About this file
This Request for Qualifications (RFQ) is issued by the City of LaFayette, Georgia, seeking a qualified consultant or consultant team to develop a Comprehensive Safety Action Plan aligned with the Safe Streets & Roads for All (SS4A) Program. The consultant will be responsible for a comprehensive scope of work including project management, state of practice and data collection, public participation and needs assessment, crash data analysis spanning a minimum five-year period, and preparation of draft and final comprehensive safety action plans with associated outreach materials. The RFQ submission deadline is November 3, 2025, at 3:00 p.m., with responses to be delivered to the City Manager at 207 S Duke Street, LaFayette, GA 30728, in person or by mail. The selection process includes evaluation of responses by the City, with no pre-proposal conference scheduled; however, consultants may submit written questions to ctracy@lafga.org by October 14, 2025, at 12:00 p.m., with answers posted by October 16, 2025. The notice of preferred consultant is anticipated November 4, 2025, with contract award by November 10, 2025, and project initiation on November 13, 2025. The consultant must complete all work within ten months of the notice to proceed, with the final Comprehensive Safety Action Plan due by October 30, 2026, though firms capable of completion prior to May 1, 2026, will receive additional consideration.
The contract will be structured as cost-plus-fixed-fee with a contract maximum, with monthly reimbursement based on documented work task completion. Consultants must provide an hourly rate for services and estimated total project costs based on prior experience. Evaluation criteria are weighted as follows: understanding of project purpose (25 percent), capability and qualifications of staff (25 percent), proposed schedule (30 percent), and cost (20 percent). Responses must include resumes for all key personnel and sub-consultants, three recently completed related projects from the past five years with client references, an organizational chart, a detailed project schedule with milestones and deliverables, and any proposed innovative or supplemental methods. The consultant must comply with FHWA Order 4470.1A regarding certification of indirect costs and provide a Certificate of Insurance prior to commencing work. All work products shall be delivered in Microsoft Word and Adobe PDF formats, with monthly progress reports and invoices required for payment processing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| questions.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF LAFAYETTE, GEORGIA
MAYOR AND COUNCIL
REQUEST FOR QUALIFICATIONS
FOR
ENGINEERING SERVICES TO ESTABLISH A
COMPREHENSIVE SAFETY ACTION PLAN
Issue Date: October 1, 2025 Submission Deadline: November 3, 2025 – 3:00 p.m.
The City of LaFayette is hereby issuing this Request for Qualifications (RFQ) to firms that have the capability and interest in undertaking and performing the scope of work described below.
Each firm is officially a consultant. Each consultant must submit a package containing an original, four (4) copies, and one (1) digital copy of its response labeled “Sealed RFQ for LaFayette SS4A Comprehensive Safety Action Plan” to the City of LaFayette no later than 3:00pm on November 3, 2025 to David Hamilton, City Manager, 207 S Duke St, LaFayette, GA 30728.
Responses may be submitted in person or by mail. All responses will be logged in and date and time stamped. Any response package that is received after the date and specified time will be logged and date and time stamped as “late” and returned unopened to the consultant. Responses shall include:
1. Name of the Prime and sub-consultants that will comprise the team. Identify the Executive Officer of each company.
2. Identify the proposed Project Manager for the team who will be the primary point of contact for the City of LaFayette (City) for day-to-day operations.
3. List the key personnel who will participate in performing the scope of work. Provide a resume for each listed team member; including sub-consultants and key personnel who will be completing a portion of the scope of work. Please describe previous engagements where the sub-consultants have worked with the prime consultant.
4. Provide an organizational chart depicting the relationships between the team members and agencies.
5. Provide three (3) recently completed (related & relevant) projects within the last five (5) years that demonstrate the abilities and skills of the team members to carry out the tasks identified in the scope of work. Be sure to include a key client contact with their current daytime phone number.
