This is a Request for Qualifications (RFQ) issued by the City of Kingman, Arizona, seeking a qualified Construction Manager at Risk (CMAR) for the design and pre-construction services of Fire Station 25. The project involves master planning and pre-construction services for a new fire station, administration building, and possible future dispatch facility totaling approximately 25,000 square feet. The City has partnered with Seabury Fritz Architects, Inc., for programming, site evaluation, and concept design. The CMAR will be responsible for providing real-time cost modeling, constructability input, value engineering, and innovative solutions to expedite the construction schedule while maintaining quality and controlling costs. A pre-submittal conference is scheduled for January 7, 2025, at 12:00 PM at Kingman Council Chambers. Statements of Qualifications are due by January 21, 2025, with SOQ reviews occurring the week of February 2, firm notifications the week of February 16, and City Council approval targeted for March 17. The anticipated construction cost for the project is approximately $7.1 million.
Selection will be qualifications-based, with evaluation criteria including general firm information and organization (15 points), experience and qualifications of the firm and key personnel (40 points), understanding of the project and approach to services (30 points), current workload and ability to start immediately (10 points), and overall evaluation (5 points). The CMAR must hold appropriate Arizona professional and contractor licenses, demonstrate bonding capacity through an A-rated surety company, and present a subcontractor selection plan emphasizing local firm utilization. The firm must self-perform not less than 45 percent of the work in accordance with Arizona law. A Selection Committee will produce a rank-ordered list of three to five top firms, with the City intending to negotiate with the highest-ranked firm and execute a pre-construction services contract. If negotiations fail, the City may proceed with the second or third-ranked firm or terminate the selection process. The City reserves the right to reject any or all submissions and to waive any informality or irregularity.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUALIFICATIONS
CITY OF KINGMAN
CONSTRUCTION MANAGER AT RISK FOR FIRE STATION 25
The City of Kingman (City) is seeking a qualified construction manager/general contractor to provide complete construction services as the Construction Manager at Risk (CMAR) for the Design/ Pre- Construction Services for Fire Station 25.
SECTION I–PROJECT DESCRIPTION
The City of Kingman is designing/constructing a new fire station at parcel number 322-15-010A. The project's goal is to reduce response time and better serve the community. The anticipated limits of the project are shown on a map in Attachment A.
The project will consist of master planning and pre-construction services for a new fire station, administration, and possible future dispatch building of approximately 25,000 SF. The City has entered into a professional services contract with Seabury Fritz Architects, Inc., for programming, site evaluation, and concept design. The CMAR shall work closely with and be an integral part of this project team during the design and construction phases of the project.
This project is a high priority for the City, and the selected CMAR must demonstrate the ability to provide innovative, practical solutions that expedite the construction schedule while maintaining quality and controlling costs. The City intends to procure the CMAR early in the process so the CMAR can support the design team from project initiation through completion by providing real-time cost modeling, constructability input, and value engineering throughout design. The total estimated construction cost for performing the work under this project is expected to be approximately 7.1million.
SECTION II–SCOPE OF WORK
The City will retain the CMAR to represent and promote the City’s interests during both design and construction phases of the project. General roles and responsibilities required of the CMAR include the following:
• Develop and maintain the project cost model and project schedule during both design and construction phases and lead project team in ensuring compliance with critical deadlines, milestone and budgetary targets.
• Actively participate in project coordination meetings, design reviews and partnering sessions.
• Apply the CMAR’s best expertise, knowledge and skills to identify and recommend alternatives to advance the project’s interests.
• Advise the City of ways to gain efficiencies in project delivery and reduce overall project delivery time frame.
• Provide a truly collaborative process, which leverages all parties’ expertise and strengths.
• Actively contribute to the advancement and development of the project.
• Prepare and submit a Guaranteed Maximum Price (GMP) proposal that complies with the project cost model and project budget.
• Bear complete risk for any costs in excess of the GMP.
• Comply with the City’s contracts for CMAR design phase and construction phase services without modification.
