This is Addendum 2 to RFQ 426528, issued by the City of Oakland's Public Works Department, Sewer Division, regarding wastewater lift station repair services for thirteen lift stations throughout Oakland, California. The addendum addresses critical operational requirements and contractor responsibilities for on-call emergency response services. The City requires 24-hour availability with a mandatory one-hour response time for after-hours, weekend, and emergency calls, with qualified personnel required to physically arrive at lift stations within one hour of the City placing the call. The awarded contractor must deploy dedicated technicians for all repair requests and maintain sufficient staffing to respond to multiple simultaneous emergencies at different lift station locations within the one-hour timeframe. There is no secondary or backup contractor; the City relies solely on the primary awarded contractor to fulfill all service requests without exception throughout the contract term.

The addendum clarifies that an isolated inability to accept or respond to a service call constitutes a contractual violation, with no cure opportunity or corrective action process outlined. The contractor bears responsibility for compliance even when circumstances such as traffic congestion, severe weather, or road closures delay physical arrival, though the City does not dictate repair methods. The contractor is required to have a written safety protocol in place and may stabilize conditions and coordinate additional personnel, equipment, or subcontractors as needed when conditions make immediate repair unsafe or impractical. The original RFQ solicitation is for a two-year contract period with an option to extend for one additional one-year period, with proposals to include hourly labor rates, overtime rates, and miscellaneous charges with detailed breakdowns of all costs reflecting current market pricing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ: 426528 WASTEWATER LIFT STATION REPAIR SERVICES: ADDENDUM 2

1. If the awarded contractor is temporarily unable to accept a particular on-call service request, what procedure does the City expect the contractor to follow? For example, this could occur because the contractor is already responding to another City emergency, has an unexpected staffing issue, experiences an equipment failure, or encounters another unusual circumstance that temporarily prevents an immediate response.

Once the contractor is awarded a particular on-call service request, the contract is required to deploy dedicated technician for the repair.

2. Does the City maintain a secondary or backup contractor/vendor that may be contacted if the primary awarded contractor is already committed to another emergency or is temporarily unable to service a particular request?

No, the City will not maintain a secondary contractor or backup contractor/vendor.

3. Would an isolated inability to accept or respond to a particular service call be considered a contractual violation or default? If so, please clarify any applicable corrective-action process, cure opportunity, penalties, or other consequences.

Yes, the contractor must deploy dedicated staff to perform the repair.

4. Is the City’s expectation that the awarded contractor make reasonable good-faith efforts to accept and service every call, or is acceptance of every individual service request mandatory without exception throughout the contract term?

Yes, the contractor must deploy dedicated staff to perform the repair.

5. Addendum 1 states that the City requires 24-hour availability with a one-hour response time for after-hours, weekend, and emergency calls. Please clarify exactly how the one-hour response period is measured. Does the requirement mean:

o the contractor must acknowledge the City’s request, accept the call, and have appropriate personnel dispatched and en route within one hour; or

Yes, the contactor must deploy dedicated staff to perform the repair.

o qualified personnel must physically arrive at the lift station within one hour of the City placing the call?

Yes, qualified personnel must physically arrive at the lift station with one hour.

6. If physical arrival within one hour is required, when does the one-hour period begin? For example, is it measured from the City’s initial phone call, from the time the contractor acknowledges and accepts the request, or from the point at which sufficient site information and authorization have been provided to permit dispatch?

Qualified personnel must physically arrive at the lift station within one hour.

7. If the one-hour requirement refers to acknowledgment and mobilization rather than physical arrival, is there a separate expected or maximum timeframe for arrival at the site? We understand that actual travel time may vary depending on the lift-station location, traffic conditions, time of day, and availability of appropriately qualified personnel.

Qualified personnel must physically arrive at the lift station within one hour.

8. If personnel are dispatched within the required response period but circumstances outside the contractor’s reasonable control delay physical arrival, such as significant traffic congestion, road closures, severe weather, restricted site access, or another active

City emergency, how would the City evaluate compliance with the response requirement?

Qualified personnel must physically arrive at the lift stations within one hour.

9. If two or more City lift-station emergencies occur at approximately the same time, is the awarded contractor expected to maintain sufficient staffing to physically respond to multiple locations simultaneously? Or would the City prioritize the service calls and permit the contractor to respond sequentially based on urgency?

Qualified personnel must physically arrive at each of the lift stations within one hour.

10. In a situation where the contractor responds promptly but determines that conditions make it unsafe or impractical to immediately complete the repair, is the City’s expectation that the contractor stabilize the condition where reasonably possible, communicate the findings to the City, and then coordinate the necessary personnel, equipment, materials, or subcontractors to complete the work?

The City does not dictate on how the contractor determines the method for the repairs.

The contractor would be required to have a written safety protocol in place.