representative:

§ 8.3 The Contractor’s representative:

§ 8.4 Neither the Owner’s nor the Contractor’s representative nor the Design Agent’s representative shall be changed without 10 working days’ prior notice to the other party.

§ 8.5 Insurance and Bonds § 8.5.1 The Owner and the Contractor shall purchase and maintain insurance as set forth in the Solicitation and elsewhere in the Contract Documents.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

§ 8.5.2 The Contractor shall provide bonds as set forth in the Solicitation and elsewhere in the Contract Documents.

§ 8.6 Deleted.

§ 8.7 Other provisions:

§ 8.7.1 The Contractor represents and warrants to the Owner, in addition to any other representations and warranties of the Contractor elsewhere in the Contract Documents:

.1 The Contractor and its Subcontractors are each financially solvent, able to pay their debts as they mature, and possess sufficient working capital to perform their obligations under the Contract Documents.

.2 The Contractor and its Subcontractors are each able to furnish the tools, materials, equipment, and labor required to complete the Project as required under the Contract Documents.

.3 The Contractor and each Subcontractor are authorized to do business in the State of Rhode Island and are properly licensed by all necessary governmental authorities having jurisdiction over them and over the Work and the Project.

.4 The execution of this Agreement and its performance is within its duly authorized powers.

.5 The Contractor has visited the site of the Project, familiarized itself with the local and special conditions under which the Work is to be performed, and correlated its observations with the requirements of the Contract Documents.

.6 The Contractor possesses the requisite level of experience and expertise in the business administration, construction, and superintendence of projects of the size, complexity, and nature of the Project, and it will perform the Work with the care, skill, and diligence of a contractor possessing such experience and expertise.

§ 8.7.2 The representations and warranties of the Contractor in this Section 8.7 and elsewhere in the Contract Documents will survive the execution and delivery of this Agreement, any termination of this Agreement, and the final completion of the Work.

§ 8.7.3 Any Change Orders or other Modifications must be approved in writing by the Owner.

§ 8.7.4 The Owner is the State of Rhode Island, acting by and through its Department of Administration, Division of Purchases, and therefore, pursuant to the provisions of R.I. Gen. Laws § 34-28-31, mechanics liens may not be placed against the Project.

ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS

§ 9.1 This Agreement is comprised of the following documents:

.1 AIA Document A101™–2017, Standard Form of Agreement Between Owner and Contractor, as modified by the Owner

.2 Deleted.

.3 AIA Document A201™–2007, General Conditions of the Contract for Construction, as modified by the Owner.

.4 Deleted.

.5 Drawings

The Drawings are included in the Solicitation and are available on the Division of Purchases website at www.purchasing.ri.gov.

.6 Specifications

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

The Specifications are included in the Solicitation and are available on the Division of Purchases website at www.purchasing.ri.gov.

.7 Addenda, if any, issued pursuant to the Solicitation form a part of the Solicitation and are available on the Division of Purchases website at www.purchasing.ri.gov.

.8 Supplementary and other Conditions of the Contract, including without limitation, the State of Rhode Island General Conditions of Purchase Regulation.

.9 Other documents listed below:

.1 The Solicitation, issued by the Owner, including without limitation, the Invitation to Bid, the Instructions to Bidders, the Specifications and Drawings, any Addenda, and the Bid Checklist.

.2 The Bid Proposal, including without limitation, the Bid Form and the Bidder Certification Cover Form.

(Paragraph Deleted)

.3 The Purchase Order issued by the Owner.

.4 Contractor’s Initial Milestone Schedule.

§ 9.2 This Agreement and the Contract Documents are subject to, and governed by, the laws of the State of Rhode Island, including all procurement statutes and regulations (available at www.purchasing.ri.gov), and applicable federal and local law, all of which are fully incorporated into this Agreement by this reference.

§ 9.3 In the event of any conflict between or among the Contract Documents, or any Contract Documents and any provision of the State of Rhode Island Procurement Regulations and/or any other provision of the Rhode Island General Laws, the State of Rhode Island Procurement Regulations and the Rhode Island General Laws shall control.

ARTICLE 10 BENEFITS OF AGREEMENT

§ 10.1 The User Agency is a disclosed third-party beneficiary of this Agreement and shall have all of the rights and benefits hereunder to which such a party is entitled. Nothing contained in this Agreement shall create a contractual relationship with, or a cause of action in favor of, any other third party against the Owner or the User Agency.

§ 10.2 This Agreement shall be binding on the Contractor and its successors and assigns; provided, however, that the Contractor may not assign its rights nor delegate its responsibilities under this Agreement without the Owner’s prior written consent.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

This Agreement is entered into as of the day and year first written above; provided, however, that this Agreement shall not become a valid, binding, and enforceable contract unless and until the Owner shall have issued a Purchase Order.

THE STATE OF RHODE ISLAND, acting by and through its Department of Administration, Division of Purchases

OWNER (Signature) CONTRACTOR (Signature)

Abby Benson Sr. Vice President & CFO, Division of Administration and Finance, University of Rhode Island

(Printed name and title) (Printed name and title)

Additions and Deletions Report for AIA® Document A101® – 2017

This Additions and Deletions Report, as defined on page 1 of the associated document, reproduces below all text the author has added to the standard form AIA document in order to complete it, as well as any text the author may have added to or deleted from the original AIA text. Added text is shown underlined. Deleted text is indicated with a horizontal line through the original AIA text.

