This Request for Qualifications/Request for Proposal (RFQ-P 6570) is issued by the Town of Trumbull Board of Education for material testing services related to the construction of the new Hillcrest Middle School located at 530 Daniels Farm Road, Trumbull, Connecticut (State Project No. 144-0108N). The project encompasses construction of a new approximately 139,283 square-foot, multi-story building with associated infrastructure including underground utilities, geothermal well field, drives, and walkways, along with demolition of the existing middle school building and replacement with playing fields. The Design Team is led by TSKP Studio, with Michael Horton Associates, Inc. serving as Structural Engineer-of-Record, Bismark Construction as Construction Manager, and Arcadis-US, Inc. as Project Manager. Proposals must be submitted by May 15, 2026, at 2:00 PM to Richard Kotchko, Interim Purchasing Agent, at Trumbull Town Hall, 5866 Main Street, Trumbull, Connecticut 06611, in one original and three exact copies plus one electronic copy on thumb drive or CD in a sealed envelope. The last day to submit requests for information is May 8, 2026, at 5:00 PM. Firm selection is anticipated for May 26, 2026, with construction anticipated to begin July 6, 2026, and be completed by December 2028. The Hillcrest Middle School Building Committee will make the final award determination following review and recommendations from the Town and its project consultants.
All lump sum fees and hourly rates quoted must remain firm fixed for 90 days from the date of proposal opening. No separate travel expense charges are permitted, and all travel costs must be included in unit prices. Administration charges in addition to quoted charges are not allowed. Overtime will be considered only when technicians or inspectors are on-site for more than eight hours in one day, with weekday overtime and Saturday hours charged at one-and-one-half times the straight-time rate and Sunday and federal holiday hours at two times the straight-time rate. Responding firms must provide hourly rates for all staff by title for any additional material testing services not included in the base contract. The Material Testing Firm must obtain and maintain comprehensive insurance coverage including Workers' Compensation (statutory limits), Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Business Automobile Liability ($1,000,000 per occurrence), Professional Liability ($1,000,000 per claim/aggregate for five years post-substantial completion), and Excess Umbrella Liability ($2,000,000). The project is funded through Town referendum approval and State of Connecticut funding. Bidders must submit copies of certifications, evidence of personnel qualifications meeting special inspection requirements, prior experience on similar projects, references from at least five clients served in the past five years, and a non-collusion affidavit.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN of TRUMBULL
BOARD OF EDUCATION
NEW SCHOOL CONSTRUCTION PROJECT
MATERIAL TESTING SERVICES
REQUEST FOR QUALIFICATIONS / REQUEST FOR PROPOSAL
RFQ-P:6570 DUE: May 15, 2026, AT 2:00PM
GENERAL INFORMATION
New Hillcrest Middle School, located at 530 Daniels Farm Rd, Trumbull, CT 06611, State Project No. 144-0108N
1. PROJECT DESCRIPTION
The Town of Trumbull, on behalf of the Hillcrest Middle School Building Committee (HMSBC), is seeking to contract with a qualified firm to provide material testing services for construction of the new Hillcrest Middle School. The project includes construction of a new building, anticipated to be approximately 139,283 square feet, with portions that will be multi-story. The project also includes new underground utilities, a geothermal well field, drives, and walkways. The existing middle school building will be demolished and replaced with playing fields.
