RFQ 01-SA-SS-2026-005 - SSSP ADMIN CEILING - ADDENDUM 1 - QUESTIONS RESPONSE.pdf
PDF 207 KB Posted
- Solicitation number
- 2139408
- Issued by
- Saratoga County, New York
About this file
This document is an Addendum 1 - Questions Response issued by the New York State Office of Parks, Recreation and Historic Preservation (OPRHP) for RFQ 01-SA-SS-2026-005 regarding abatement and repair work to the plaster ceiling in the Administration Building at Saratoga Spa State Park. The project scope comprises three primary tasks: removal of six ceiling-mounted electrical fixtures (two ceiling fans and four 8-foot linear fluorescent lights) with proper NEC-compliant termination and coverage; abatement of 441 square feet of 12-inch by 12-inch acoustic ceiling tile and trace-asbestos-containing adhesive glue dabs; and repair, patching, and skimcoating of 441 square feet of plaster ceiling with lead-based paint. The ceiling area measures approximately 21 feet by 21 feet at 12 feet above finish floor. Questions were due October 9, 2026, with quotes due October 20, 2026. Work must be completed within 30 days after Purchase Order approval.
Quotes must be valid for 90 days with all ancillary costs included in bid prices, and award will be made to the responsive, responsible, and qualified bidder offering the lowest price. Prime contractors or subcontractors must hold EPA Lead Renovation, Repair & Painting (RRP) Certification and New York State Licensed Asbestos Abatement Contractor Certification. Prevailing wage requirements apply under New York Labor Law Article 8/9 per NYS DOL Prevailing Wage Schedule (PRC Number 2026026011). OPRHP requests good faith efforts to include MWBE/SDVOB vendors where subcontracting is available, with documented evidence of outreach required if requested. No incumbent has held an identical or substantially similar contract within the past five years. Commercial General Liability insurance of $1,000,000 per occurrence and $2,000,000 aggregate, Comprehensive Business Automobile Liability with $1,000,000 combined single limits, and Workers' Compensation/Disability Benefits Insurance are required. Hazardous-materials compliance includes OSHA 1926.1101 and Construction Lead Standard 29 CFR 1926.62, with air monitoring per NIOSH 7300 Method or equivalent objective data.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 01-SA-SS-2026-005 - SSSP ADMIN CEILING.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OPRHP-Pre-Bid Addendum Page 1 of 1
ADDENDUM
PROJECT: RFQ01-SA-SS-2026-005
Administration Building Ceiling
Saratoga Spa State Park
ADDENDUM NO: 1
ISSUE DATE: October 13, 2026
ALL BIDDERS SUBMITTING A BID FOR THE ABOVE-NAMED PROJECT SHALL TAKE NOTE OF THE FOLLOWING CHANGES, ADDITIONS, INTERPRETATIONS, CLARIFICATIONS, ETC. IN CONNECTION WITH THE DRAWINGS AND SPECIFICATIONS AND OTHER BID DOCUMENTS. THE FOLLOWING INSTRUCTIONS HAVE PRECEDENCE OVER ANYTHING CONTRARILY
SHOWN ON THE DRAWINGS OR DESCRIBED IN THE SPECIFICATION DOCUMENTS, AND ALL SUCH INFORMATION SHALL
BE TAKEN INTO CONSIDERATION AND BE INCLUDED IN THE BIDDERS BID AMOUNT.
SUMMARY OF ADDENDUM ITEMS
Contractor Questions and Answers:
• Question #1: There are other hazardous materials identified in the hazardous materials survey, ATTACHMENT 2, e.g.
vinyl asbestos tile. Are these being abated in this project as well?
o Answer #1: No, only the identified hazardous materials related to the ceiling work are being abated.
• Question #2: Can subcontractors be used for any portion of the work?
o Answer #2: Yes, any portion of the work may be subcontracted, however all contractors, prime and sub, working on the job must be registered in the New York State Department of Labor Public Work Contractor and Subcontractor Registry.
• Question #3: Is there an area next to the building for staging?
o Answer #3: Yes, there is an approximately 15’ x 45’ lawn area directly adjacent to the building that may be used for staging. Any disturbance or damage to the lawn resulting from its use shall be restored. This lawn area is next to a small parking lot, through which it may be accessed.
• Question #4: What do the photos in ATTACHMENT 5 show in the space with the green walls?
o Answer #4: These photos represent another area where similar work was previously done. The purpose of including these photos is to show the likely condition of the underlying plaster ceiling once the adhered acoustic ceiling tiles are abated.
File details come from the government source that posted it. Updated .