This document is Addendum No. 2 for the Kmart Site Redevelopment Project (Bid No: RFQ2025-005) issued by the City of Kissimmee on May 8, 2025. The addendum addresses a clarification request regarding the estimated construction cost for the project. Since this is a Request for Qualifications (RFQ), no specific construction cost estimate is provided; instead, proposers are expected to include a detailed pro forma outlining their estimated construction costs as part of their submission requirements. The addendum instructs proposers to acknowledge receipt of the document by completing the applicable section in the RFQ and submitting the form with their proposal.

The addendum does not introduce new substantive details about the project beyond the existing RFQ requirements. Proposers are reminded that all other terms and conditions of the original RFQ remain unchanged. The document includes a standard acknowledgment section for proposers to complete, which requires company information, signature, date, and contact details. The addendum is signed by Brandon Durango, the Procurement Manager, and maintains the procedural formality typical of municipal procurement documents.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

May 8, 2025

Addendum No.2

Project: Kmart Site Redevelopment Project Bid No: RFQ2025-005

TO ALL PROPOSERS:

The following items are clarifications, corrections, additions, deletions and / or revisions, which shall take precedence over the original documents.

Question 1: Please provide the estimated construction cost for this project. Do you foresee the value range being $25M - $50M?

Answer: Since this is an RFQ, we do not have an estimated construction cost at this time. As part of the submission requirements, proposers are expected to include a detailed pro forma outlining their estimated construction costs.

ACKNOWLEDGMENT OF ADDENDA:

1. The proposer shall acknowledge receipt of this addendum by completing the applicable section in the RFQ. The Proposer shall submit said Form with the proposal.

2. All other terms and conditions of the RFQ remain unchanged.

Brandon Durango Procurement Manager

ACKNOWLEDGMENT OF ADDENDA NO.(S) _________ (IF APPLICABLE)

(Signature)

COMPANY NAME _______________________________________

COMPANY ADDRESS _______________________________________

BY: _________________________ DATE:________________________

(signature)

_____________________________ EMAIL:_______________________

(typed name/title of signer)

File details come from the government source that posted it. Updated .