The Design Team is led by TSKP Studio, the Structural Engineer-of-Record is Michael Horton Associates, Inc., the Construction Manager is Bismark Construction, and the PM is Arcadis-US, Inc. The Trumbull Board of Education has been awarded funding through referendum approval and State funding for a new Hillcrest Middle School, with a Building Committee selected to bring the project to fruition.
| 2. | PREPARATION FOR PROPOSALS |
| a) | Bids shall be submitted by using the enclosed BID PROPOSAL FORMS that accompanies this request. Submit one (1) ORIGINAL and three (3) exact copies and one (1) EXACT ELECTRONIC COPY on a thumb drive or a CD. Bidders should submit bids in a clear, concise and legible manner to permit proper evaluation of responsive bids. Submission shall be in a sealed envelope and plainly marked on the outside as “MATERIAL TESTING SERVICES”. The envelope shall bare on the outside the name of the proposer and its address. |
| b) | Bidders may also submit, under separate cover with their proposal, any samples of reports and documents that are necessary to meet the requirements (deliverables) such as Bid bond, all qualifications, reference, subcontractors if applicable, non-collusion form as noted of this request should a purchase order and Contract be awarded. |
| c) | No oral, email, telephone or telegraphic responses will be considered. Proposals received after the advertised time and date due shall not be opened or considered. The Town reserves the right to communicate with any or all of the proposers to clarify the provisions of Proposals. The Town further reserves the right to request additional information from any proposer at any time after proposals are opened. |
3. PROPOSAL SUBMISSION
a) Proposals are to be completed (unless directed otherwise in the specifications), printed, signed by an authorized agent, and sealed in an envelope (including all official literature, brochures, etc., which support this request) and addressed as follows:
RFP #6570 DUE: May 15, 2026, at 2:00 PM
MATERIAL TESTING SERVICES
Trumbull Town Hall – Attn: Richard Kotchko, Interim Purchasing Agent 5866 Main Street, Trumbull CT 06611
b) All Proposals must be made on the enclosed Proposal form. All blank spaces for Proposal prices must be filled in, in ink or typewritten, and the proposal form must be fully completed and executed when submitted.
c) The party signing the formal proposal must be authorized by your organization to contractually bind your firm with regard to prices and related contractual obligations for the contractual period requested.
d) The Town reserves the right to correct, after proposer verification, any mistake in a proposal that is a clerical error, such as a price extension or decimal point error.
4. PROPOSAL RESPONSE TIME
Responses to this request shall be received at the office of the Purchasing Agent, Town Hall prior to the advertised hour (noted above) of opening, at which time all proposals (total proposal amount only) shall be publicly opened and read aloud. A proposer may withdraw a proposal at any time prior to the above scheduled date and time. Any proposal received after the above scheduled date and time shall not be considered or opened. No proposer may withdraw a proposal within Ninety (90) days after the actual proposal opening.
5. TOWN OPTIONS
The Town reserves the right to accept all or any part of a proposal, reject any or all proposals and to waive any requirements, informalities or irregularities, technical defects or non-material deficiencies in a proposal. The Town also reserves the right, if applicable, to award the purchase of individual items under this RFP to any combination of separate proposals or proposers. The award shall be made after careful consideration of all factors including but not limited to price.
6. TAX EXEMPT
The Town of Trumbull is exempt from the payment of taxes imposed by the Federal Government and/or State of Connecticut. Such taxes must not be included in the proposal price. The Town of Trumbull Tax Exempt number is 05-010 31-000.
| 7. | INQUIRIES & ADDENDUMS |
| a) | All technical inquiries regarding this request may be directed to Robert Tencza at robert.tencza@arcadis.com. All other questions shall be directed to Richard Kotchko (203) 452.5042 rkotchko@trumbull-ct.gov . |
b) No inquiries shall be responded to that are received after May 8, 2026, by close of business 5pm.
c) Answers to questions the Town deems to be in the interest of all proposers will be posted as an addendum on the Town web site under Purchasing/Bid Opportunities.
d) The Town reserves the right to communicate with any or all of the proposers to clarify the provisions of this request; the Town further reserves the right to request additional information from any proposer at any time after proposals are opened.
e) It is the sole responsibility of a proposer to verify any addendums that may have been issued relating to this request prior to submission of a proposal. Any notice of addendum shall be published on the Town website (www.trumbull-ct.gov ) in the Purchasing Department Section (Bid Notices) . Submission of a response that does not address any changes or addendums may result in a disqualification of a proposal submission.