6. Provide a proposed list of required tasks and milestones to address the study goals identified in the scope of work.
7. Provide a proposed project schedule that includes key tasks, duration, milestones and deliverables that will complete the scope of work within a ten (10) month timeframe.
8. Provide a flow chart depicting key task activities and sequence.
9. Any innovative or supplemental methods proposed by the consultant that would provide value to the City of LaFayette.
**An authorized officer of the prime consultant firm shall sign all proposal submissions** RFQ SELECTION PROCESS
All responses received shall be subject to an evaluation by the city. The city reserves the right to reject any and all proposals in whole or in part.
The selection of the successful consultant will be made solely by the city. There will be no pre- proposal conference conducted by the city. However, the consultant may ask questions to discuss the contents of this RFQ and the expectation of the city related to this work effort. These questions must be submitted via email to Clay Tracy, Project Manager, at ctracy@lafga.org; questions and answers received will be provided to all participants via the GA procurement website.
If in the judgment of the city, changes in the contents of the RFQ are required, an addendum will be issued by the city. Any addendum that may be issued will be posted on the GA Procurement website.
Due to potential conflict of interest, no consultant or a person representing a consultant may arrange or meet with the individual members of the city to discuss any items or matters related to this RFQ during the period between the date of the release of this RFQ and the date the city makes the decision selecting the successful consultant.
The city shall rank each proposal against the stated criteria. The city reserves the right to contact a firm to obtain written clarification of information submitted and to contact references to obtain information regarding performance reliability and integrity.
All questions or requests for clarifications regarding this RFQ shall be submitted by email or in writing no later than 12:00 p.m. October 14, 2025. All questions submitted and their answers will be provided via an addendum posted on the GA procurement website the following day. No telephone inquiries shall be accepted.
RFQ EVALUATION CRITERIA
The criteria and the percentage of their importance in making the selection are as follows:
Understanding the purpose: 25 Percent
A determination will be made of the consultant’s understanding of the project purpose and goals as presented in the RFQ. Evaluation will be based on the data presented in the consultant’s response, and the approach and allocation of time on specific tasks. consultants should feel free to suggest other requirements and problems that may have been overlooked.
Capability and qualifications: 25 Percent
The ability of a prospective consultant and firm (years experience) will be evaluated under the terms of the RFQ, relative to having staff with the qualifications needed to successfully complete the project. Qualifications of professional personnel assigned to the project, as specified in the response including Sub- consultants, will be measured by both education and experience, and with particular reference to experience on similar projects and an ability to work together as evidenced from previous projects. The consultant’s professional and project staff that work on the project must be the same staff that are identified in the response. Include a minimum of 3 references.
Schedule: 30 Percent
The prospective consultant will be evaluated on their ability to follow a schedule that will successfully complete the project within the specified time frame.
Based on the evaluations of the submitted responses, the city will select the top-ranked firm and negotiations will begin immediately to finalize the scope of work, personnel, hours, hourly rates, use of sub-consultants, and other direct costs that will be required to complete the agreement between the city and the selected firm. If an agreement cannot be reached with the top-ranked firm, the city will identify the next most responsive and qualified firm, and the negotiation phase will be repeated. This process will continue until an agreement is reached with a qualified firm that can provide the required services. The city reserves the right to reject any and all proposals received, and in all cases the city will be the sole judge as to whether a consultant’s response has or has not satisfactorily met the requirements of this RFQ.
Cost: 20 Percent
Please provide an hourly rate for services and an estimated cost based on your prior experience.
TYPE OF CONTRACT
Upon selection, the City of LaFayette will propose a contract to the selected consultant for review. The contract is for a cost plus fixed fee with a contract maximum. Reimbursement will be made on a periodic schedule based on documentation of work tasks completed. The city will review, and if appropriate, approve payment of all invoices submitted under the contract.
Consultants and sub-consultants shall comply with FHWA Order 4470.1A “Certification of Indirect Costs” in accordance with FAR.