CONSTRUCTION MANAGER AT RISK FOR
FIRE STATION 25
Anticipated scope items for each phase of the project are listed below:
Design Phase
During the design phase, services by the CMAR may include (but not be limited to):
• Detailed construction estimates based upon knowledge of marketplace conditions
• Detailed cost model that validates the project’s budget, with stated assumptions
• Updates and refinements to the cost model as design is finalized
• Advice regarding materials, material costs, and escalations
• Subsurface utility and soil investigations, if deemed necessary
• Utility company coordination
• Provide long-lead procurement studies and initiate procurement of long-lead items
• Documented constructability reviews that shall minimize construction issues and RFI’s.
• Construction sequencing to optimize overall construction time
• Concurrence with the plans, contract, and specifications prior to construction
• Early establishment of contractor’s indirect costs such as general conditions, fee, bonds, insurance, tax, and overhead.
• At the 95% design milestone, prepare and submit a Guaranteed Maximum Price (GMP) proposal that aligns with the established project cost model and remains within the project budget.
Construction Phase
Construction phase services by the CMAR may include (but not be limited to):
• Serve as the general contractor during construction
• Coordinate with various City departments and other agencies, utility companies, etc.
• Arrange for procurement of materials and equipment
• Schedule and manage site operations
• Award and manage all construction related contracts and subcontracts while meeting the City goals including use of local firms. The City prefers that local firms be employed to the maximum extent practicable.
• Provide quality controls
• Bond and insure the construction, as required by the contract
• Comply with all federal, state and local permitting requirements
• Deal with Owner issues
• Maintain a safe work site for all project participants.
• Prepare and turn over record drawings
Prior to construction, the CMAR will assume the risk of delivering the project through a guaranteed maximum price contract. The CMAR will be responsible for construction means and methods and will be allowed to self-perform the work in accordance with Arizona law (CMAR will be required to self-perform not less than forty-five percent of the work). For all subcontracts, the CMAR will be required to solicit bids based on their subcontractor selection plan that complies with Arizona law. If the CMAR and the City cannot agree on the final GMP, the City reserves the right to end negotiations and commence discussions with the next-ranked firm or end the procurement under this advertisement.
SECTION III–PRE-SUBMITTAL CONFERENCE
A pre-submittal conference will be held on January 7, 2025, at 12:00 PM Local Time at the Kingman Council Chambers, 310 N. Fourth Street, Kingman, AZ 86401. At this meeting, the design team, including City staff, will discuss the scope of work, general contract issues and respond to questions from the attendees. This pre-submittal conference is not mandatory but is highly recommended for all interested firms.
SECTION IV–STATEMENT OF QUALIFICATIONS SELECTION CRITERIA
The CMAR will be selected through a qualifications-based selection process. Firms interested in providing CMAR services must submit a Statement of Qualifications (SOQ) that addresses the following issues:
A. General Information. (15 points)
1. (5 points) Provide a general description of the firm and/or team that is proposing to provide CMAR services. Explain the legal organization of the proposed firm or team. Provide an organization chart showing key personnel.
2. (5 points) Provide the following information:
a. List the Arizona professional and contractor licenses held by the firm/team and the key personnel who will be assigned to this project. Provide the license number and explain if held by an individual or the firm.
b. Identify any contract or subcontract held by the firm or officers of the firm, which has been terminated within the last five years. Identify any claims (public or private, including third party claims) arising from a contract which resulted in litigation or arbitration within the last five years. Briefly describe the circumstances and the outcomes.
c. Describe the firm’s bonding capacity. Include as an appendix a letter from an A- or better surety company that substantiates the firm’s/team’s stated bonding capacity. (Said letter included in the appendix will not count towards the maximum page limit of the SOQ).
3. (5 points) Briefly describe your subcontractor selection plan. The selection of subcontractors must be based on qualifications or a combination of qualifications and price, but should not be based on price alone. (Note: your Subcontractor selection plan will be included in the CMAR contract.) Discuss the amount of work that may be performed by local subcontractors including suppliers and services.