8. ASSIGNMENT OF RIGHTS, TITLES, AND INTERESTS
Any assignment or subcontracting by a proposer, bidder, supplier, or contractor for work to be performed, or Goods and/or services to be provided, in whole or in part, and any other interest in conjunction with a Town Procurement shall not be permitted without the express written consent of the Town of Trumbull
9. HOLD HARMLESS CLAUSE
Any contractor or subcontractor of the Town agrees to indemnify, hold harmless and defend the Town from and against any and all liability for loss, damage or expense which the Town may suffer or for which the Town may be held liable by reason of injury, including death, to any person or damage to any property arising out of or in any manner connected with the operations to be performed under this request and subsequent Contract, whether or not due in whole or in part of any act, omission or negligence of the Town or any of its representatives or employees.
10. WORK REGULATIONS, STANDARDS AND FEDERAL AND STATE PREVAILING WAGE
All work activities performed in association with this request must be performed and completed for the Town in accordance with current Federal State and Local regulations. All services performed shall also conform to the latest OSHA standards and/or regulations.
11. INSURANCE
The successful proposer shall provide the Town Purchasing Agent with a Certificate of Insurance before work commences. The Town shall be named as an additional insured with Insurance Company licensed to write such insurance in Connecticut, against the following risks and in not less than the following amounts:
The Material Testing Firm shall be responsible for maintaining insurance coverage in force for the term of the contract of the kinds and adequate amounts to secure all the Material Testing Firm’s obligations under this contract with an insurance company(ies) with an AM Best Rating of A-VIII or better licensed to write such insurance in the State of Connecticut and acceptable to the HMSBC and the Town.
The insurer shall provide the HMSBC, and the Town with Certificates of Insurance signed by an authorized representative of the insurance company(ies) prior to the performance of this contract describing the coverage and providing that the insurer shall give the HMSBC and the Town written notice at least thirty (30) days in advance of any termination, expiration, or any and all changes in coverage. Such insurance or renewals or replacements thereof shall remain in force during the Material Testing Firm’ s responsibility under this contract.
a. The Material Testing Firm, at the Material Testing Firm’s own cost and expense, shall procure and maintain all insurances required and shall include the Town of Trumbull, the Trumbull Board of Education, and the HMSBC as additional insureds on all contracts, except Workers' Compensation and Professional Errors and Omissions coverage.
b. In order to facilitate this requirement for insurance, it is recommended that the Material Testing Firm forward a copy of these requirements to the Material Testing Firm’ s insurance representative(s).
2. SPECIFIC REQUIREMENTS
a. WORKERS' COMPENSATION INSURANCE
b. The Material Testing Firm shall provide statutory Workers' Compensation Insurance, including Employer's Liability with limits of:
| i. $ 1,000,000 | Each Accident |
| ii. $ 1,000,000 | Disease, Policy Limit |
| iii. $ 1,000,000 | Disease, Each Employee. |
c. COMMERCIAL GENERAL LIABILITY INSURANCE
i. The Material Testing Firm shall carry Commercial General Liability insurance. A per occurrence limit of at least $1,000,000 combined single limit bodily injury and property damage is required. The Aggregate limit will be not less than $2,000,000. Any deviations from the standard unendorsed form will be noted on the Certificate of Insurance.
d. BUSINESS AUTOMOBILE LIABILITY INSURANCE
i. The Material Testing Firm shall carry Business Automobile Liability Insurance. A per occurrence limit of $1,000,000 combined single limit bodily injury and property damage is required. "Any Auto" (symbol 1 or equivalent) is required. Any deviations from the standard unendorsed form will be noted on the Certificate of Insurance.
e. PROFESSIONAL LIABILITY INSURANCE
i. The Material Testing Firm shall carry Professional Liability Insurance in the amount of $1,000,000 per claim/aggregate basis prior to commencement of services on the project; coverage shall be maintained in effect continuously for a period of at least five (5) years after substantial completion of the project.
f. EXCESS UMBRELLA LIABILITY INSURANCE
i. The Material Testing Firm shall carry excess liability insurance in the amount of at least $2,000,000 overlaying employers’ liability, commercial general liability (including completed operations), and business automobile liability coverage.