INSURANCE
Any consultant contracted by the City shall be required to provide a Certificate of Insurance on acceptable forms with limits acceptable to and approved by the city prior to commencing work.
PROPOSED TIMEFRAME
| Advertisement of RFQ |
| October 1, 2025 |
| Deadline for submitting written questions |
| October 14, 2025, by 12:00 pm EST |
| Deadline for posting answers to website |
| October 16 2025, by 5:00 pm EST |
| Responses Due |
| October 16, 2025, by 5:00 pm EST |
| Notice of preferred consultant |
| November 4, 2025 |
| Contract development and award |
| November 10, 2025 |
| Project Initiation |
| November 13, 2025 |
| Draft Comprehensive Safety Action Plan |
| November 2026 |
| Final Comprehensive Safety Action Plan |
| October 2026 *PLEASE SEE THE NOTE IN THE SCHEDULING SECTION BELOW |
SCOPE OF WORK
COMPREHENSIVE SAFETY ACTION PLAN
PURPOSE
The City of LaFayette, Georgia, is seeking a qualified consultant to assist staff in the development of a Comprehensive Safety Action Plan consistent with the objectives of the Safe Streets & Roads for All or SS4A Program.
The City of LaFayette (City) is committed to promoting a safe, efficient, accessible, and reliable transportation network for all users of the transportation system. As a city with a heavily utilized road network; multi-modal needs; and a robust development environment – elevating and incorporating well thought out safety strategies and actions is viewed as critical to the continued economic vitality of the city.
The central goal of this work effort is to develop a comprehensive safety action plan that will thoroughly take account of the full range of variables that substantially influence both operational and safety outcomes across the city – resulting in a grounded plan of appropriate and implementable safety strategies.
This RFQ provides the interested consultant / consultant team, hereafter referred to as “consultant,” with specific information concerning the goals of this work effort. This RFQ provides sufficient information to enable the consultant to prepare and submit a proposal for consideration by the City.
WORK STATEMENT: PLAN GOALS
1. Development of a comprehensive safety action plan that will identify and document the range of variables that influence safety outcomes for all users of the transportation system.
2. Examine city trends for traffic safety as well as the principal risk considerations across the city (i.e., location; concentration; proximity to schools / parks / developments of regional impact, etc.).
3. Ensure that solutions and issues are coordinated with neighboring jurisdictions.
4. Review city plans and policies for how they reflect and prioritize safety in planning design; and identify effective, grounded and area appropriate recommendations to minimize risk.
5. Provide a comprehensive course of action to incorporate a “safe system approach”.
6. Preparation and delivery of the final work product is expected to address federal and state regulations, transportation performance management requirements, as well as SS4A programmatic requirements.
SERVICES TO BE PROVIDED / SCOPE OF WORK
City of LaFayette seeks a transportation consultant to undertake the following scope of work. Task 1: Project Management Plan:
The consultant will:
· Develop a project management and public engagement plan within 10 days of the notice to proceed.
· Submit monthly progress reports covering performed work; upcoming tasks / milestones; status of scope / schedule and any issues to be aware of.
· Prepare any necessary information required for reporting to the FHWA.
· Facilitate and participate in periodic meetings of the City Council and Stakeholder Committee.
Task 2: State of Practice & Data Collection / Review:
The consultant will:
· Review FHWA / GDOT guidelines, policies, and regulations related to the development of Comprehensive Safety Action Plans; and the “Safe Systems Approach,” as well as applicable Transportation Performance Management requirements.
· Review local and statewide plans, studies and initiatives particularly relevant to LaFayette given current and future growth projections; specifically, this shall include an assessment of current policies, guidelines and standards utilized across the city.
Task 3: Public Participation & Identifying Needs:
The consultant will:
· Develop and implement a public outreach effort to ensure broad based access and input from across the planning area; an important component of this process will include identification and engagement for those disproportionately impacted by traffic risks and / or traditionally underserved by safety planning efforts.