B. Experience and qualifications of the firm/team and key personnel. (40 points)
1. (15 points) Provide a list of projects (at least two) of comparable character, size, budget and complexity on which the firm/team served as either the CMAR or General Contractor. For each project provide the following information:
a. Description of the project, including name and location.
b. Role of the firm (specify whether CMAR or General Contractor).
c. Role of each key team member who worked on the reference project and the percentage of the time spent on said project
d. Project’s original contracted construction cost and final construction cost. Explain the difference.
e. Construction dates
f. Project Owner
g. Reference information (two names with current telephone numbers/email addresses per project).
Preference will be given to firms that have experience with alternative project delivery methods (i.e. CMAR, Design Build or JOC) on successful projects.
2. (20 points) Highlight each key person’s experience in the following areas: role in delivering past CMAR or alternative delivery projects, experience working in a collaborative environment in both the pre-construction and construction phases, analyzing and generating innovative alternatives and evaluating them using real time pricing, constructing water facilities in commercial areas and being an advisor to an Owner.
3. (5 points) List any proposed subcontractors, including key staff names and the experience and qualifications of these individuals.
C. Understanding of the project and approach to performing the required services.
(30 points)
1. (10 points) Discuss the major issues your team has identified on this project and how your team will mitigate them. Critical project issues considered are constructability concerns, risk areas affecting the project delivery, design concerns, permitting, utilities, material availability and project costs.
2. (10 points) List specific innovations and/or innovative approaches for the project illustrating potential project savings, schedule acceleration, risk reductions and improved quality your team can deliver.
3. (5 points) Discuss the particular expertise your team offers and how you propose to use this expertise to benefit and add value to the project.
4. (5 points) Describe your understanding of the CMAR role for the project and its responsibilities. Describe your approach to performing preconstruction services.
D. Current workload and the ability of the project team to start immediately. (10 points)
1. Provide a table or list that summarizes the current major assignments of all key team members, percentage of time committed to each assignment, anticipated end date of major assignments, and percentage of time to be committed to this project. Also include a statement as to when the team would be available to start work on this project. Firms that demonstrate their ability to start immediately and to effectively manage this project, in addition to their current workload, will be scored the highest.
E. Overall evaluation of the firm/team and its perceived ability to provide the required services. (5 points)
This is to be determined by the selection panel members. No submittal response is required.
SECTION V–SUBMITTAL REQUIREMENTS
Firms interested in the above project should submit a SOQ clearly identifying this project on the cover of the SOQ which includes a one-page cover letter and address the SOQ criteria. Resumes for each key team member should be attached to the SOQ. The SOQ shall be uploaded on OpenGov as indicated.
Submittals will only be accepted through OpenGov. Failure to comply with these instructions will be grounds for disqualification.
SECTION IV–SELECTION PROCESS AND SCHEDULE
A Selection Committee will evaluate each SOQ according to the above criteria and will be based solely on qualifications of the firm/team. The selection panel will produce a rank-ordered list of at least the top three, but no more than five firms. Interviews may be conducted as part of the selection process.
The City intends to enter into negotiations with the top-ranked firm and execute a contract upon completion of negotiation of fees and contract terms for City Council approval as soon as possible.
If the City is unsuccessful in negotiating a contract with the best-qualified team, the City may then negotiate with the second or third most qualified team until a contract is executed, or may decide to terminate the selection process.
The following tentative schedule has been prepared for this project:
SOQ submittal date January 21 SOQ reviewed by committee week of February 2 Firms notified of selection week of February 16th City Council approval of pre- March 17th construction services contract
Instructions. The City of Kingman shall not be held responsible for any oral instructions. Any changes to this Request for Qualifications will be in the form of an addendum in OpenGov, which will be furnished to all registered Request for Qualifications holders.
Any person or firm desiring to submit a protest in connection with the procurement shall follow the procedures stated in Arizona Revised Statutes 34-603 J.
City Rights. The City of Kingman reserves the right to reject any or all SOQs, to waive any informality or irregularity in any SOQ received, and to be the sole judge of the merits of the respective SOQs received.
Questions. Questions regarding this solicitation must be submitted online through the OpenGov portal. Questions must be received by no later than the date and time specified in the timeline included in this RFQ (Questions Due From Proposers).