The insurance policy must contain the additional provision wherein the company agrees that Thirty (30) days prior to termination, expiration, cancellation or reduction of the insurance afforded by this policy with respect to the contract involved, written notice will be served by registered mail to the Purchasing Agent, Town of Trumbull.
Additionally, the successful proposer (Contractor) shall provide adequate statutory Workmen’s Compensation Insurance for all labor employed on this project, and comprehensive General Public Liability Insurance (Coverage “B”)
a) SUBCONTRACTOR REQUIREMENTS The Material Testing Firm shall require that any subcontractor and/or independent contractor hired by the Material Testing Firm to carry enough insurance and to obtain Certificates of Insurance before subcontractors and/or independent contractors are permitted to begin work. All subcontractors if applicable, shall carry insurance equal to the amounts required of the Material Testing Firm. The Material Testing Firm shall require that the Town of Trumbull, the Trumbull Board of Education, and the HMSBC are listed as additional insureds on all subcontractor’s insurance before being permitted to begin work. The Material Testing Firm and all subcontractors and their insurers shall waive all rights of subrogation against the Town of Trumbull, the Trumbull Board of Education, and the HMSBC, and their officers, agents, servants, and employees for losses arising from work performed by each under the Contract established.
The insurance policy must contain the additional provision wherein the company agrees that Thirty (30) days prior to termination, expiration, cancellation or reduction of the insurance afforded by this policy with respect to the contract involved, written notice will be served by registered mail to the Purchasing Agent, Town of Trumbull.
Additionally, the successful proposer (Contractor) shall provide adequate statutory Workmen’s Compensation Insurance for all labor employed on this project, and comprehensive General Public Liability Insurance (Coverage “B”) The successful proposer (Contractor) and each Subcontractor agree that their insurance carriers waive subrogation against the Town, its agents or employees with respect to any loss covered by the Contractor’s and each Subcontractor’s insurance.
1. Professional Liability Insurance must be documented in the amount of $2,000,000.
2. General Liability Insurance. The Consultant, upon the submission of a proposal shall deliver to the Town of Trumbull proof of professional liability insurance in the sum of $1,000,000 (one million dollars) issued by a reputable insurance company. This insurance must be maintained throughout this engagement and proof thereof must be provided upon request.
12. CONFLICT OF INTEREST
Public officials shall be prohibited from receiving any town work procured through a Public Bid or bid waived process so as to avoid any appearance of impropriety or Conflict of interest; and public officials cannot circumvent the intent of this Ordinance by receiving town work through a bid waiver, as proscribed by the Trumbull Town Charter.
13. STATEMENT OF EXPERIENCE AND REFERENCES
Bidders shall complete and submit the “Statement of Qualifications” section of this request along with the References form. The Town and Engineering Department may make such investigations as necessary, and it deems appropriate to determine the qualifications of the proposer to perform the work required. If the Town is not satisfied that the proposer is properly qualified, the Town along with Engineering Department reserves the right to reject the proposal of said proposer.
14. AWARD AND AUTHORITY & PRICING
The Town, along with the input from the hired project consultants, will review all proposals and make recommendations to the HMSBC. The HMSBC will make the final decision as to appropriate proposal to award. The Purchasing Agent of the Town shall issue notification of award in writing along with a town Standard Contract, then a Purchase Order (PO).
15. PRICING
All lump sum fees and hourly rates quoted shall remain firm fixed for a period 90 days from the date of proposal opening.
16. SCOPE OF WORK
Materials testing and inspections as indicated on the accompanying Statement of Special Inspections Form (attached) as well as site materials testing.
