This is Addendum No. 1 to a Request for Qualifications (RFQ) issued by the Georgia Department of Transportation (GDOT) on May 20, 2026. The addendum modifies RFQ 484-061526 for Special Drainage Studies across Districts 3, 6, and 7. The contract type is IDIQ (Indefinite Delivery/Indefinite Quantity), with qualifications due by June 15, 2026. The addendum clarifies cover page requirements, specifying that respondents should list district information rather than counties, and confirms that no description needs to be displayed on the cover page despite earlier instructions. All addendum content, including questions and answers, becomes part of the original RFQ package and must be incorporated into proposals.
The addendum addresses three key clarifications from the question and answer period. GDOT confirmed that districts rather than counties should appear on the cover page, and established that evaluation forms from other owner agencies are acceptable alternatives to the Legacy Evaluation Form for documenting referenced project performance. A signed acknowledgment of the addendum must be attached to Phase I submissions. The complete RFQ cover page and Exhibit I-1 have been revised and replaced in their entirety, with the addendum emphasizing that failure to adhere to the specified changes may result in disqualification of submissions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ_484_061526 Special Drainage Studies.pdf | ||
| Legacy Evaluation Form.xlsx | XLSX spreadsheet | |
| LAP Evaluation Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 1
ISSUE DATE: 5/20/2026
This Addendum shall become and form a part of the RFQ for:
RFQ 484-061526 - Special Drainage Studies for Districts 3,6 and 7
NOTE: PLEASE REVIEW CAREFULLY! THERE MAYBE CHANGES TO THE INFORMATION TO BE PROVIDED.
FAILURE TO ADHERE TO ANY CHANGES ADDRESSED IN THIS ADDENDUM MAY RESULT IN
DISQUALIFICATION.
In the event of a conflict between previously released information and the information contained herein, the latter shall control.
NOTE: A signed acknowledgment of this addendum (this page) MUST be attached to your SUBMITTAL for Phase I.
Firm Name
Signature Date
Typed Name and Title
Georgia Department of Transportation (GDOT)
Office of Procurement Engineering and Design Services
One Georgia Center 600 West Peachtree Street, NW
19th Floor Atlanta, Georgia 30308
This Addendum, including all questions and answers, shall become and form a part of the original RFQ package and shall be taken into account when preparing your proposal.
The purpose of this addendum is to provide the answers to the written questions received during the question and answer period of the RFQ Phase as follows:
I. Written Questions (Q) and Answers (A):
Q1: On page 5 of the RFP it states that the cover page must include a description; however, on page 15 there is no description listed. Can GDOT confirm that there is no description to be displayed on the cover page for submittals of this project?
A1: See Addendum below.
Q2: On page 5 of the RFP it states that the cover page must include county(ies); however on page 15 there is no counties listed. Can GDOT confirm that instead of counties respondents should list districts as shown on page 15?
A2: Yes, district information should be listed on the cover page as referenced on page 15 of the RFQ.
Q3: Some owner agencies on projects we may reference have policies that do not allow them to complete outside evaluation templates, including the Legacy Evaluation Form. Those agencies will only provide their own standard internal project evaluation forms. Would GDOT accept an owner agency’s standard completed evaluation form in lieu of the Legacy Evaluation Form in those situations? If not, please advise whether there is an alternate acceptable method of documenting project performance for those referenced projects.
A3. Yes, GDOT will accept evaluation forms from other agencies.
Date Posted: 5/11/2026
II. Addendum Revisions:
RFQ Cover Page is deletled in its entirety and replaced with the following:
Request for Qualifications
To Provide
Special Drainage Studies for Districts 3, 6, and 7
RFQ-484-061526
Qualifications Due: June 15, 2026
Georgia Department of Transportation
One Georgia Center 600 West Peachtree Street, NW
Atlanta, Georgia 30308
v. 4-2026 IDIQ Single
Exhibit I-1, Contract I, 1-4 is deleted in its entirety and replaced with the following:
EXHIBIT I-1
1. Contract Type: IDIQ
2. PI Number(s): N/A
3. District(s): 3, 6 and 7
4. Description: Special Drainage Studies
| NOTE: PLEASE REVIEW CAREFULLY! THERE MAYBE CHANGES TO THE INFORMATION TO BE PROVIDED. FAILURE TO ADHERE TO ANY CHANGES ADDRESSED IN THIS ADDENDUM MAY RESULT IN DISQUALIFICATION. |
| Request for Qualifications |
File details come from the government source that posted it. Updated .