Note: This Additions and Deletions Report is provided for information purposes only and is not incorporated into or constitute any part of the associated AIA document. This Additions and Deletions Report and its associated document were generated simultaneously by AIA software at 13:25:34 ET on 10/22/2026.

Additions and Deletions Report for AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

(Name, legal status, address and other information)address, telephone and facsimile numbers, and website)

State of Rhode Island, acting by and through the Department of Administration, Division of Purchases,One Capitol Hill, Second Floor Providence, Rhode Island 02908-5855

401.578.8100 (telephone); 401.574.8387 (facsimile) www.puchasing.ri.gov and The University of Rhode Island Board of Trustees 35 Campus Avenue, Green Hall Kingston, Rhode Island 02881 on behalf of the User Agency:

The University of Rhode Island 45 Upper College Road

(Name, legal status, address and other information)address, telephone and facsimile numbers, and website)

Additions and Deletions Report for AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

The Architect:Design Agent:

(Name, legal status, address and other information)address, telephone and facsimile numbers, and website)

The Owner and Contractor agree as follows.

The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, (General Conditions, Supplementary Conditions (if any), and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.

The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others. No part of the Work shall be performed by Subcontractors without the Owner’s prior written consent.

§ 3.1 The date of commencement of the Work shall be:

(Check one of the following boxes.)be the later of: (i) the issuance of the Purchase Order by the Owner; and (ii) the

[ ] The date of this Agreement.

[ ] A date set forth in a notice to proceed issued by the Owner.User Agency.

[ ] Established as follows:

Additions and Deletions Report for AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38)

(Insert a date or a means to determine the date of commencement of the Work.)

If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.

§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be ($ ), subject Subject to additions and deductions as provided in the Contract Documents.Documents, the Contract Sum shall be: $____________.

§ 4.3 Allowances, if any, included in the Contract Sum:are specified in the Bid Proposal Form and are included in the Contract Sum.

(Identify each allowance.)

Item Price

§ 4.4 Unit prices, if any:

(Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)any, are specified in the Bid Proposal Form and include all costs, including without limitation, labor, materials, services, regulatory compliance, overhead, and profit necessary for the completion of the Work. Unit prices shall be used for both additions to, and deletions from the Work.

Item Units and Limitations Price per Unit ($0.00)

.1 In the event that there is one date for Substantial Completion of the Work, the Contractor shall pay the Owner the sum stipulated in this Section 4.5.1 as liquidated damages, and not as a penalty, for each calendar day of delay until the Work is substantially complete: $________________.

.2 In the event that the Project is scheduled to be completed in phases, and there is more than one date for Substantial Completion of the Work, the Contractor shall pay the Owner an aggregate amount equal to the sums

Additions and Deletions Report for AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38) stipulated in this Section 4.5.2 as liquidated damages, and not as a penalty, for each calendar day of delay until the Work for each phase is substantially complete:

Phase Liquidated Damages Sum

.3 The Owner and the Contractor have reasonably determined the sums set forth in this Section 4.5 to be a fair estimate of the Owner’ actual damages which are difficult to ascertain in the event of delay.

(Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.)The Owner shall not be liable to the Contractor or any Subcontractor for claims or damages of any nature caused by or arising out of any delays. The sole remedy against the Owner for delays shall be the allowance of additional time for completion of the

Work.

§ 5.1.1 Based upon Applications for Payment submitted to the Architect Design Agent by the Contractor and Certificates for Payment issued by the Architect, Design Agent and approved by the Owner in writing, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.

§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:month.

§ 5.1.3 Provided that an Application for Payment is received by the Architect not later than the day of a month, the The Owner shall make payment of the amount certified amount, less retainage, to the Contractor not later than the day of the month. If an Application for Payment is received by the Architect after the application date fixed above, payment of the amount certified shall be made by the Owner not later than ( ) days after the Architect receives the Application for Payment.30th working day following written approval by the Owner.

(Federal, state or local laws may require payment within a certain period of time.)

§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor and approved by the Design Agent and the Owner in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of

Additions and Deletions Report for AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:25:34 ET on 10/22/2026 under Order No.3104238454 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA38) values shall be prepared in such form, and supported by such data to substantiate its accuracy, as the Architect Design Agent and the Owner may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment.

§ 5.1.6 In accordance with AIA Document A201™–2017, A201™–2007, General Conditions of the Contract for Construction, Construction as modified by the Owner, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:

.3 That portion of Construction Change Directives that the Architect determines, in the Architect’s Design Agent determines, in the Design Agent’s professional judgment, to be reasonably justified.

.2 The amount, if any, for Work that remains uncorrected and for which the Architect Design Agent has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document A201–2017;

.3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay;A201–2007 as modified by the Owner;

.4 .3 For Work performed or defects discovered since the last payment application, any amount for which the Architect Design Agent may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document…