· Complete an assessment of the feedback received (i.e., safety concerns; locations of interest, etc.) and how the feedback will be incorporated into the Safety Action Plan.
Task 4: Crash Data Analysis:
The consultant will:
· Collect and review crash, traffic, and roadway data for at least the most recent 5-year period to understand critical safety issues and provide insight into trends, causes, and patterns of transportation safety throughout the city.
· Analyze existing conditions and historical trends that provide a baseline level of crashes. This should include an analysis of the crash locations; the severity of the crash; as well as crash type by transportation system user (vehicle; pedestrian; motorcycle; bicyclist, etc.).
· Summarize key crash characteristics and determine the most likely contributing factors linking crash activity with applicable roadway characteristics such as speed limits, intersection controls, streetlights, pedestrian or railroad crossings, etc. in order to develop an appropriate understanding of the patterns, trends and opportunities for implementable strategies.
· Develop a High Injury Network of the key intersections and roadway segments in LaFayette.
Task 5: Prepare Draft & Final Plan; Present Final Report The consultant will adhere to:
· Leadership Commitment and Goal Setting: An official public commitment to an eventual goal of zero roadway fatalities and serious injuries.
· Planning Structure: A committee, task force, or similar body charged with oversight of the Action Plan development, implementation, and monitoring.
· Safety Analysis: Analysis of existing conditions and historical trends that provides a
· baseline level of crashes involving fatalities and serious injuries across the MPO Planning Area.
· Engagement and Collaboration: Robust engagement with the public and relevant stakeholders, including the private sector and community groups, that allows for both community representation and feedback.
· Policy and Process Changes: Assessment of current policies, plans, guidelines, and/or standards to identify opportunities to improve processes and prioritize transportation safety.
· Strategy and Project Selections: Identification of a comprehensive set of projects and strategies, shaped by data, the best available evidence and noteworthy practices, as well as stakeholder input and equity considerations, that will address the safety problems described in the Action Plan.
· Progress and Transparency: Method to measure progress over time after an Action Plan is developed or updated, including outcome data.
Task 6 - Safety Action Plan Summary Sheet / Outreach Materials. The consultant will submit:
· A one-to-two-page document summarizing the Safety Action Plan contents and making all City communities aware of the SS4A program and their eligibility to apply for grant funding.
SCHEDULE
The consultant must agree to begin work upon issuance of a notice to proceed by City and to complete this work within ten (10) months (or by October 30, 2026) of the date of notice to proceed. Additional consideration will be given to firms that can complete the project prior to May 1, 2026. The work shall be guided by a detailed project management plan, prepared by the consultant and furnished to the city within one week of receipt of notice to proceed, and approved by the city. Monthly payments for the work shall be made to the consultant with the consultant providing a detailed invoice and progress report.
PROJECT MANAGEMENT
The consultant will submit monthly invoices accompanied by supporting documentation including monthly progress reports to the City Manager outlining status of work elements; any delays or concerns; and schedule updates. Progress report briefings will be held during this project. The consultant shall be responsible for the logistics for these meetings.
MEETINGS
Stakeholder meetings shall be conducted by the consultant during the course of this project. The consultant shall be responsible for the logistics for these meetings. The specific number of meetings shall be negotiated between the consultant and the City Manager.
PRESENTATIONS
One (1) technical presentation (PowerPoint) shall be made to City Council as specified by the City Manager, following the completion of the Plan.
SPECIFICATIONS FOR WORK
All documentation shall be in Microsoft Word or later and Adobe Portable Document Format (PDF). Any programming source codes, form designs, raw source database (in dBase III format, with field coding definition sheet) and other ancillary files shall be transferred to the City in addition to the executable applications at the closure of each task or any moment specified by the City Manager.
DELIVERABLES
The consultant will provide digital copies of the draft and final Comprehensive Safety Action Plan. Draft work tasks / chapters will be submitted as prepared throughout the schedule. The final draft of the completed Plan must be submitted by October 30, 2026.