17. QUALIFICATIONS and PROPOSAL
a) All forms in this package are required for submission.
b) Responding firms shall include copies of their certifications in their responses to illustrate their qualifications to perform these services.
c) The qualifications of the testing personnel must meet the requirements indicated on the Statement of Special Inspections. Provide copies of individual certifications for proposed personnel. Use of cross-certified personnel is desired for cost efficiencies.
d) Provide unit pricing and extended pricing as requested on the accompanying Pricing Proposal Bid Form. All hourly pricing shall be for on-site time only. Portal to portal pricing will not be accepted. A single technician with multiple certifications will perform inspections and tests as required at no additional cost.
e) No separate travel expense charges will be permitted. Ensure that the cost of travel is included in your unit prices.
f) Administration charges in addition to quoted charges will not be allowed.
g) A half day is defined as any portion of the day when the technician or inspector is on site from 0-4 hours. A full day is defined as any portion of the day when the technician is on site from 4-8 hours.
h) Overtime will be considered only when your technician or inspector is on this project site for more than eight hours in one day. Weekend days and federal holidays are also considered overtime. Weekday overtime and Saturdays can be charged up to one- and one-half times the straight time rate. Sunday and federal holidays can be charged up to two times the straight time rate. Non-federal holidays will be charged at straight time rates.
i) Provide a rate sheet for services not listed but believed by the respondent to be necessary.
18. SCHEDULE
| The following is the anticipated schedule for this scope of work. | ||||
| 1. | Issue Solicitation | April 24, 2026 | ||
| 2. | Last day to submit an RFI | May 8, 2026 | ||
| 3. | RFQ/P due to the Town | May 15, 2026 | ||
| 4. | Firm Selection | May 26, 2026 | ||
| 6. | Anticipated Start of Construction | July 6, 2026 | ||
| 7. | Anticipated Completion of Construction | December 2028 |
19. AVAILABLE INFORMATION
The Hillcrest Middle School project plans, specifications, and overall Project Schedule will be available upon request for qualified respondents by emailing Robert Tencza at robert.tencza@arcadis.com.
Required Forms
NEW SCHOOL CONSTRUCTION PROJECT
MATERIAL TESTING SERVICES
REQUEST FOR QUALIFICATIONS / REQUEST FOR PROPOSAL
RFQ-P: 6570 DUE: May 15, 2026, AT 2:00PM
REQUEST FOR PROPOSAL FORM
THIS FORM MUST BE SIGNED AND SUBMITTED WITH PROPOSAL.
Company Name & Address: __________________________________________________
ADDENDA
The following Addenda have been received. The modifications to the Bid Documents noted therein have been considered and all costs thereto are included in the Base Bid.
Addenda # _________, ___________, __________, ___________, ____________
INSTRUCTIONS: The above signed, attesting to be a duly authorized representative of the Material Testing firm submitting this Proposal and Bid Form, having familiarized themself with the proposed projects and the Scope of Work contained herein affecting the cost of the work, hereby proposes to furnish the Town of Trumbull / Hillcrest Middle School Building Committee with all supervision, technical personnel, labor, materials, equipment, tools, appurtenances and services required to perform and satisfactorily complete the work specified for the rates as indicated below.
HOURLY RATES: Attach to this Proposal Form the hourly rates for all staff in your Firm, indicated by Title, that your Firm would charge for any additional Material Testing services as may be requested by the Hillcrest Middle School Building Committee that were not included in the Contract established between the Town of Trumbull and your Firm if selected.
Company Name by (Signature)
| _______________________________ | _____________________________________ | |
| Address | Print Name (Duly Authorized Representative) |
| _______________________________ | _____________________________________ | |
| City, State, Zip | Title |
| _______________________________ | ______________________________________ | |
| Date | Telephone/Fax |
| _______________________________ | ______________________________________ | |
| Cell Phone/ Alt.Contact Number |
NEW SCHOOL CONSTRUCTION PROJECT
MATERIAL TESTING SERVICES
REQUEST FOR QUALIFICATIONS / REQUEST FOR PROPOSAL
RFQ-P: 6570 DUE: May 15, 2026, AT 2:00PM
EXPERIENCE
Schedule A: Prior Experience Similar projects (Add Additional Pages as Needed)
| Project |
| Owner |
| Design |
Professional
| Contract Price |
| Date of Completion |
Schedule B: Current Workload (Add Additional Pages as Needed)
| Project |
| Owner |
| Design |
Professional
| Contract Price |
| Percent Completed |
| Date of Scheduled Completion |
NEW SCHOOL CONSTRUCTION PROJECT
MATERIAL TESTING SERVICES
REQUEST FOR QUALIFICATIONS / REQUEST FOR PROPOSAL
RFQ-P: 6570 DUE: May 15, 2026, AT 2:00PM REFERENCES MUST Be Submitted with Proposal (To be submitted with qualifications – attach additional pages as necessary) List references for similar services provided for at least five (5) clients in the past five (5) years (attach any other client references if desired). PLEASE NOTE IT IS THE TOWN’S INTENT TO COMMUNICATE WITH THE REFERENCES LISTED HEREIN.
CLIENT 1:
Organization Name: __________________________________________________________ Contact Name:______________________________________________________________ Phone: _________________________ Service Dates: _____________________________________________________ Project(s): _________________________________________________________________
CLIENT 2:
Organization Name: __________________________________________________________ Contact Name:______________________________________________________________ Phone: _________________________ Service Dates: _____________________________________________________ Project(s): _________________________________________________________________
CLIENT 3:
Organization Name: __________________________________________________________ Contact Name:______________________________________________________________ Phone: _________________________ Service Dates: _____________________________________________________ Project(s): _________________________________________________________________
CLIENT 4:
Organization Name: __________________________________________________________ Contact Name:______________________________________________________________ Phone: _________________________ Service Dates: _____________________________________________________ Project(s): _________________________________________________________________
CLIENT 5:
Organization Name: __________________________________________________________ Contact Name:______________________________________________________________ Phone: _________________________ Service Dates: _____________________________________________________ Project(s): _________________________________________________________________ TOWN of TRUMBULL
BOARD OF EDUCATION
NEW SCHOOL CONSTRUCTION PROJECT
MATERIAL TESTING SERVICES
REQUEST FOR QUALIFICATIONS / REQUEST FOR PROPOSAL
RFQ-P: 6570 DUE: May 15, 2026, AT 2:00PM
NON-COLLUSION AFFIDAVIT
MUST be Submitted with Proposal
State of SS: ______________ County of , being first duly sworn,
1. He is of _________________________ The bidder that has submitted the attached bid.
2. He is fully informed respecting the preparation and contents of the attached Bid and of all pertinent circumstances respecting such bid.
3. Such price is genuine and is not a collusive or sham bid.
4. Neither the said Bidder nor any of its officers, partners, owners, agents, representatives, employees or parties in interest, including this affiant, has in any way colluded, conspired, connived or agreed, directly or indirectly with any other Bidder, firms or person to submit a collusive or sham Bid in connection with the Contract for which the Contract, or has in any manner, directly or indirectly, sought by agreement or collusion or communications or conference with any other Bidder, firm or person to fix the proceeds or prices in the attached Bid or of any other Bidder, or to fix any overhead, profit or cost element of the Bid price or the Bid price of any bidder, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantage, against the Town of Trumbull, (Owner) or any person interested in the proposed Contract; and
5. The price or prices quoted in the attached Bid are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the Bidder or any of its agents, representatives, owners, employees, or parties in interest including this affiant.
Signed Title Subscribed and sworn to before me this day of , 2026.
Title
My Commission Expires
END of RFQ/P Material Testing Services Hillcrest Middle School Trumbull, CT image1.emf